Griffith, Indiana Building Permit Guide

To get a building permit in Griffith, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Griffith’s Building Department, in the lower level of Town Hall at 111 North Broad Street, issues building and trade permits for the whole town, licenses every contractor who works there, and accepts applications by email, fax, mail, drop box or at the counter.

Authority: Griffith Building DepartmentFiling: Email, fax, mail or counterPhone: 219-922-3091
Authority
Town Building Department111 N. Broad St., lower level
Contractors
Town license requiredEven for work with no permit
Failed inspection
$30 chargePaid before the re-inspection
Boards
3rd MondayBZA 6:00 p.m., Plan Commission 7:00 p.m.

Griffith is a town, and its own Building Department at Town Hall, 111 North Broad Street (219-922-3091), issues building permits, inspects the work and licenses contractors everywhere inside the town limits. Building work goes on one application and electrical, plumbing and HVAC work on a separate M.E.P. application; while the online portal is offline, both are taken by email, fax, mail, drop box or in person.

What requires a building permit in Griffith?

The Building Department publishes its own examples of work that needs a permit and work that does not. Its list is broad: most exterior replacement work, all concrete and asphalt, and any change to the electrical, plumbing or heating systems needs a permit.

Permit required

  • Any new structure: a house, a commercial or industrial building, a garage, shed, fence, deck, ramp or swimming pool
  • Additions such as a room addition, porch or attached garage
  • Interior and exterior remodeling: bathrooms, kitchens, finished basements, framing and drywall, new windows and doors, siding, soffit, fascia, gutters, roofing, cutting any wall or partition, drain tile and tuck pointing
  • Concrete or asphalt work: driveways, sidewalks, patios, aprons, parking lots and pads
  • Most commercial and industrial alterations and construction
  • Extending or altering electrical, plumbing, heating or air conditioning: new circuits, rewiring, service releases, panel upgrades, repiping, and boiler, furnace or AC change-outs

No permit

  • Changing light fixtures and receptacles
  • Sewer rodding or maintenance
  • Painting or wallpapering
  • Residential floor coverings
  • Landscaping

A job on the no-permit list still has to be done by a contractor who holds a current Griffith contractor license if a contractor is hired; the department repeats that rule on its permit page and its license page. Signs need their own sign permit, and any cut into a road, parkway, sidewalk, curb or alley needs a right-of-way construction permit.

What Griffith decides and what the state holds

The town decides which work needs a local permit, sets its permit and license fees in the Griffith Code of Ordinances, licenses contractors, runs zoning through its Plan Commission and Board of Zoning Appeals, and enforces its 2024 stormwater management ordinance. The building and trade rules themselves are the state’s: the department says its permits let inspectors enforce the Indiana Building Code and local ordinances. For a Class 1 building, one used by the public, by three or more tenants or by anyone’s employees, the state Construction Design Release from the Indiana Department of Homeland Security must be issued before construction starts unless 675 IAC 12-6-4 exempts the work; the town permit does not replace it.

Griffith building department: who handles permitting

The Griffith Building Department handles every permit inside the town limits, whether the work is done by a contractor or by a homeowner. Besides building permits and inspections, it issues occupancy permits, does plan review, licenses contractors, handles planning and zoning questions and acts as the point of contact for the Plan Commission and the Board of Zoning Appeals. Lake County’s Plan Commission has no role inside Griffith; it permits only unincorporated land.

Short on time to read all of this?

Get a free quote →
Griffith Building Department contacts
DetailInformation
OfficeGriffith Building Department, Town Hall (lower level), 111 North Broad Street, Griffith, IN 46319
Phone / fax219-922-3091 / 219-924-3840 (Town Hall main line 219-924-7500)
Emailbuilding@griffith.in.gov
HoursMonday to Friday until 4:30 p.m., closed for lunch from noon to 1 p.m. and on major holidays; the department page gives an 8 a.m. opening and its contact page 8:30 a.m.
Drop boxesOutside the front and rear doors of Town Hall
BoardsBoard of Zoning Appeals and Plan Commission, both on the third Monday of the month at Town Hall (6:00 p.m. and 7:00 p.m.)

Griffith permit types

Griffith keeps its forms short. The Building Permit Application covers building work of every size, from a new house or store to a fence, shed, pool, deck or window replacement. Electrical, plumbing and HVAC work goes on the M.E.P. Permit Application, with a section and a project cost for each trade contractor. Both forms say copies of the signed contracts are required. A Contractor Recap Sheet lists every contractor on a larger job, from the general contractor and carpenter to the concrete, drywall, insulation, landscape and sign firms, and states the total cost of improvements.

Residential permits

  • New houses and additions use the building form, which asks for the structure type (single-family, duplex or multi-unit), number of stories, square footage, height, foundation type (slab, crawl or basement), garage size and whether the basement is finished, plus an M.E.P. application for the trades.
  • Garages, sheds, decks, fences, pools and ramps are new structures on the town’s list and use the same building form.
  • Remodeling and exterior work, including roofing, siding, gutters, windows, doors and concrete flatwork, needs a building permit even when nothing structural changes.
  • Owner-builders file the Homeowner Affidavit described under trade permits.

Commercial permits

For commercial and industrial work the building form asks for the business name, whether a fire sprinkler system is required and how many heads, and the number of seats for a restaurant. Mechanical details on the M.E.P. form include rooftop units, unit heaters, kitchen hoods, boilers, refrigeration and exhaust fans, and the plumbing section lists grease traps, backflow preventers, floor drains and roof drains. Most commercial buildings are Class 1, so the state design release comes first; signs use the town’s sign permit application with the sign and electrical contractors named.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. Check the parcel on the town’s interactive zoning map, linked from the department’s pages. Variances go to the Board of Zoning Appeals and rezoning or subdivision to the Plan Commission; the Building Department is the contact for both.
  • Flood zone. The building form records the flood zone designation, and work in a flood zone needs a section completed by an Indiana-licensed engineer or surveyor: the flood map used, an elevation certificate, the base flood elevation, the lowest floor elevation and the foundation venting.
  • Erosion control and stormwater. Every applicant signs an acknowledgment that soil erosion control will be strictly enforced, and the town’s Stormwater Management Ordinance (Ordinance 2024-7) is administered through its MS4 coordinator.
  • Right-of-way work. Cuts into a road, parkway, sidewalk, curb or alley need a right-of-way construction permit signed by the Public Works Director, with insurance, a stated type of surety and a one-year guarantee on the workmanship.
  • State design release. Class 1 projects need the IDHS Construction Design Release before construction begins.

Griffith permit costs and fees

Griffith’s permit fees are set in the town Code of Ordinances, and the department fills in the permit fee and any escrow on each application when it reviews it, so a quote for a specific job comes from the department at 219-922-3091. The town’s own forms do publish the charges below. The online code is updated only two to four times a year, so a recent ordinance may not appear there yet.

Griffith charges printed on current town forms
ItemFee
Re-inspection after a failed inspection$30, paid before the re-inspection
General contractor license$100 plus $25 application fee; renewal $50
Subcontractor license$50 plus $25 application fee; renewal $25
Electrical or HVAC contractor license$100 plus $25 application fee; renewal $50
Plumbing contractor license$50; renewal $50
Scavenger license$125; renewal $125
Building, trade, demolition, occupancy, sewer tap and water tap fees; escrowSet by the town code and entered by the department at review
Copies of public records$0.10 per page, $0.25 per color page

Rather talk it over?

Call 1-855-478-4290 →

All contractor licenses expire on December 31 of the year they are issued, whatever month they were bought. Budget separately for the state design release on Class 1 work, which the state charges on floor area under 675 IAC 12-3-2.

Trade permits and who may pull them

All electrical, plumbing and HVAC work is permitted on the M.E.P. application, and each trade needs a Griffith-licensed contractor unless the owner qualifies as an owner-builder.

  • Contractor license. Every contractor working for hire in Griffith needs a Griffith contractor license, even for work that needs no permit. The application goes to the Clerk-Treasurer for review by the town’s Board of Contractor Examiners and needs a certificate of insurance naming the Town of Griffith as holder (general liability and vehicle liability of $100,000/$300,000 and property damage of $100,000), workers’ compensation or a state exemption, a recorded Lake County license and permit bond (ask the office for the wording), a copy of the owner’s driver’s license and copies of every field employee’s USCIS Form I-9.
  • Plumbing. Plumbing contractors attach a copy of their State of Indiana plumbing contractor license to the town application.
  • Electrical and HVAC. Licensed under the same Griffith application at the electrical/HVAC rate.
  • Homeowners. An owner who lives in the house may act as owner and contractor by signing the Homeowner Affidavit under penalty of perjury and attaching a driver’s license. Helpers must be friends or relatives named on the form with address and phone, and they may not be paid. The owner must be present and working whenever helpers are on site, or a citation follows, and false statements can bring penalties of up to $2,500 that may accrue daily.

The department keeps a list of licensed contractors and will confirm whether a contractor is licensed before you hire.

How to apply for a Griffith building permit

1. Check the permit lists and zoning

Compare the job with the department’s permit and no-permit examples and look up the zoning district on the town map.

2. Confirm every contractor is licensed

Call 219-922-3091 or ask for the licensed contractor list; an unlicensed firm must apply for a Griffith license first.

3. Fill in the right forms

The Building Permit Application for the structure, the M.E.P. application for trades, the Contractor Recap Sheet on larger jobs, and the Homeowner Affidavit if you are doing the work yourself.

4. Attach the paperwork

Signed contracts, plans for new construction and additions, and the engineer’s or surveyor’s flood section if the site is in a flood zone.

5. Submit

Email the package to building@griffith.in.gov, fax it to 219-924-3840, mail it to 111 N. Broad St., drop it in a Town Hall drop box or bring it to the counter.

6. Pay and pick up the permit

The department sets the fee and any escrow at review; do not start until the permit is issued.

Rather not deal with the building department?

Get a free quote →

Review, corrections and what causes delay

The department’s notice says its online portal is temporarily unable to accept permit or license applications, so electronic filing means email for now. The forms themselves name what must be in the package: signed contracts, a currently licensed contractor for every trade, the recap sheet on larger jobs and, on a flood-zone site, the elevation section completed by a licensed engineer or surveyor. A zoning variance adds a Board of Zoning Appeals hearing on the third Monday of the month before the permit can issue.

Inspections and occupancy in Griffith

Inspections are required on permitted work, and Griffith puts the duty to book them on the contractors: each contractor schedules its own inspections by calling 219-922-3091. If an inspection fails, a $30 charge must be paid before the inspector returns. The department’s permit forms state that all work must meet or exceed the current Griffith and State of Indiana codes.

The department also issues occupancy permits, and the recap sheet carries a separate certificate of occupancy fee line. On Class 1 work, keep the state design release posted on site with the released plans until occupancy.

Indiana building code in Griffith

Griffith enforces the state’s building rules together with its own ordinances, and its Code of Ordinances is published through Municode with periodic updates. FEMA’s Community Status Book lists the Town of Griffith (community 185175) as participating in the National Flood Insurance Program, with flood maps effective March 16, 2016, which is why the building form asks for flood zone and elevation data.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Griffith permit search and official resources

For permit status on a current application, call the Building Department or use the status link on its permit page when the portal is back online. Older permits, inspection results and other town records are requested on the Clerk-Treasurer’s Request to Review and/or Copy a Public Record form, which describes the records wanted and charges $0.10 per copied page under IC 5-14-3-8. Plan Commission and BZA agendas and minutes are posted on the town’s meetings page.

Want this handled start to finish?

Get a free quote →

Inspections are where schedules slip.

Get a free quote →

Griffith building permit FAQs

Do I need a permit to replace my roof or windows in Griffith?

Yes. Roofing, siding, soffit, fascia, gutters and new windows and doors are all on the town’s list of work that needs a building permit.

Does a fence or shed need a permit?

Yes. Fences, sheds, garages, decks, ramps and pools are new structures on the Building Department’s permit list and use the Building Permit Application.

Can I apply online?

Not at the moment. The department’s notice says the online portal cannot take permit or license applications for now; send the forms by email, fax, mail or drop box, or file in person.

Does my contractor need a Griffith license?

Yes. Every contractor working for hire in Griffith must hold a town contractor license, even for work that needs no permit, and licenses expire on December 31.

Can a homeowner do the work?

Yes, if you own and live in the house and sign the Homeowner Affidavit. Only unpaid friends or relatives named on the form may help, and you must be on site working whenever they are.

How do I schedule an inspection?

Contractors book their own inspections by calling 219-922-3091; a failed inspection carries a $30 charge before the re-inspection.

When do the BZA and Plan Commission meet?

Both meet on the third Monday of the month at Town Hall, the BZA at 6:00 p.m. and the Plan Commission at 7:00 p.m.

Simplify Griffith permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Griffith sooner?

Let Alliance prepare, file, and track your Griffith permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Griffith permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.