Richland County, Illinois Building Permit Guide

To get a building permit in Richland County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Unincorporated Richland County has no zoning ordinance and no zoning official; the County Engineer in Olney handles floodplain, road entrance and utility questions.

Authority: County Engineer (floodplain, roads)Zoning: None in unincorporated areasPhone: 618-392-3141
County zoning
NoneMemorandum of November 5, 2025
Floodplain administrator
County Engineer618-392-3141
New entrance culvert
Exact pipe costNo charge for labor or equipment
Solar farm permit
$5,000 per MWCounty Board special use permit

Richland County has no zoning ordinance and no zoning official for its unincorporated areas, according to a memorandum from the County Engineer dated November 5, 2025, so there is no county building or zoning permit for an ordinary house or shed outside the towns. What the county does regulate runs through the Richland County Engineer at the Highway Department, 4334 N. Meridian Road, Olney (618-392-3141): floodplain development, entrances and utilities on county highways, mobile home parks and commercial solar farms. The memorandum notes that Olney, Noble, Parkersburg, Calhoun and Claremont can, by statute, extend their zoning 1.5 miles outside their limits, and sends zoning questions in or near a town to its municipal clerk.

What requires a permit in unincorporated Richland County?

Because the county has no zoning ordinance, it sets no general setbacks, lot sizes or permitted uses and issues no county building permit for a home, garage or farm building outside the municipalities. The County Engineer’s memorandum lists the ordinances the county does have: a solar farm development ordinance, a floodplain construction ordinance, a setback line ordinance, a subdivision ordinance and a trailer park operation ordinance.

County approval needed

  • Construction or other development in a mapped floodplain
  • A new driveway entrance, or extending one, on a county highway
  • Utilities in a county highway right-of-way, by written request
  • Building or altering a mobile home park
  • Commercial solar farms and solar storage facilities (special use permit)
  • Subdividing land under the county subdivision regulations

No county zoning or building permit

  • Houses, garages and sheds outside the towns’ reach and outside mapped flood zones
  • Farm buildings
  • Solar power generated for use on the same premises, which the solar ordinance does not cover

The county code’s flood chapter, a resolution passed July 9, 2009 to apply for participation in the National Flood Insurance Program, assures FEMA that the county will enact, as necessary in flood hazard areas, land-use controls that include permits for all proposed construction or other development, so it can tell whether the work lies in the floodplain, and review of whether the other required state and federal permits have been obtained. The floodplain construction ordinance the memorandum mentions is not in the posted code book, so ask the County Engineer before building near a mapped flood zone.

Short on time to read all of this?

Get a free quote →

What the county decides and what the state holds

The county board decides which land-use ordinances exist; for now that means floodplain, setback-line, subdivision, mobile home park and solar farm rules rather than countywide zoning. Statewide pieces still apply to the work itself: plumbing follows the state plumbing code and is done by licensed plumbers, roofers hold state licenses, and the plumbing in a mobile home park must be inspected and approved by a licensed plumber.

Richland County building department: who handles permitting

The Richland County Engineer, Danny J. Colwell, P.E., runs the Highway Department and serves as the county floodplain administrator. The County Engineer wrote the county’s zoning memorandum and takes written requests for utilities and entrances on county highways. The county board’s Road and Bridge Committee reviews highway matters at 6 p.m. on the first Thursday of each month, and the full board meets at 7 p.m. on the second Thursday.

Richland County offices for building projects
OfficeContact
County Engineer and Highway Department (floodplain, entrances, utilities, mobile home parks)4334 N. Meridian Road, Olney, IL 62450; 618-392-3141; Monday to Friday 7:30 a.m. to 4 p.m.
County Clerk and Recorder (board minutes, land records, permit and license fees under the code)Courthouse, 103 W. Main Street, Olney, IL 62450; 618-392-3111; countyclerk@richlandcounty.illinois.gov; Monday to Friday 8 a.m. to 4 p.m.
Township Highway Commissioners (township roads)Nine township road districts; contacts listed on the county website

Cities and villages

Richland County has five incorporated municipalities: the City of Olney (population 8,347) and the villages of Noble (609), Parkersburg (184), Claremont (158) and Calhoun (153). The county memorandum notes that, by statute, these municipalities can extend their zoning 1.5 miles outside their corporate limits, and it directs zoning questions in or near a town to that town’s municipal clerk. Building permits inside a municipality are a matter for that municipality.

The Richland County TB and Public Health Office at 208 E. Main Street, Olney (618-392-6241) lists immunizations, tuberculosis testing and other clinical services; its published service list does not include septic or well permits, and the county’s pages do not name the office that permits private sewage systems.

Richland County permit types

Instead of one building permit, Richland County has a handful of specific approvals tied to roads, floods and particular land uses.

Not sure this scope needs a permit?

Get a free quote →

Residential permits

  • Floodplain development: before building in a flood hazard area, contact the County Engineer as floodplain administrator; the flood zones can be viewed on the county’s web-based GIS by turning on the floodplain layer.
  • Driveway entrances: ask the County Engineer for a new entrance or an extension on a county highway; on a township road, ask that township’s highway commissioner.
  • Utility lines: make a written request to the County Engineer to place utilities in a county highway right-of-way, or to the township highway commissioner for a township road.
  • Near a town: within 1.5 miles of Olney or a village, ask the municipal clerk whether the town’s zoning reaches your lot.

Commercial permits

  • Mobile home parks: no building permit to construct a mobile home park may issue until the County Engineer approves the application, which must include the applicant, the tract, sewage, garbage, water and fire protection facilities, lighting, plot and building plans, and an affidavit.
  • Commercial solar farms: Ordinance 2022-10-13, revised January 8, 2026, governs solar farms built for utility purposes; they need a special use permit decided by the county board after a public hearing.
  • Subdivisions: the county subdivision regulations, adopted by reference in 1966, apply to land divisions.

What comes before construction

  • Flood maps: FEMA’s first flood insurance rate map for unincorporated Richland County took effect July 21, 2026, and it is marked as showing no base flood elevations.
  • Road access: arrange the entrance culvert with the Highway Department before building a driveway onto a county highway.
  • Utility locates: the solar ordinance requires a call to JULIE, the Illinois utility-locating service, before digging.

Richland County permit fees

There is no county building or zoning permit fee for ordinary construction, because there is no county building or zoning permit. The fees the county does set are tied to its specific ordinances and policies.

Rather talk it over?

Call 1-855-478-4290 →
Richland County fees by ordinance or policy
ItemFee
New entrance culvert on a county roadExact cost of the culvert; no charge for labor, equipment or overhead
Rock for a new entrance (on request)The county’s purchase cost
Lengthening an existing entrance culvertAt the owner’s expense
Mobile home park application$25, non-refundable, paid to the County Clerk
Mobile home park annual license$50, due by April 30
Mobile home park annual inspection$10 or $1 per space, whichever is greater
Commercial solar farm special use permit$5,000 per megawatt AC, non-refundable
Commercial solar farm annual inspection$10,000
Solar farm administrative fee$10,000 every tenth anniversary of the permit

Worked example: a 5-megawatt commercial solar farm pays a $25,000 special use permit fee with its application, then $10,000 each year for inspection. A homeowner opening a new field or driveway entrance onto a county highway pays only the price of the culvert pipe the county installs, plus any rock requested. A solar farm whose fence is not kept secure or whose weed and grass control plan is not followed can be fined up to $750 per violation per week, and solar applicants must post decommissioning security set by a mutually agreed Illinois-licensed engineer, never less than $1,000 per acre.

Trade permits and who may pull them

Richland County issues no county electrical, plumbing or mechanical permits and registers no contractors on its published pages. Trade rules that reach unincorporated property come from the county’s specific ordinances and from state licensing:

  • Mobile home park plumbing: the code requires each park’s plumbing to be inspected and approved by a licensed plumber under state codes, and water and sewage system plans to be approved by the state Department of Public Health.
  • Solar farms: new solar generation facilities must be installed by a qualified person as the state’s Future Energy Jobs Act defines it, foundations must be certified by an engineer, and power and communication lines are buried except where technical or physical constraints, such as shallow bedrock or watercourses, make above-ground lines more practical.
  • Plumbing and roofing generally: plumbers and roofing contractors hold state licenses.

Rather not deal with the Richland County building department?

Get a free quote →

Inside Olney and the villages, ask the municipal clerk about local permits and any contractor registration.

How to start a building project in Richland County

1. Check whether the lot is in or near a town

Inside or within 1.5 miles of a municipality, ask its clerk about zoning and permits.

2. Check the flood map

Open the county GIS, turn on the floodplain layer and see whether the building site is in a flood zone.

3. Call the County Engineer if it is

Floodplain development goes through the County Engineer at 618-392-3141.

4. Arrange road access

Ask the County Engineer for a county highway entrance, or the township commissioner for a township road.

5. Plan utilities

Send a written request before placing any line in a road right-of-way.

6. Special uses

Mobile home parks and solar farms need the County Engineer’s or county board’s approval first.

Review, corrections and what causes delay

An ordinary home gets no county plan review; the county steps are road access and, in a flood area, floodplain review by the County Engineer. Entrances that need more than a standard round culvert require a written agreement with the county before installation. Solar farm applications follow a fixed timetable: a complete application, a public hearing within 45 days of filing with notices mailed 15 to 30 days ahead, and a board decision within 30 days after the hearing.

Inspections in Richland County

With no county building code program, there are no county framing or final building inspections for houses in unincorporated areas. The inspections the county does make are tied to its ordinances:

  • Mobile home parks: the County Engineer or a representative inspects a newly built park before the County Clerk issues its license, and then at least twice a year while it is licensed.
  • Floodplain: the 2009 resolution has the county keep records of the lowest-floor elevation of new or substantially improved buildings in flood hazard areas and any floodproofing certificates.
  • Solar farms: an annual inspection, paid for by the $10,000 yearly fee.
  • County roads: seasonal weight limits apply on county highways from January 15 to April 15, which affects heavy deliveries to rural building sites.

Want this handled start to finish?

Get a free quote →

Illinois building code in Richland County

FEMA’s Community Status Book lists Richland County (community 170995, unincorporated areas) as participating in the National Flood Insurance Program. The Community Status Book dates the county’s entry to August 18, 2009, and its first flood insurance rate map, effective July 21, 2026, is also its current map, marked as having no base flood elevations.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Permit search and official resources

The county website’s FOIA link leads to the County Clerk and Recorder, who keeps the county board’s agendas and minutes and the land records; floodplain and road records sit with the County Engineer. The county posts its code books, the solar ordinance and the zoning memorandum under Documents and Forms.

Inspections are where schedules slip.

Get a free quote →

Richland County permit FAQs

Do I need a county building permit for a house in rural Richland County?

No county building or zoning permit exists for unincorporated land; the county has no zoning ordinance. Floodplain sites and county road entrances still need the County Engineer.

Who is the floodplain administrator?

The Richland County Engineer, at the Highway Department in Olney, 618-392-3141.

How do I get a driveway entrance on a county highway?

Ask the County Engineer. The county installs the culvert, charges only its exact cost and maintains it afterward.

Does Olney’s zoning reach outside the city?

The county memorandum notes that municipalities may extend zoning 1.5 miles by statute; ask the Olney city clerk about your lot.

How much is a solar farm permit?

$5,000 per megawatt AC for the special use permit, plus $10,000 a year for inspection.

Can I build a mobile home park?

Only with the County Engineer’s approval, a $25 application fee, and a $50 annual license.

Simplify Richland County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Richland County sooner?

Let Alliance prepare, file, and track your Richland County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Richland County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.