In unincorporated Floyd County, building permits, zoning and inspections are handled by the Department of Building & Development Services at the Pine View Government Center, 2524 Corydon Pike, Suite 203, New Albany (812-981-7611, building@floydcounty.in.gov), headed by Building Commissioner Kelley Lang. Applications are PDF forms sent by email or dropped off, and a complete residential package takes 5 to 7 business days to review. Under the fee schedule the commissioners adopted on June 18, 2024 (FCO 2024-16), a new house costs $200 plus $0.15 per square foot of floor area.
What requires a building permit in Floyd County?
The department’s own answer is short: any structure of 120 square feet or more, such as a storage shed, garage or pool house, and any pool that can hold water 48 inches deep or more. The building permit application then covers four kinds of residential work: a new single-family dwelling, an addition, a renovation or rehab of an existing house, and accessory structures such as post buildings, detached garages and in-ground pools. Commercial and industrial buildings, their remodels and additions use the commercial application, and parking structures are charged per space.
Electric permit only
- Repairs at the meter base or service equipment that need the power disconnected
- A generator installation that needs the service temporarily disconnected
- Upgrading from one service rating to another, such as 100 to 200 amps
- Reconnecting permanent service after the meter has been moved
Full building permit
- Any electrical work beyond those four cases (a rehabilitation permit)
- Renovations and rehabs of existing houses
- Interior remodels, residential or commercial, charged on the remodel fee lines
Starting work before the permit is issued carries an “early bird” fine of twice the permit fee, and building something that does not match the approved site plan carries a fine of five times the permit cost plus the cost of the variance it then needs. When a new building uses lightweight I-joists or trusses, the application includes a Firefighter Safety Notification so the county can tell the fire department and 911 centers, as IC 22-11-21 requires for Class 1 and Class 2 structures.
What Floyd County decides and what the state holds
The county sets its zoning and development standards in Zoning Ordinance FCO 2006-06 (updated June 18, 2024), its own permit fees and its inspection stages, and the Building Commissioner issues the certificate of occupancy. For commercial work the department’s process places the state’s release between zoning and the county permit: step one is a development plan where the district requires one, step two the state design release, and only then the building permit application.
Floyd County building department: who handles permitting
The commissioners re-established the Building and Development Services Department on January 2, 2018. Its staff include the Building Commissioner, the County Planner and a building inspector, and it recommends making an appointment before visiting. The county zoning ordinance applies to all land in the county except the planning jurisdiction of the City of New Albany, the towns of Georgetown and Greenville, and land owned by the state or federal government.
Short on time to read all of this?
Get a free quote →| Item | Detail |
|---|---|
| Address | Pine View Government Center, 2524 Corydon Pike, Suite 203, New Albany, IN 47150 |
| Phone / fax | 812-981-7611 / 812-948-4744 |
| Email (applications, inspections, status) | building@floydcounty.in.gov |
| Office hours | Monday to Friday, 8:00 a.m. to 4:00 p.m. |
| Building Commissioner | Kelley Lang |
| Plan Commission and BZA | Second Monday monthly at the Judicial Center, 311 Hauss Square, 3rd floor assembly room; BZA 5:00 p.m., Plan Commission 7:00 p.m. |
| Place | Building permits |
|---|---|
| New Albany (city, 37,463) | The city’s own Building Department, 142 E. Main Street, Suite 206 (812-948-5371); zoning in the city and its Two-Mile Fringe Area goes through the New Albany City Plan Commission (812-948-5327), so ask both offices about a fringe lot; see the New Albany guide |
| Georgetown (town, 3,855) | Apply and pay at Georgetown Town Hall, 9111 State Road 64 (812-951-3012); the town forwards the application to the county for review, and the county inspects |
| Greenville (town, 1,452) | The county’s Plan Commission page posts Greenville’s own zoning and subdivision ordinances; the published sources do not say who issues its building permits, so ask the town |
To find the zoning district of a parcel, use the county’s Beacon GIS portal or email the department with the address or parcel number. Georgetown also registers contractors: its form asks for a certificate of $1,000,000 liability insurance and a $25 fee.
Floyd County permit types
All applications are fillable PDFs on the department’s Documents & Applications page: the building permit (houses, additions, rehabs, accessory structures), the commercial building permit, the electric permit, sign permits and the Plan Commission and BZA petitions.
Residential permits
- Health approval. A new house needs a septic permit or a sewer tap-in receipt; an addition, rehab or accessory building on a lot with a septic system needs a Floyd County Health Department site approval permit.
- Site plan. Property lines and streets, all existing and new structures, setbacks to lot lines and county right-of-way, driveways with material and culvert size, easements, drainage arrows, LP gas tanks and a north arrow. For a new house the site plan must come from an Indiana licensed surveyor or engineer; for an accessory structure the owner may instead sign a notarized plot diagram affidavit accepting responsibility for its location.
- Deed or purchase contract.
- Building plans. Elevations of all four sides, a wall section, stair and deck details, door and window details, foundation plan and floor plans for every level, plus a construction statistics sheet on joists, rafters, foundation and electrical service.
- Manufactured homes. Photos of the HUD data plate and label or the Indiana modular insignia, and the pier and tie-down layout.
Not sure this scope needs a permit?
Get a free quote →The application also asks for the water utility, the electric provider (Harrison REMC, Clark REMC or Duke), the energy rating company and the plumber’s license number.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
A development plan is required before commercial work in the Highlander Point and Edwardsville gateway districts and in the RU, MF, NC, GC, HS, OB and GI districts; the County Planner starts that process. After the development plan comes the state design release, then the commercial building permit application. Public and semi-public pools also need an operating permit from the Health Officer under FCO 2025-19, which does not apply to a pool at a one- or two-family home used by the household.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Septic or sewer. Floyd County Health Department, 1917 Bono Road, New Albany (812-948-4726).
- Development plan and zoning relief. The Plan Commission and BZA hear cases on the second Monday; the pre-application deadline for the December 14, 2026 hearing was November 6, and its final submission deadline is November 20. A pre-submission meeting with staff is encouraged.
- Stormwater. The county runs an MS4 stormwater program under a Stormwater Board and a revised stormwater ordinance (FCO 2024-27); road, bridge and stormwater engineering questions go to the Engineering Division (812-948-5441).
- State design release. Commercial step two.
Floyd County permit costs and fees
Fees are set by Appendix D of the zoning ordinance, replaced by FCO 2024-16, which the commissioners adopted on June 18, 2024; the department lists the schedule as effective August 1, 2024. The ordinance says many fees had not changed since 2006.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Single- or two-family dwelling (excluding garage, attic and similar areas) | $200 plus $0.15 per sq ft of floor area |
| Multi-family dwelling | $300 per unit |
| Detached garage or accessory structure | $40 minimum or $0.15 per sq ft |
| Attached garage | $100 minimum or $0.15 per sq ft |
| Residential addition / interior remodel | $55 / $40 plus $0.15 per sq ft |
| Swimming pool | $250 |
| Temporary mobile home | $155 for the first two years, then $300 a year |
| Commercial or industrial structure | $530 plus $0.15 per sq ft |
| Commercial interior remodel / accessory structures and additions | $110 plus $0.15 per sq ft / $150 minimum plus $0.15 per sq ft |
| Change in electrical service | $60 |
| Parking structure | $15 per space |
| Building inspection / re-inspection | $50 per inspection / $75 residential, $180 commercial or industrial |
| Variance / special exception / rezoning | $300 / $500 / $500 |
| Conditional use / development plan / sign permit | $450 / $300 / $100 |
| Starting work before the permit | Twice the permit fee |
Worked example from the schedule: a new house with 2,000 square feet of floor area, not counting the garage, costs $200 plus 2,000 × $0.15 ($300), or $500 for the permit. The 2025 application form still mentions a $50 re-inspection fee; the adopted ordinance sets $75 for residential work, and the newer figure is the one in force.
Trade permits and who may pull them
Floyd County folds most trade work into the building permit. The application lists the electrical, mechanical or HVAC and plumbing contractors, with the plumber’s license number, and the inspections include a plumbing ground rough-in, the framing and all rough-ins, and the electric service. It also asks which set of electrical provisions the design follows, the residential code’s or the state electrical code’s.
- Electric permit: a separate $60 permit for service repairs, generator hook-ups that need a disconnection, service upgrades and reconnections after a meter move; other electrical work needs a rehabilitation permit.
- Utility release: after the service inspection the department notifies the electric company the next business day.
- Local registration: the county posts no contractor license or registration of its own; in Georgetown, contractors register with the town.
Rather not deal with the Floyd County building department?
Get a free quote →How to apply for a Floyd County building permit
Check that the lot is outside New Albany’s planning area and the towns, and look up its district and setbacks in Section 4 of the zoning ordinance or on Beacon.
Get the septic permit, site approval or sewer tap-in receipt first.
Use a licensed surveyor or engineer for a new house; include driveway, culvert, drainage and LP tank locations.
Residential, commercial or electric form, with the firefighter safety notification where advanced structural components are used.
Email the package to building@floydcounty.in.gov or drop it off at Suite 203; call ahead before visiting.
The fee follows FCO 2024-16; do not start before the permit is issued.
Review, corrections and what causes delay
The department will not issue a residential permit until every item on its checklist is in, and it asks for 5 to 7 business days to review a complete application. Commercial projects in districts that need a development plan add a hearing cycle, with pre-application and final submission deadlines several weeks before each monthly meeting. A lot inside a subdivision may also have conditions set by the developer or association, which the county asks applicants to check.
Inspections in Floyd County
Book inspections by phone at 812-981-7611 or by email, giving your name and number, the permit number, the address and lot, the type of inspection and, before a pour, the time the concrete will arrive. The required stages are a temporary pole (with the footer, wall or plumbing ground rough), footers and walls with forms set before concrete, plumbing ground rough-in, framing with all rough-ins, the electric service, and a final once all work and outside grading are complete.
The department’s pages give three different inspection windows: the main notice says inspections can be scheduled Monday to Thursday, 8:00 to 11:30 a.m. and 1:00 to 4:00 p.m., while the contact and inspection pages list Monday to Friday windows, so confirm the time when you book. Work that is not ready is charged a re-inspection fee. A new house fails its final if the energy certificate is not posted in the electrical panel, and no building may be occupied until the Building Commissioner issues a certificate of occupancy.
Indiana building code in Floyd County
FEMA’s Community Status Book shows unincorporated Floyd County (community 180432) participating in the National Flood Insurance Program, with flood maps effective April 16, 2014; New Albany and the towns are listed separately. The County Surveyor keeps flood maps for public review and links a guide to requesting a Letter of Map Amendment.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Floyd County permit search and official resources
The county has no public permit search; to check the status of an application or an inspection result, email building@floydcounty.in.gov or call 812-981-7611. Plan Commission and BZA agendas, dockets and 2026 minutes are on the Plan Commission page, and older minutes are available from the office on request.
- Floyd County Building & Development Services
- Department contacts and hours
- Building and zoning fees
- FCO 2024-16 fee schedule ordinance
- Residential and commercial permit process
- Building inspection criteria
- Documents and applications
- Building permit application
- Electric permit application
- Floyd County Zoning Ordinance FCO 2006-06
- Plan Commission and Board of Zoning Appeals
- Floyd County Stormwater
- Georgetown Town Hall building permit steps
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Floyd County building permit FAQs
Do I need a permit for a shed in Floyd County?
Yes if it is 120 square feet or more; a detached accessory building costs $40 minimum or $0.15 per square foot.
How much is a building permit for a new house?
$200 plus $0.15 per square foot of floor area, excluding the garage and attic; a 2,000-square-foot house is $500.
How long does review take?
The department asks for 5 to 7 business days once the residential package is complete.
Can I email my application?
Yes. Send it to building@floydcounty.in.gov, or drop off a paper copy at 2524 Corydon Pike, Suite 203.
I live in Georgetown. Where do I apply?
At Georgetown Town Hall; the town sends the application to the county for review, you pay at the town office, and the county inspects.
What if I start before the permit is issued?
The county charges an early-bird fine of twice the permit fee.
Do I need a surveyor for my site plan?
For a new house, yes: the site plan must come from an Indiana licensed surveyor or engineer. For an accessory building the owner may sign a notarized plot diagram affidavit instead.
Simplify Floyd County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Floyd County sooner?
Let Alliance prepare, file, and track your Floyd County permits while your crew stays on the job.
More Indiana permitting guides
New Albany
Read guide →Jeffersonville
Read guide →Harrison County
Read guide →Fort Wayne Building Permit Guide
Read guide →Fountain County Building Permit Guide
Read guide →Frankfort Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Floyd County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.