To get a building permit in O'Fallon, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

O’Fallon’s Building and Inspections Division, part of the Community Development Department on the second floor of City Hall, issues building, zoning, electrical and plumbing permits inside the city and runs its occupancy permit program.

Authority: O’Fallon Building and Inspections DivisionPermit fee: Value x 0.004, $50 minimum for homesPhone: 618-624-4500, ext. 4
Permit office
Community Development255 S. Lincoln Ave., 2nd floor
Building fee
0.004 x value$50 minimum for homes
Occupancy permit
$75Homes, since May 1, 2025
Inspections
24 hours’ noticeSame day if called by 10 a.m.

In O’Fallon, Illinois, permits come from the Building and Inspections Division of the Community Development Department at 255 S. Lincoln Avenue, second floor (618-624-4500, ext. 4), whose Building Official is Chad Truran. A residential building permit is the construction value times 0.004, with a $50 minimum, plus a $20 occupancy fee and a $35 zoning fee for a new home, and a $75 occupancy permit is needed whenever a home changes owner or occupant without a current permit.

What requires a building permit in O’Fallon?

O’Fallon requires a building permit before anyone renovates, remodels or changes the use of a property, and the same residential form doubles as the zoning permit for new homes, additions, basement finishes, decks, pergolas and patio covers, pools and hot tubs, sheds and electrical or plumbing-only jobs. Separate permits cover electrical work before rewiring or significant remodeling, plumbing that is renovated or added, demolition of any structure and every sign. A solar installation with no structural changes can go in on an electrical permit alone.

Building permit

  • New homes, additions, remodels and basement finishes
  • Decks, pergolas and patio covers
  • Sheds and accessory buildings of 200 sq ft or more
  • Pools, spas and hot tubs holding over 24 inches of water
  • Fences taller than 6 feet
  • Change of use
  • Demolition and signs

Zoning permit only

  • Sheds of 101 to 199 sq ft

A fence over 6 feet counts as an accessory structure, so it needs a building permit and must meet accessory-structure setbacks. Pools count as accessory structures too and must sit at least 3 feet from side and rear lot lines. Before a demolition permit is approved, neighbors must be notified and every utility company must give a written release.

What O’Fallon decides and what the state holds

The city adopts its own codes by ordinance. Since January 1, 2026, under Ordinance 4348, it enforces the 2021 International Building, Residential, Fire, Property Maintenance, Existing Building, Mechanical, Fuel Gas and Swimming Pool and Spa Codes and the 2020 National Electrical Code, with local changes. The city’s codes page also lists the Illinois Energy Conservation Code, the Illinois Plumbing Code and the Illinois Accessibility Code. Paper copies of the adopted ICC codes can be read at the City Clerk’s office and the O’Fallon Public Library.

O’Fallon building department: who handles permitting

The Building and Inspections Division of Community Development handles residential and commercial building permits, plan review and inspections, the occupancy permit and property maintenance program, the Crime-Free Rental Housing Program, code complaints and floodplain management. Chad Truran, C.B.O., is the city’s Building Official. The Planning and Zoning Division in the same department checks setbacks, heights and lot coverage on every building application, coordinates site plan review with the Engineering, Fire and Public Safety Departments, handles home-based businesses and supports the Planning Commission, Zoning Hearing Officer and Historic Preservation Commission.

Short on time to read all of this?

Get a free quote →

The division works only inside O’Fallon’s city limits. Land outside them is unincorporated St. Clair County, permitted by the county Building & Zoning Department (see our St. Clair County guide).

O’Fallon permit contacts
DetailInformation
OfficeCommunity Development Department, Building and Inspections Division, 255 S. Lincoln Avenue, 2nd floor, O’Fallon, IL 62269
Phone618-624-4500, ext. 4
Fax618-624-4534 (also used for written zoning look-ups)
Emailcommunitydevelopment@ofallon.org
City Hall hoursMonday to Friday, 7 a.m. to 5:15 p.m.
Online portalO’Fallon Permit Portal (occupancy and electrical permits, rental and business licenses)

O’Fallon permit types

The residential building and zoning application asks for the cost of the improvement, the parcel number, lot and subdivision, the owner, the general, electrical and plumbing contractors (with the plumber’s license number), square footage before and after the work and the percentage of the lot covered by structures. Building plans and product cut sheets are separate submittals that must come with it, and staff mark whether the lot is in a floodplain and which flood zone applies.

Residential permits

  • New homes. The site plan must be professionally drawn to scale and show setbacks, the driveway at least 3 feet from the lot line, a sidewalk poured separately through the driveway, utility locations, swales and floodplain lines, and the top-of-foundation and lowest-opening elevations, which are compared with the table on the recorded final plat. Finished grade must fall at least 6 inches in the first 10 feet away from the foundation.
  • Additions, decks, sheds and retaining walls. A simpler site plan with lot dimensions and distances to every lot line.
  • Pools. The site plan shows the pool, concrete decking, the barrier and gates, equipment, lighting, the equipotential bonding grid and overhead and buried utilities.
  • Manufactured homes. Priced separately, and a used home also needs a dwelling maintenance and occupancy inspection.
  • Occupancy permit. Required when a home changes owner or occupant and no current permit is on file.

Commercial permits

New commercial development needs a building permit application, building plans and a site plan, reviewed for zoning compliance and the city’s development standards; some go through site plan review meetings with the Engineering, Fire and Police Departments, and the city may send plans for larger, complex buildings to an outside code consulting firm at the owner’s cost. A change of use may need permits as well. Fire sprinkler, fire alarm and kitchen hood suppression permits are taken out by those contractors, and commercial spaces need an occupancy permit, valid for one or two years depending on the property, with annual inspections for hotels, theaters, places of worship and other assembly buildings the code official finds hazardous, buildings with fire suppression systems, child care centers with eight or more children and hazardous uses.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning compliance. A Certificate of Zoning Compliance is issued only if the project meets the zoning ordinance; otherwise the owner needs a variance, special use or rezoning first.
  • Zoning Hearing Officer. Decides area-bulk and sign variances on the second and fourth Tuesdays at 5 p.m. when a petition is filed; the City Council has 21 days to reaffirm, modify or overturn the decision.
  • Planning Commission. Meets at 6 p.m. on the second and fourth Tuesdays as business requires, in the Council Chambers.
  • Floodplain. Work in a mapped floodplain needs a floodplain development permit from the Building and Inspections Division under the city’s Floodplain Ordinance.
  • Subdivisions and planned uses. Plats, minor subdivisions and planned uses go through Planning and Zoning before building permits.

O’Fallon permit costs and fees

Building fees come from the city’s Building Permit Fee Schedule, effective January 1, 2010, and zoning fees from the Zoning Permit Fee Schedule of the same date. Construction value for new single-family homes and accessory structures comes from the International Code Council’s Building Valuation Data chart: the Building Official’s February 4, 2025 notice phases in newer charts each May, using the 2021 ICC chart from May 2025 and the 2024 chart from May 2026, with the 0.004 multiplier unchanged. The chart posted with the notice is the 2021 one, so ask the division for the current figures.

O’Fallon permit fees (schedules effective January 1, 2010)
ItemFee
Residential new construction and additions0.004 x ICC value, $50 minimum; new homes add $20 occupancy and $35 zoning fees
Commercial new construction, additions and alterations0.004 x ICC value or actual cost, whichever is higher, $125 minimum; new buildings add $20 occupancy and $35 zoning fees
Residential remodel0.004 x value; minimum $50, or $75 with plumbing or electrical
Swimming pool0.004 x value, $50 minimum, plus $35 zoning fee
Accessory structure (shed, deck, garage, porch, sunroom)0.004 x value, $35 minimum ($50 with electric), plus $35 zoning fee
Hot tub$50, no zoning fee
Electrical service or wiring only$45 up to 200 amps, plus $15 per 100 amps above 200
Plumbing only0.004 x value, $45 minimum
Demolition$45
Site development, grading or excavation permit$50
Re-inspection$50
Commercial plan review (under 4,000 sq ft)0.001 x value, $75 minimum; mechanical, plumbing, electrical and accessibility reviews each 20% of that, $25 minimum
Fire sprinkler / fire alarm / hood suppression permit$75 / $75 / $50
Residential occupancy permit (from May 1, 2025)$75
Variance / special use / zoning amendment$225 / $200 / $200
Preliminary plat / final plat$150 + $10 a lot / $100 + $5 a lot

Rather talk it over?

Call 1-855-478-4290 →

Worked example from the electrical line: upgrading a house to a 400-amp service costs $45 for the first 200 amps plus $15 for each of the two extra 100-amp steps, or $75, before any added wiring charge.

Trade permits and who may pull them

O’Fallon issues its own electrical and plumbing permits through the Building and Inspections Division, and the residential application asks the owner or contractor to name the electrical and plumbing contractors. Electrical permits can be applied for and paid online through the city’s permit portal.

  • Electrical: needed before rewiring, significant remodeling or renovation, with a plan showing the use, outlet locations and service size; solar arrays without structural work also use it. The city enforces the 2020 National Electrical Code and checks bonding and barriers on pools strictly.
  • Plumbing: work follows the Illinois Plumbing Code, the application asks for the plumbing contractor’s license number (plumbers are licensed by the Illinois Department of Public Health), and inspection requests must leave the inspector two business days.
  • Fire protection: sprinkler, alarm and kitchen hood suppression permits are issued to those specialty contractors.

The division’s pages do not describe a city license or registration for general contractors or electricians.

Rather not deal with the building department?

Get a free quote →

How to apply for an O’Fallon building permit

1. Confirm the parcel and zoning

Check the zoning map, visit the office, or fax the address and parcel ID to 618-624-4534 for a written answer.

2. Clear zoning questions

Get any variance, special use, rezoning or plat approval before applying.

3. Draw the site plan

Use St. Clair County property records for lot lines and include every item the application lists for your project type.

4. Submit the application

File the building and zoning permit form, plans and cut sheets with Community Development, in person or by email.

5. Pay the fees

Fees follow the 2010 schedules and the current valuation chart.

6. Book inspections

Call 618-624-4500, ext. 4, at least 24 hours ahead for each required stage.

Review, corrections and what causes delay

The city does not publish a review time. Planning and Zoning staff check setbacks, heights and lot coverage, and an application cannot be approved if the structure breaks the zoning ordinance. Changing plans or specifications after approval needs written approval from city officials, and the permit can be revoked without notice if any statement on the application proves untrue. Appeals of a Building Official’s code decision go to the Building Code Review Committee, which meets at 5 p.m. on the second Tuesday of March and September when needed.

Inspections and certificates in O’Fallon

Permit holders call 618-624-4500, ext. 4, for every required inspection, including the final, with the street address ready, giving at least 24 hours’ notice and allowing until the end of the next work day; calls made by 10 a.m. are worked into the same business day when possible. No work may continue past each stage without the Building Official’s written approval. Decks are checked at the pier holes (at least 30 inches below finished grade, before concrete), the ledger attachment, rough framing and final; in-ground pools before any concrete, at rough electric and bonding, and at final, including barriers and door alarms; signs at the footings and at final.

Occupancy permits work differently. After applying online, in person, by mail or through the drop box, the owner must call within 7 days to book the property maintenance inspection, which must happen within 30 days of the application, and the permit must be obtained within 30 days of that first inspection to allow repairs. Water and electricity must be on, inspection slots run 9 a.m. to 4 p.m. Monday to Thursday and 9 a.m. to 3:30 p.m. on Friday, and a property may be occupied before the inspection if there are no life safety issues. A residential occupancy permit is valid for two years, and Ameren Illinois and O’Fallon Utility Billing ask for its number before starting service.

Illinois building code in O’Fallon

From January 1, 2026, O’Fallon enforces the 2021 International Building, Residential, Fire, Property Maintenance, Existing Building, Mechanical, Fuel Gas and Swimming Pool and Spa Codes and the 2020 National Electrical Code as modified by Ordinance 4348, with the Illinois energy, plumbing and accessibility codes; a Planning and Zoning FAQ still mentions the 2012 property maintenance code, but the codes page lists the 2021 edition. FEMA’s Community Status Book lists the City of O’Fallon (community 170633) as participating in the National Flood Insurance Program, with a current flood map dated November 5, 2003, and no Community Rating System class.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

O’Fallon building permit FAQs

How much is a building permit in O’Fallon?

For a home, the ICC construction value times 0.004, with a $50 minimum; a new house adds a $20 occupancy fee and a $35 zoning fee. Commercial work has a $125 minimum.

Do I need a permit for a shed?

A shed of 101 to 199 square feet needs a zoning permit; at 200 square feet or more it needs both a building and a zoning permit.

Do I need a permit for a fence?

A fence taller than 6 feet is treated as an accessory structure and needs a building permit and accessory-structure setbacks.

Do I need a permit for a pool or hot tub?

Yes, for any pool, spa or hot tub that can hold more than 24 inches of water, and pools must be at least 3 feet from side and rear lot lines.

When do I need an occupancy permit?

Whenever a home or commercial space changes owner or occupant and no current permit is on file. A residential permit costs $75 and lasts two years.

How quickly can I get an inspection?

Give 24 hours’ notice; the city tries to inspect the same day for calls made by 10 a.m.

Is this the O’Fallon in Missouri?

No. The office described here serves O’Fallon, Illinois, in St. Clair County; the Missouri city has its own office and rules.

O’Fallon permit records and official resources

Community Development posts monthly building permit and occupancy permit reports. Other records are requested in writing on the city’s Freedom of Information form, which can be delivered in person, by mail, by fax or electronically; the city responds within five business days, or 21 business days for a commercial request, and the first 50 pages are free, with copies after that at 15 cents a page.

Inspections are where schedules slip.

Get a free quote →

Simplify O'Fallon permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in O'Fallon sooner?

Let Alliance prepare, file, and track your O'Fallon permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about O'Fallon permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.