Woodford County, Illinois Building Permit Guide

To get a building permit in Woodford County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Woodford County has adopted no building code. In unincorporated areas its Building and Zoning Department issues zoning permits for new homes, additions, sheds, pole barns, decks, fences and pools, while the county Health Department issues septic and well permits.

Authority: Woodford County Building and ZoningServes: Unincorporated Woodford CountyPhone: 309-467-3023
Zoning office
Building and ZoningCourthouse, 115 N. Main St., Room 100, Eureka
New house
$250 zoning permitPer dwelling unit, with attached garage
Septic permit
$225Health Department, non-refundable
Building without a permit
4 times the feePenalized permit under the fee schedule

In unincorporated Woodford County, construction permits come from the Building and Zoning Department on the first floor of the Courthouse, 115 N. Main Street, Room 100, Eureka (309-467-3023, weekdays 8 a.m. to 5 p.m.). The county is a non-building-code jurisdiction, so what it issues is a zoning permit, priced under the county fee schedule: $250 for a new house and 15 cents a square foot for additions and larger accessory buildings. Cities and villages in the county handle their own permits.

What requires a permit in unincorporated Woodford County?

Under the county zoning ordinance, no building or structure may be built, rebuilt, altered, converted, moved, added to or put to a new use until the Zoning Administrator has issued a zoning permit. That covers permanent, temporary and movable buildings, structures and signs, unless the ordinance exempts them. The county FAQ gives common examples: sheds, fences, decks, additions, garages, pools, pole barns and porches.

Zoning permit needed

  • New homes, two-family and multi-family dwellings
  • Additions to a house
  • Sheds, detached garages and pole barns
  • Decks and porches, new or replaced
  • Fences over 4 feet or more than 50% solid
  • In-ground pools over 2 feet deep and 125 sq ft
  • Signs, towers, wind and solar systems
  • Moving a structure or changing its use

No zoning permit

  • Siding, insulation and gutters
  • Painting, flooring, cabinets and similar finish work
  • Roof shingles, if the structure is not changed
  • Same-size windows and doors
  • Driveways, sidewalks and landscape or retaining walls
  • No fee for farm buildings or accessory buildings on an operating farm

Front-yard fences may be no more than 48 inches tall and must be at least 50% open, and no fence may stand in the road right of way. The county has no rule requiring a fence around a pool.

What the county decides and what the state holds

The County Board sets the zoning, subdivision, floodplain and stormwater ordinances and the fee schedule. Because the county has adopted no building code, it does not review construction plans or inspect framing, wiring or plumbing in unincorporated areas; its review covers zoning, setbacks, floodplain and erosion control. Septic systems and wells are permitted by the county Health Department under the state’s private sewage and water well codes, and the Illinois Plumbing Code applies to plumbing work statewide.

Woodford County building department: who handles permitting

The Building and Zoning Department administers and enforces the zoning ordinance, subdivision regulations, floodplain ordinance, erosion, sediment and stormwater rules and rural addressing in the unincorporated county, issues zoning permits and handles plat approvals, variances, special uses, text amendments and rezonings. The department head is the Zoning Administrator, Kayla Underwood. It works with the Zoning Board of Appeals and the County Board’s Conservation, Planning and Zoning Committee.

Short on time to read all of this?

Get a free quote →

To tell whether an address is unincorporated, look the parcel up in the county’s GIS property viewer on its Maps page or call the zoning office. The county FAQ says its rules apply only to unincorporated property and that owners inside a city or village should contact that municipality.

Woodford County offices for building projects
OfficeContact
Building and Zoning (zoning permits, floodplain, erosion, addressing)Courthouse, 115 N. Main St., Room 100, Eureka, IL 61530; 309-467-3023; wczoning@woodfordcountyil.gov; weekdays 8 a.m. to 5 p.m.
Health Department, Environmental Health (septic, wells)1831 S. Main St., Eureka; 309-467-3064; office hours Tuesday 7:30 to 11:30 a.m., Thursday 11 a.m. to noon and 1 to 4 p.m.
Highway Department (county roads)301 S. Main St., Roanoke; 309-923-2891; weekdays 7 a.m. to 3:30 p.m.

Cities and villages in Woodford County

The county zoning office covers only unincorporated land, and its FAQ tells owners of property inside a city or village to contact that local jurisdiction for permitting rules. The county has 16 cities and villages, and four of them extend into neighboring counties.

Municipalities in Woodford County
PlacesWho handles permits
Cities: Eureka (county seat), Minonk, El Paso (partly in the county)The city; contact its city hall
Villages: Metamora, Germantown Hills, Roanoke, Spring Bay, Congerville, Secor, Benson, Bay View Gardens, Kappa, PanolaThe village; contact its village office
Villages partly in the county: Washburn, Goodfield, Deer CreekThe village; contact its village office
Unincorporated landWoodford County Building and Zoning

Woodford County permit types

The zoning office takes applications in person during office hours. To process a permit it needs the structure’s dimensions, location, use and construction cost and an elevation drawing or a picture of something similar, and with those it can usually issue the permit the same day. The county posts a zoning permit worksheet, single-family dwelling requirements and an accessory building handout.

Residential permits

  • New homes. A dwelling with an attached garage is $250 per dwelling unit. The zoning permit cannot be processed until the septic permit and the soil erosion permit have been issued.
  • Additions and accessory buildings. The handout asks for a site plan showing every structure, the well and septic and their distances from lot lines and the road, the footprint and height, an elevation drawing, floor plans for additions and the cost. A new bedroom or new plumbing needs the Health Department first.
  • Sheds without a house. A shed of up to 1,800 square feet for property maintenance is allowed with no house on lots of at least 2 acres in the Agriculture, Conservation or Residential districts; in residential districts a detached building may not be larger than the house footprint.
  • Fences and pools are $50 each.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial and industrial buildings and additions are $2.50 per 100 square feet with a $250 minimum, and a change of use is $250. Projects that disturb more than half an acre need the county’s erosion, sediment and stormwater control permit, and large solar farms, towers and wind systems have their own fees.

What comes before the zoning permit

  • Address. The department runs rural addressing, and new addresses are requested on the county’s 911 address application form.
  • Septic and well. A new home on a private system needs its Health Department septic permit before the zoning permit, and a new well needs its own Health Department permit.
  • Erosion control. Required for every new single- or two-family home and for any project disturbing 5,000 square feet up to half an acre.
  • Floodplain. Development in the floodplain needs a floodplain development permit.
  • Land division. Splits go through the subdivision ordinance or a Plat Act affidavit.

Woodford County permit fees

Fees come from the county’s zoning fee schedule, last revised on December 16, 2025, and are collected by the Zoning Administrator. No zoning permit fee is refunded. Work started without a permit is charged a penalized fee of four times the normal amount.

Rather talk it over?

Call 1-855-478-4290 →
Woodford County zoning permit fees (revised December 16, 2025)
ItemFee
Dwelling with attached garage (per unit)$250 (penalized $1,000)
Additions over 70 sq ft and 8 ft tall$0.15 per sq ft
Detached accessory buildings over 287 sq ft and 8 ft tall$0.15 per sq ft
Commercial / industrial new building or addition$2.50 per 100 sq ft, $250 minimum
Not-for-profit new building$250
In-ground pool / fence / sign$50 each
Change of use / moving a structure$250 / $100
DemolitionNo fee
Solar farm$250 per megawatt
Variance or appeal hearing$60
Special use or rezoning$200 for the first 5 acres plus $10 an acre
Erosion and sediment control permit (Ch. 152)$200
Septic permit (Health Department)$225

Worked example: a 1,200-square-foot detached pole barn on a residential lot is over 287 square feet, so the zoning permit is 1,200 times 15 cents, or $180. A new house on a private septic system pays $250 for the zoning permit, $200 for the erosion control permit and $225 for the septic permit, $675 in county permits before any well permit.

No fee is charged for buildings used for farming or accessory buildings on an operating farm, or for government bodies and government-owned utilities. The erosion control permit is also free for agricultural projects and for projects started by a local government.

Trade permits and who may pull them

With no county building code, Woodford County issues no electrical, mechanical or plumbing permits in unincorporated areas, and its pages describe no county contractor license or registration. The trade rules that do reach rural projects come from the state and the Health Department.

  • Plumbing: new plumbing still has to meet the Illinois Plumbing Code, and plumbers are licensed by the Illinois Department of Public Health; the county handout asks owners adding plumbing or a bedroom to contact the Health Department first.
  • Septic installers: the Health Department registers licensed Illinois private sewage disposal contractors, approves system plans, issues permits and inspects installations.
  • Well drillers: wells are built, modified and sealed under a Health Department permit and the Illinois water well construction and pump installation codes.
  • Septic pumpers: the Health Department posts a list of licensed pumpers.

Projects inside a city or village follow that municipality’s own trade permit rules.

Rather not deal with the Woodford County building department?

Get a free quote →

How to get a permit in unincorporated Woodford County

1. Confirm the parcel is unincorporated

Use the county GIS viewer; municipal parcels go to the city or village.

2. Check the zoning district

Follow the county’s GIS instructions for zoning districts or call the office.

3. Get the septic permit and address

For a new home, obtain the Health Department septic permit and request a 911 address.

4. File the erosion control permit

Contact the Soil and Water Conservation District, then file with the county ($200).

5. Apply for the zoning permit

Bring the site plan, dimensions, use, cost and an elevation drawing to Room 100.

6. Build within the time limits

Start within 90 days and finish within 2 years of the permit.

Review, corrections and what causes delay

Simple applications are usually processed the same day when the drawings and details are complete. Delays come from missing septic or erosion permits (a house permit cannot be processed without them), Health Department appointments, since environmental health staff keep short office hours and are often in the field, and projects that need a variance or special use, which must wait for a Zoning Board of Appeals hearing and, for special uses and rezonings, a County Board decision.

Inspections in Woodford County

Because the county has adopted no building code, it does not carry out building, electrical or plumbing inspections on houses or accessory buildings in unincorporated areas, and it issues no certificate of occupancy. The county’s own checks focus on zoning, setbacks, floodplain and erosion control, and the Zoning Administrator can issue a stop work order, which carries a $100 fee.

The Health Department inspects private sewage systems it permits, investigates sewage complaints and, on request, may provide a diagram of where an existing system sits. Residential septic tanks must be evaluated within three years of installation and at least every five years after that. Disturbed ground on an erosion-control permit must reach final stabilization within six months of completion or occupancy, whichever comes first.

Illinois building code in Woodford County

Woodford County states that it is a non-building-code jurisdiction and has adopted no building code for unincorporated areas. Its floodplain ordinance (Chapter 150) requires new and improved buildings in the floodplain to be built to the flood protection elevation, which is the base flood elevation plus one foot. FEMA’s Community Status Book lists Woodford County’s unincorporated area (community 170730) as participating in the National Flood Insurance Program, with its first flood insurance rate map dated February 1, 1984 and the current map dated September 17, 2010; it has no Community Rating System class.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Woodford County permit FAQs

Does Woodford County issue building permits?

It issues zoning permits for structures in unincorporated areas. The county has adopted no building code, so it does not inspect construction.

How much is a permit for a new house?

The zoning permit is $250 per dwelling unit; add $200 for erosion control and $225 for a septic permit if the house is on a private system.

Do I need a permit for a pole barn or shed?

Yes. The county FAQ lists sheds and pole barns among the projects that need a zoning permit. Detached buildings over 287 square feet and 8 feet tall pay 15 cents a square foot; farm buildings on an operating farm pay no fee.

Do I need a permit to re-roof or replace windows?

No, as long as the structure and the openings’ dimensions are not changed.

Do I need a permit for a fence?

Yes, if it is over 4 feet tall or more than 50% solid; front-yard fences are limited to 48 inches and must be at least half open.

What if I build without a permit?

The permit is issued at four times the normal fee, for example $1,000 instead of $250 for a house.

Who handles permits in Eureka, Metamora or Roanoke?

The city or village itself; the county zoning office covers only unincorporated land.

How long do I have to build?

Construction must start within 90 days of the permit and be finished within 2 years.

Woodford County permit records and official resources

The Building and Zoning Department keeps zoning permit, variance and plat records for unincorporated land, and the Health Department keeps septic and well records. Zoning Board of Appeals agendas, minutes and its 2026 meeting schedule are posted on the county website, and records requests use the county’s Freedom of Information forms.

Inspections are where schedules slip.

Get a free quote →

Simplify Woodford County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Woodford County sooner?

Let Alliance prepare, file, and track your Woodford County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Woodford County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.