To get a building permit in Harrison County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Harrison County Plan Commission office in Corydon issues improvement location permits, which serve as building permits, inspects construction and issues certificates of occupancy, with applications filed through its online permit portal.

Authority: Harrison County Plan CommissionFees: Ordinance 2025-32Phone: 812-738-8927
New house
$200 + 10¢/sq ftPlan review included
Review time
5–7 business daysComplete applications
Driveway permit
No feeCounty Highway Dept.
Hours
8 a.m.–4:30 p.m.245 Atwood St. NE, Suite 215

In Harrison County, the Harrison County Plan Commission office at 245 Atwood Street NE, Suite 215, Corydon (812-738-8927) issues improvement location permits, which the county treats as building permits, and its inspectors check the work and issue certificates of occupancy; Chris Kincade is the Administrator. Applications go through the county’s iWorQ permit portal and take five to seven business days to review once complete. Under Ordinance 2025-32, a new house costs $200 plus 10 cents a square foot, plan review included. The Town of Corydon issues its own permit for work inside the town.

What requires a building permit in Harrison County?

The county zoning ordinance is short and broad on this point: no construction, alterations or additions of any kind may begin without an improvement location permit (ILP) issued by the Plan Commission’s administrator, and no new or altered building may be occupied until a certificate of occupancy is issued. The fee ordinance shows the work the office permits and inspects.

Residential

  • New single-family and two-family dwellings
  • Additions, decks, porches and patios
  • Accessory buildings and barns
  • Manufactured, mobile and modular homes (an ILP is required before a home is placed)
  • Above-ground and in-ground pools
  • Electrical work, HVAC systems and plumbing

Commercial and land use

  • New commercial, multi-family, institutional and industrial buildings, additions and temporary structures
  • Tenant finishes and general build-outs
  • Commercial demolition (an asbestos survey is required)
  • Commercial electrical, HVAC, hood suppression and plumbing work
  • New cell towers and co-locations; replacing equipment needs no permit
  • Permanent and temporary signs

Applications for rezoning, variances, special exceptions, plats and development plans go through the Plan Commission’s separate planning and zoning portal.

What Harrison County decides and what the state holds

The county writes its own zoning, subdivision and sign ordinances, its permit fees and its floodplain rules, and runs its own inspections. State rules decide when a building needs the state Construction Design Release: the county’s checklist says commercial additions, renovations and new structures need one, and the zoning ordinance lets a commercial, industrial or institutional ILP rest on either that release or an engineer’s certificate of compliance with the district’s performance standards.

Harrison County building department: who handles permitting

The Plan Commission office processes rezonings, subdivisions, variances and special exceptions, and also issues ILPs, inspects buildings, issues certificates of occupancy, assigns addresses and issues sign permits. Building inspectors are assigned by area of the county, north and south of Corydon.

Short on time to read all of this?

Get a free quote →
Harrison County permit contacts
OfficeContact
Plan Commission (permits, inspections, zoning)245 Atwood Street NE, Suite 215, Corydon, IN 47112; 812-738-8927, fax 812-738-8939; Monday to Friday 8 a.m. to 4:30 p.m.
Health Department (septic, site approval)241 Atwood Street, Suite 200, Corydon; 812-738-3237
Highway Department (driveways, right-of-way)812-738-2920; online application
Surveyor and Drainage Board812-738-3206
Recorder (deeds)245 Atwood Street, Suite 201; 812-738-3788

Towns in Harrison County

Harrison County towns
TownWhat the official sources show
CorydonThe town issues building and development permits through its Planning and Zoning office at Town Hall (812-738-3958), usually in 48 to 72 hours; the county’s checklist also lists the town permit for work inside Corydon
Crandall, Elizabeth, Lanesville, Mauckport, New Amsterdam, PalmyraCovered by the county’s floodplain regulations, and the Plan Commission posts a comprehensive plan for each
Laconia, Milltown (Harrison part), New MiddletownThe Plan Commission posts their comprehensive plans

The county’s pages do not say outright whether the Plan Commission issues building permits inside each of these towns, so ask the Plan Commission office for any parcel inside town limits. For unincorporated land, the county’s zoning confirmation line is 812-738-8927.

Harrison County permit types

The building permit application, together with its attachments, is submitted through the county’s iWorQ permit management portal. The county will not start its review until every item on its checklist is attached.

Residential permits

  • Health approval: for a new dwelling, a septic permit from the Harrison County Health Department or a sewer tap-in receipt; for other work, the Health Department’s site approval letter.
  • Ownership: a copy of the recorded deed or purchase contract.
  • Driveway: a permit for any new or changed driveway, from the county Highway Department on county roads or the state highway office (812-282-7493) on state routes.
  • Site plan: property lines and streets, all existing and proposed structures with the distances between them, setbacks to every property line, and the driveway location; for a new address, the neighboring driveways too. A printed map from the county’s Beacon GIS is accepted.
  • Building plans: wall cross-section, truss or rafter, stair and deck details, door and window details, foundation plan, floor plans for each level and all four elevations; new home plans must be digital or architectural drawings. Manufactured homes need the pier layout and tie-down specifications.
  • Plan review checklist: the county’s residential checklist also asks for job-site pins or stakes marking lot lines and easements within 50 feet of construction, energy compliance papers (a HERS rater certificate for the performance path or a REScheck or prescriptive checklist), and, for additions, remodels and fire restorations, a scope of work and smoke detectors throughout the house.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial buildings use the same portal and need a detailed, scaled site plan showing parking, access, loading, lighting, signs, landscaping and sewage and drainage, plus the state Construction Design Release or an engineer’s certificate of compliance. Fees are charged per square foot and per inspection, and a commercial demolition requires an asbestos survey.

What comes before the building permit

  • Zoning: confirm the zoning by phone; rezonings, variances and special exceptions are filed in the planning and zoning portal and heard by the Plan Commission or the Board of Zoning Appeals.
  • Septic: the zoning ordinance requires the Health Department’s sewage disposal permit before an ILP is issued.
  • Road access: a road cut-in permit from the state, the county or the town must accompany the ILP application.
  • Floodplain: work in a mapped flood area is reviewed under the county’s floodplain article, and building in a floodway needs an Indiana DNR permit before the local permit.
  • Drainage: the County Surveyor oversees the Drainage Board and settles drainage disputes.

Harrison County permit costs and fees

Permit fees are set by Ordinance 2025-32, which amends the county zoning ordinance on the recommendation of the Plan Commission. The signed copy is dated the 15th day of December 2025 (“June” is struck out and “December” written in). The building fee for a new dwelling or a commercial building includes plan review.

Rather talk it over?

Call 1-855-478-4290 →
Harrison County permit fees (Ordinance 2025-32)
WorkFee
New single-family or two-family dwelling (includes plan review)$200 plus $0.10 per sq ft
Residential addition$100 plus $0.10 per sq ft
Accessory building or barn$75 plus $0.02 per sq ft
Manufactured, mobile or modular home$300
Pool, above-ground / in-ground$75 / $150
Deck, porch or patio; certificate of occupancy$75; $50
Residential electric, new structure (temporary pole, rough, TOM, final)$75 each
Residential electric, additions and accessory buildings$75 per inspection
Residential HVAC, new structure / replacement$100 / $50
Residential plumbing$40 plus $5 per additional fixture, $85 minimum
Commercial new structure, addition or temporary structure (includes plan review)$0.30 per sq ft plus $50 per inspection
Tenant finish or build-out$0.20 per sq ft plus $50 per inspection
Commercial demolition / certificate of occupancy$200 / $50
Commercial electric$0.75 per amp; temporary pole or alteration $75
Commercial HVAC: units / rooftop unit / hood suppression$100 / $150 / $200
Commercial plumbing$60 first fixture, $10 each additional
Re-inspections, residential$75, $150, then $300
Re-inspections, commercial$125, $250, then $500
Working without a permitTwice the fee
Variance or special exception / development plan$500 / $500
Rezoning$500 (A-R) to $1,500 (industrial, PEC and PUD)
Sign, permanent / temporary$100 / $50

Worked example from the ordinance: a 2,000-square-foot house is $200 plus 2,000 × $0.10, or $400, for the building permit. Add four residential electrical inspections at $75 ($300), the $100 HVAC fee for a new structure and the $50 certificate of occupancy, and the county fees reach $850 before plumbing, which is at least $85. Driveway permits from the Highway Department are free; right-of-way permits cost $50.

Land-use petitions follow the same ordinance. A zone map change costs $500 to agricultural-residential, $600 to R-1 or R-1a, $700 to R-2 or R-3, $1,000 to a business district and $1,500 to an industrial, PEC or PUD district. A minor plat is $300, a major subdivision primary plat $1,000 plus $20 a lot and a secondary plat $1,000, an administrative appeal $150, and every public hearing adds $40 for the newspaper notice, sign and postage.

Trade permits and who may pull them

Harrison County permits and inspects electrical, HVAC and plumbing work itself, with its own fee lines for each trade. On a new house, the electrical work is inspected four times: the temporary pole, the rough-in, the TOM inspection and the final, at $75 each.

Rather not deal with the Harrison County building department?

Get a free quote →
  • Plumbing: priced per fixture; plumbing contractors carry the state plumbing license.
  • HVAC: new systems and replacements each have a flat fee; commercial rooftop units and hood suppression are priced separately.
  • Electrical: commercial services are priced by amperage at 75 cents per amp.
  • Who applies: the county’s FAQ points any applicant to the online building permit application; the posted pages show no county contractor license or registration, so ask the Plan Commission what it needs from your contractors.

How to apply for a Harrison County building permit

1. Confirm the zoning

Call the Plan Commission at 812-738-8927 to confirm the zoning and that the parcel is in the county’s jurisdiction, not inside Corydon.

2. Get health approval

Obtain a septic permit or sewer tap-in receipt for a new home, or a site approval letter for other work, from the Health Department.

3. Get the driveway permit

Apply online to the county Highway Department, or to the state for a state highway.

4. Prepare the attachments

Recorded deed or purchase contract, site plan with setbacks and the driveway, and full building plans.

5. Submit in the iWorQ portal

Upload everything with the permit application; incomplete applications are not reviewed.

6. Pay and schedule

Pay the Ordinance 2025-32 fees and arrange the required inspections with the inspector for your area.

Review, corrections and what causes delay

The county allows five to seven business days to review a complete application, and the zoning ordinance asks that an ILP application be in at least five days before the permit is issued, although the administrator may waive that. A missing health approval, deed or driveway permit stops the review. Commercial applications also wait for the state design release.

Inspections and certificates in Harrison County

Ask the office which inspections your permit needs when it is issued; the fee ordinance sets four electrical inspections on a new home and an inspection fee for each visit on commercial jobs. Re-inspections are charged from $75 for homes and $125 for commercial work, rising with each repeat.

A certificate of occupancy is applied for together with the ILP, and the zoning ordinance says it is issued within 10 days after the building is lawfully completed. The certificate costs $50, and the Plan Commission keeps a record of every certificate, with copies available to anyone holding an ownership or tenancy interest in the property.

Want this handled start to finish?

Get a free quote →

Indiana building code in Harrison County

The county floodplain regulations in the zoning ordinance apply to unincorporated Harrison County and to Crandall, Elizabeth, Lanesville, Mauckport, New Amsterdam and Palmyra. FEMA’s Community Status Book lists unincorporated Harrison County (community 180085) as participating in the National Flood Insurance Program, with maps effective October 16, 2014. The Plan Commission page also posts the county’s 2025–2045 comprehensive plan.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Harrison County permit search and official resources

The Plan Commission keeps the plans filed with every ILP as a permanent record, and its iWorQ planning software lets the public search variances, appeals and plans. For a copy of an older permit or certificate of occupancy, call the office at 812-738-8927.

Inspections are where schedules slip.

Get a free quote →

Harrison County building permit FAQs

How much is a building permit for a new house in Harrison County?

$200 plus 10 cents a square foot under Ordinance 2025-32, with plan review included; electrical, HVAC, plumbing and the certificate of occupancy are extra.

How long does review take?

Five to seven business days once every checklist item is attached in the portal.

Do I need a permit in Corydon?

Yes, from the Town of Corydon’s Planning and Zoning office at Town Hall; the county’s checklist also lists the town permit for work inside Corydon.

Do I need the septic permit first?

Yes. A new dwelling needs a Health Department septic permit or a sewer tap-in receipt before the county reviews the building permit.

Is there a fee for a driveway permit?

No. County driveway permits are free; right-of-way permits for other work in county roads cost $50, under Ordinance 2026-5.

What happens if I build without a permit?

The fee ordinance doubles the permit fee for work started without a permit, for both residential and commercial work.

Do commercial projects need a state release?

Yes. The county’s checklist says commercial additions, renovations and new structures need a state Construction Design Release.

Simplify Harrison County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Harrison County sooner?

Let Alliance prepare, file, and track your Harrison County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Harrison County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.