In unincorporated Mercer County, building permits and zoning come from Mercer County Zoning, 100 SE 3rd Street, Aledo (zoning@mercercountyil.org, 309-525-3799), a part-time office that asks for up to 48 hours to answer. A building permit costs a $25 application fee plus $5 for each $1,000 of the cost of improvements, and a certificate of occupancy $1 per $1,000 of valuation. Wells and septic systems are permitted by the Mercer County Health Department, and questions about land inside Aledo or another city or village go to that city or village hall.
What requires a county permit in unincorporated Mercer County?
Mercer County zones its unincorporated land, and building permits are issued by the zoning officer under the Mercer County Zoning Ordinance. The building permit application asks for the dimensions of the lot or tract, the exact location of every proposed building and structure on a drawing, and a description of the proposed buildings, structures, signs, changes in use or other improvements, which is how the zoning officer checks a project against the district rules. Towers and wind turbines are charged by height.
County Zoning
- Building permits for structures and improvements
- Certificates of occupancy (Zoning Ordinance, pages 69–70)
- Rezonings, conditional uses and variances
- Subdivision plats under the Illinois Plat Act
- Solar and wind energy facilities under the county’s solar and wind ordinances
- Nuisance complaints
Other county offices
- Wells, septic systems and sewer: Mercer County Health Department
- Access (driveway), utility, drainage, signage and overweight permits on county highways: County Engineer
- Notice when rezoning out of agricultural use: Mercer County Soil and Water
Land inside a city or village is not under county zoning. The county keeps every parcel’s zoning in its property tax software; if no zoning shows for the current tax year, the parcel may be inside city limits, and the city or village hall is the place to ask.
What Mercer County decides and what the state holds
The county sets its own zoning districts, permit fees, solar and wind rules and plat procedures; the County Board makes the final decision on rezonings, conditional uses and variances after the Zoning Board of Appeals recommends. Septic and well rules are run locally by the Health Department under an Illinois Department of Public Health grant program, plats follow the Illinois Plat Act, and plumbers and roofing contractors are licensed by the state.
Short on time to read all of this?
Get a free quote →Mercer County building department: who handles permitting
Mercer County Zoning issues building permits, certificates of occupancy and zoning approvals for the unincorporated county, and its zoning officer also collects the platting officer fee and handles nuisance complaints. The office is part time, so expect up to 48 hours for a reply to calls and e-mails on weekdays. The Zoning Board of Appeals hears zoning changes, conditional uses and variances at the courthouse, and the County Board decides them.
| Office | Contact |
|---|---|
| Mercer County Zoning | 100 SE 3rd Street, Aledo, IL 61231; zoning@mercercountyil.org; 309-525-3799 (part-time office) |
| Mercer County Health Department (wells, septic, sewer) | 305 NW 7th Street, Aledo; 309-582-3759; Monday to Thursday, 8 a.m. to 5 p.m. |
| County Engineer / Highway Department | 1630 Hwy 17, P.O. Box 167, Aledo; 309-582-2715; weekdays 7 a.m. to 3:30 p.m. |
| Mercer County Soil and Water | 308 SE 8th Avenue, Aledo; 309-582-5153 ext. 3 |
| Municipality | Where to ask about building and zoning |
|---|---|
| Aledo (city, pop. 3,506) | Aledo city hall (county zoning does not cover land inside city limits) |
| Keithsburg (city, 546), New Boston (city, 600) | City hall |
| Viola (836), Sherrard (691), Matherville (689), Windsor (649), Joy (357), Seaton (208), North Henderson (159) | Village hall |
| Alexis (330 in Mercer, 425 in Warren County), Reynolds (37 in Mercer, 458 in Rock Island County) | Village hall |
| Unincorporated land | Mercer County Zoning; Health Department for wells and septic |
Mercer County permit types
All county zoning applications can be e-mailed to the zoning office, but fees must be mailed to Mercer County Zoning at 100 SE 3rd Street, Aledo; the office mails the permit once payment arrives. Every application must be complete or it is returned, which can push back a hearing date.
Not sure this scope needs a permit?
Get a free quote →Residential permits
- Building permit. For proposed buildings, structures and other improvements on unincorporated land, with a drawing showing lot dimensions and the location of all proposed buildings.
- Certificate of occupancy. Required under the Zoning Ordinance (pages 69–70) and charged at $1 per $1,000 of the structure’s valuation.
- Well and septic permits. From the Health Department, which inspects and permits private onsite wastewater systems and new and existing water wells.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and industrial buildings use the same county building permit, charged on the cost of improvements. Uses that are not allowed outright in a district need a conditional use permit ($200 the first time and $150 a year to renew; if it lapses the whole process starts again) or a rezoning. Solar energy facilities follow the county’s amended solar ordinance (final version dated January 11, 2024), and wind projects follow the wind ordinance as amended in 2026; towers and turbines pay $25 per foot.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning check. Confirm the district on the property tax site before you apply.
- Rezoning. A $200 application, a survey, notice to owners within 200 feet (residential), 300 feet (business or manufacturing) or a quarter mile (agricultural or special districts), a newspaper notice at least 15 days before the hearing, a report of proceedings and an amending ordinance for the County Board. The zoning page notes that tracts of 15 acres or more do not have to be rezoned, while smaller tracts do, and that Soil and Water must be notified when land leaves agricultural zoning.
- Variance. $125, no survey needed; the owner pays for the newspaper notice and the zoning officer writes to adjoining owners.
- Plats. The first split of a parcel can be any size without a subdivision plat; after that, any lot under 5 acres needs a surveyor’s subdivision plat and the $300 platting officer fee.
- Road access. Driveways and other work on a county highway need a permit from the County Engineer.
Rather talk it over?
Call 1-855-478-4290 →Mercer County permit fees
Fees are those printed on the county zoning page:
| Item | Fee |
|---|---|
| Building permit application | $25 |
| Building permit, cost of improvements | $5 per $1,000 |
| Towers and turbines | $25 per foot |
| Certificate of occupancy | $1 per $1,000 of the structure’s valuation |
| Zoning change (rezoning) application | $200, non-refundable |
| Conditional use | $200 first time; $150 annual renewal |
| Variance | $125 plus the newspaper notice |
| Platting officer (subdivision plat) | $300 |
Checks are made out to “Mercer County Zoning”, and rezoning and conditional use fees are paid when the application is filed.
Worked example. A new house with $300,000 of improvements on rural land pays the $25 application fee plus 300 × $5 = $1,500, or $1,525 for the building permit; the certificate of occupancy on the same $300,000 valuation adds 300 × $1 = $300. Well and septic permit fees are set separately by the Health Department.
Trade permits and who may pull them
Mercer County’s zoning page lists no separate county electrical, plumbing or mechanical permits and no county contractor registration; the county permit is a zoning-based building permit and certificate of occupancy. Well and septic work goes through the Health Department, whose environmental health program regulates private onsite wastewater systems and water wells. Plumbing in Illinois is governed by the state plumbing code and done by plumbers licensed through the Illinois Department of Public Health, and roofing contractors need a state license. Inside Aledo and the other municipalities, ask the city or village about its own trade permits and contractor rules.
Rather not deal with the Mercer County building department?
Get a free quote →How to apply for a Mercer County building permit
Look up the zoning on the county’s property tax site; no zoning listed may mean the parcel is inside a town.
File any rezoning, conditional use or variance at least 30 days before the Zoning Board of Appeals meeting.
Contact the Health Department (309-582-3759) for the well and septic permits a rural site needs.
Show the lot dimensions and the exact location of every proposed building.
Send the form to zoning@mercercountyil.org and mail the check to 100 SE 3rd Street, Aledo.
The office mails the permit after payment; apply for the certificate of occupancy when the building is complete.
Review, corrections and what causes delay
The office is part time, so allow up to 48 hours for answers. Incomplete applications are returned and can postpone a hearing. Zoning changes can take up to three hearings: a first review by the Zoning Board of Appeals and zoning officer, a public hearing, and the County Board decision, which usually comes at its meeting on the first Tuesday of the following month. The applicant must attend every public hearing. Zoning officer applications are reviewed with the State’s Attorney’s office, and filing does not guarantee an outcome.
Inspections and occupancy in Mercer County
The county’s zoning page does not describe a schedule of building inspections; it sets out a certificate of occupancy requirement under pages 69 and 70 of the Zoning Ordinance, charged at $1 per $1,000 of the structure’s valuation and issued through the zoning office. Well and septic systems are inspected by the Health Department’s environmental health staff, who handle well and septic inspections and permitting. Work in a county highway right-of-way is reviewed under the County Engineer’s access, utility and drainage permits, and the Highway Department inspects all county and township bridges.
The Zoning Board of Appeals meets at 7 p.m. on the second floor of the courthouse in Aledo, usually on the fourth Thursday; its 2027 dates run from January 28 to December 16, with the November and December meetings moved to the third Thursday for the holidays.
Want this handled start to finish?
Get a free quote →Codes and flood maps in Mercer County
Mercer County regulates unincorporated land through its Zoning Ordinance, its amended solar ordinance and its wind ordinance; the zoning page does not name a building code edition, so ask the zoning officer what construction standards apply to your plans. FEMA’s Community Status Book lists Mercer County (community 170806, unincorporated areas) as a participating community in the National Flood Insurance Program, with a flood insurance rate map first issued January 3, 1986 and a current map dated April 19, 2010.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Mercer County building permit FAQs
How much is a building permit in Mercer County?
$25 to apply plus $5 for each $1,000 of the cost of improvements; towers and turbines pay $25 per foot.
Can I apply by e-mail?
Yes. Applications can be e-mailed to zoning@mercercountyil.org, but the fee must be mailed to the zoning office, which then mails the permit.
Who issues septic and well permits?
The Mercer County Health Department, 305 NW 7th Street, Aledo (309-582-3759).
When does the Zoning Board of Appeals meet?
Usually the fourth Thursday of the month at 7 p.m. at the courthouse; file at least 30 days before.
How much is a variance?
$125, plus the cost of the newspaper notice, which the property owner pays.
Does the county issue permits in Aledo?
No. Parcels inside Aledo or any other city or village go to that municipality.
Do I need a subdivision plat to split my land?
Not for the first split; after that, any parcel under 5 acres needs a subdivision plat and a $300 platting officer fee.
Mercer County permit records and official resources
Mercer County has no single FOIA officer: send a records request for permits to the department that holds them, such as the zoning office. Parcel and zoning information is on the county’s property tax site, and County Board agendas and minutes are posted on the county’s documents pages.
Inspections are where schedules slip.
Get a free quote →- Mercer County Zoning: permits, fees and hearings
- Mercer County property tax and zoning lookup
- Mercer County Health Department
- Health Department environmental health services
- County Engineer and Highway Department
- County agendas and minutes
- FOIA requests
- FEMA Community Status Book, Illinois
Simplify Mercer County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Mercer County sooner?
Let Alliance prepare, file, and track your Mercer County permits while your crew stays on the job.
More Illinois permitting guides
Rock Island County
Read guide →Warren County
Read guide →Henry County
Read guide →Midlothian Building Permit Guide
Read guide →Minooka Building Permit Guide
Read guide →Mokena Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Mercer County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.