In unincorporated Warren County, and in any town without its own zoning ordinance, the county’s Building and Zoning office issues the permit for every non-agricultural building, addition or structural alteration. The office is in the County Clerk’s area on the second floor of the courthouse at 100 W. Broadway, Monmouth, open 9 a.m. to noon on Mondays, Wednesdays and Fridays (309-760-4046). Permits cost $25 for projects up to $5,000 and are scaled to valuation above that, while the Warren County Health Department permits septic systems and wells.
What requires a permit in unincorporated Warren County?
The county zoning code, Chapter 150, sets the rule in section 150.152: no non-agricultural building or structure may be erected, added to or structurally altered until the Zoning Administrator has issued a permit and the building and inspection fees are paid. The code applies to the whole county outside cities, villages and towns that have their own zoning ordinance, and inside any that do not.
County permit needed
- New houses, garages and other non-farm buildings
- Additions and structural alterations
- Agricultural buildings on parcels under 5 acres (no fee)
- Grading and site plans the office reviews
- Solar energy systems, priced by kilowatts
- Changes of use and occupancy of new non-farm buildings (certificate of occupancy)
No county building permit
- Agricultural buildings on parcels of 5 acres or more, which get a no-fee zoning certificate after inspection instead
- Work inside a city or village with its own zoning ordinance
The Zoning office also inspects homes for a Certificate of Continued Occupancy, which the county requires before any residential property is sold or rented, and enforces the county’s construction and property maintenance rules.
What the county decides and what the state holds
The county board sets zoning districts, permit fees, the farm-dwelling density limits and the wind and solar rules; the Health Department enforces the county private sewage disposal ordinance alongside the state Private Sewage Disposal Licensing Act and code. Section 150.152 of the county code says permits for buildings used for agricultural purposes “shall be issued free of any charge”, citing the state Counties Code (55 ILCS 5/5-12001), which is why farm structures pay nothing here. Plumbing follows the Illinois Plumbing Code with state-licensed plumbers, and roofers hold a state license.
Warren County building department: who handles permitting
For land outside the towns, three county offices cover a building project. The building permit form calls the zoning office the Warren County Building and Zoning Department; the county’s website lists it as the Zoning Department, currently run by an interim zoning officer. To check whether a parcel is incorporated, look at the county’s zoning maps or ask the zoning office.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| Building and Zoning (building permits, zoning, occupancy certificates) | Courthouse, second floor (County Clerk’s office), 100 W. Broadway, Monmouth, IL 61462; 309-760-4046; fax 309-734-7406; warrencountyzoning@warrencountyil.gov; 9 a.m. to noon Monday, Wednesday and Friday |
| Warren County Health Department (septic, wells) | 240 South Main Street, Monmouth; 309-734-1314, fax 309-734-1315; Monday to Thursday, 8 a.m. to 4 p.m. |
| Highway Department (county roads, bridges, oversize permits) | 833 South 8th Street, Monmouth; 309-734-8518; Monday to Friday, 7:30 a.m. to 4 p.m. |
| Courthouse main line | 309-734-8592 |
Cities and villages in Warren County
The county’s towns are the city of Monmouth (population 8,599), the county seat, and the villages of Roseville (843), Kirkwood (650), the Warren County part of Alexis (425), Little York (267) and the Warren County part of Avon (4 residents). Each is a separate government. Where a town has adopted its own zoning ordinance, the county code does not apply there; where it has not, the county zoning code applies inside the town as well. The county’s pages do not list which towns have their own zoning, so ask the town hall first and the county zoning office second.
Warren County permit types
The county uses one Application for Building Permit for houses, duplexes, multi-family buildings, additions, signs and other structures. It asks for the street address and legal description (section, township, lot and subdivision), the owner and general contractor, the size and type of structure, the proposed use and the project valuation, and it must come with a drawing showing the lot’s dimensions and the exact location of every proposed building. The applicant also certifies that the owner has paid all taxes and other debts owed to the county.
Residential permits
- Farm-zone homes: in the A-1 Agricultural District, non-farm houses are limited to one per 40 contiguous acres and four per 160 acres, each on a lot of at least 1 acre, with the remaining land placed under an agricultural preservation easement that names the county. Non-farm houses may also be grouped under the code’s cluster development rules.
- R-1 district homes: a lot of at least 1 acre and 150 feet wide, a front yard of 75 feet on federal and state roads and 50 feet on others, 5-foot side yards, a rear yard of 20% of the lot depth, and no more than 30% lot coverage.
- Home sales and rentals: a Certificate of Continued Occupancy inspection before the sale or rental of any residential property.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Business and industrial buildings use the same application and valuation fee, in the B-1 to B-3 business and I-1 and I-2 industrial districts. New non-agricultural buildings need a certificate of occupancy before use, and the application for it must be made and approved before the permit to build is issued. Solar farms are permitted by kilowatt (for example $5,000 for 1,001 to 2,000 kilowatts), and wind energy systems need construction plans sealed by an Illinois structural engineer and special inspections under section 150.305 of the zoning code.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning: check the district on the county zoning maps; a rezoning, special use exception or variance goes to the Zoning Board of Appeals, with a $150 non-refundable fee plus mailing, publication, sign and site-visit costs.
- Septic and well: a Health Department septic permit, with soil analysis results attached, and a well permit if the site needs a private well.
- Road access: the Highway Department maintains 173 miles of county highways and 24 inventoried bridges, and by law the County Engineer prepares the plans for every bridge and culvert built on county or road district highways, so a new crossing or culvert on a road starts there. Oversize and overweight hauling permits also come from the Highway Department.
- Floodplain: unincorporated Warren County takes part in the National Flood Insurance Program, with flood maps dated August 10, 2021.
Warren County permit costs and fees
Building permits are priced on project valuation under the county’s posted zoning permit fee schedule:
| Project valuation | Permit fee |
|---|---|
| $0–$5,000 | $25 |
| $5,001–$30,000 | $25 plus $4 per $1,000 over $5,000 |
| $30,001–$50,000 | $125 plus $3.50 per $1,000 over $30,000 |
| $50,001–$75,000 | $195 plus $3 per $1,000 over $50,000 |
| $75,001–$200,000 | $270 plus $2.50 per $1,000 over $75,000 |
| $200,001–$500,000 | $582.50 plus $2 per $1,000 over $200,000 |
| Over $500,000 | $1,182.50 plus $1 per $1,000 over $500,000 |
Rather talk it over?
Call 1-855-478-4290 →The bands join up, so the arithmetic is simple. A $250,000 house costs $582.50 plus $2 for each of the 50 thousands over $200,000, or $682.50; a $20,000 garage costs $25 plus $4 times 15, or $85. Agricultural buildings pay nothing.
| Item | Fee |
|---|---|
| Solar energy system, 0–10 kW | $100 |
| Solar, 11–50 kW / 51–100 kW | $250 / $500 |
| Solar, 101–500 kW / 501–1,000 kW | $1,000 / $2,500 |
| Solar, 1,001–2,000 kW | $5,000 |
| Solar, over 2,000 kW | $100 for each additional 0–100 kW |
| Rezoning, special use exception or variance | $150 non-refundable, plus actual mailing, publication and sign costs |
| Additional site visit | $25 each |
| Septic permit (Health Department) | $150 contractor installed; $250 homeowner installed |
Trade permits and who may pull them
The county’s permit form and fee schedule show a single building permit with no separate county electrical, plumbing or mechanical permit, and the county publishes no contractor license or registration. The application lists only a general contractor and can be signed by the owner of record or an agent the owner authorizes.
- Septic systems: the Health Department’s application asks for the contractor’s license number, and charges $150 when a contractor installs the system and $250 when the homeowner does. The owner and contractor both sign that the work will follow the state private sewage act and code and the county ordinance, and the homeowner accepts responsibility for maintenance and records for the life of the system.
- Wells: the Health Department issues water and well permits and takes water samples.
- Plumbing: follows the Illinois Plumbing Code, done by state-licensed plumbers.
- Roofing: roofing contractors carry a state license.
Inside Monmouth and the villages, any trade permits or contractor registration are each town’s own.
Rather not deal with the Warren County building department?
Get a free quote →How to get a building permit in Warren County
Check that the parcel is outside the towns, and find its zoning district on the county zoning maps.
If the lot is too small or the use not allowed, apply for a rezoning, special use or variance before the Zoning Board of Appeals.
Have a soil analysis done and file the Health Department’s sewage disposal application.
Prepare two copies of a scaled plot plan showing the lot’s dimensions and the size and location of every building.
Bring the application, plot plan and fee to the zoning office during its Monday, Wednesday and Friday morning hours, or contact it by email.
Start within 180 days, call for the zoning inspection, and get the certificate of occupancy before moving in.
Review, corrections and what causes delay
The zoning office checks setbacks, lot size and use against the district rules; a permit cannot be issued for work that would break the zoning code unless the Zoning Board of Appeals orders it. With the office open three mornings a week, calling ahead saves a trip. Under the code and forms, a permit is held up by a lot split off farmland without meeting the 40-acre density rule, unpaid county taxes, a missing plot plan, or a septic application without soil analysis results. One approved copy of the plot plan is returned with the permit.
Inspections in Warren County
The county’s code and zoning page describe these inspections:
- Certificate of occupancy: required before a new non-agricultural building is used or the use of land or a building changes, and issued only after the work is completed, inspected and approved by the Zoning Administrator. The county keeps a record of every certificate.
- Farm buildings: on 5 acres or more, the no-fee zoning certificate is issued after an inspection showing the building meets setback lines.
- Sales and rentals: the Certificate of Continued Occupancy inspection comes before any residential property is sold or rented.
- Septic: the Health Department must be told 48 hours before installation and must inspect the system before it is backfilled.
Under section 150.215(E) of the code, a permit lapses if work does not start within 180 days or stops for 180 days, and a new permit is then needed.
Building rules in Warren County
The county’s land-use rules are in Chapter 150, the Zoning Code, posted as updated through August 26, 2022, with its zoning maps and a separate wind farm ordinance. The zoning office also enforces construction and property maintenance rules in its inspections. FEMA’s Community Status Book lists Warren County (community 170673, unincorporated areas) as participating in the National Flood Insurance Program, in the regular program since May 25, 1984, with its current flood map dated August 10, 2021.
Want this handled start to finish?
Get a free quote →Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Warren County permit records and official resources
The zoning office keeps permit applications and occupancy certificates, and copies of certificates are given on request to owners and tenants of the property. Other records go through a written Freedom of Information Act request by mail, fax, email (with FOIA in the subject line) or in person; a form is optional. The first 50 black-and-white pages are free and later pages cost 15 cents each, and the county answers within five working days. The Highway Department has its own FOIA request form.
- Zoning Department (hours, ZBA, FOIA)
- Application for building permit
- Zoning permit fee schedule
- Zoning Code, Chapter 150
- Zoning maps
- Highway Department
- FOIA request form
- Warren County Health Department
- Environmental health applications
- Sewage disposal permit application
- FEMA Community Status Book, Illinois
Inspections are where schedules slip.
Get a free quote →Warren County permit FAQs
Do I need a county building permit in rural Warren County?
Yes, for any non-agricultural building, addition or structural alteration outside the towns with their own zoning, from the county Building and Zoning office.
How much does a Warren County building permit cost?
$25 up to $5,000 of valuation, then a sliding scale: a $250,000 house costs $682.50.
Do farm buildings need a permit?
On parcels under 5 acres, yes, but at no charge. On 5 acres or more no building permit is needed, though the building gets a free zoning certificate after inspection.
When is the zoning office open?
Mondays, Wednesdays and Fridays from 9 a.m. to noon, on the courthouse’s second floor; call 309-760-4046.
Can I build a house on farmland?
In the A-1 district, one non-farm house per 40 contiguous acres and no more than four per 160 acres, each on at least 1 acre, with an agricultural preservation easement on the rest.
Do I need an inspection to sell or rent a house?
Yes. The county requires a Certificate of Continued Occupancy before any residential property is sold or rented.
How much is a septic permit?
$150 when a contractor installs the system and $250 when the homeowner does, from the Warren County Health Department.
Who handles permits in Monmouth?
The City of Monmouth is a separate government, so start at city hall; the county permit covers unincorporated land and any town without its own zoning ordinance.
Simplify Warren County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Warren County sooner?
Let Alliance prepare, file, and track your Warren County permits while your crew stays on the job.
More Illinois permitting guides
Knox County
Read guide →McDonough County
Read guide →Mercer County
Read guide →Warrenville Building Permit Guide
Read guide →Washington Building Permit Guide
Read guide →Washington County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Warren County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.