Inside the village, building permits come from the Village of Shiloh at the Shiloh Municipal Building, #1 Park Drive (618-632-1022, Monday to Thursday, 7 a.m. to 5 p.m.). The village asks applicants to start by describing the project so staff can send the right application and information sheets, and every home is inspected for a $50 occupancy permit when its occupant changes. Unincorporated land nearby is handled by St. Clair County Building & Zoning.
What requires a building permit in Shiloh?
The village’s 2024 welcome guide says building permits are needed for most construction, home improvements included, and names the usual cases: home additions, hot tubs, basement finishes, garages and carports, decks and patios with a roof, sheds larger than 10 by 12 feet, pools, and new or upgraded electrical service. Its information sheets add the details for the most common homeowner projects; the deck sheet (revised December 2021) requires a permit for every deck, roofed or not.
Permit needed
- New homes, additions and garages or carports
- Basement finishes (a sketch is enough, no architect)
- Decks of any kind, attached or freestanding
- Pools, hot tubs and spas holding water over 24 inches deep
- Sheds larger than 10 x 12 feet, and any shed with electric
- New or upgraded electrical service and EV chargers
- Any work inside an easement (easement permit)
No permit, per the village sheets
- Sheds of 10 x 12 feet or smaller without electric (a site layout is still requested)
- Fences, walls and natural barriers (the village still asks you to contact it first)
The no-permit items still have rules. Fences may not exceed 6 feet, may not sit in an easement or the street right-of-way, and except for decorative fences may not come closer to the street than the building setback line, which runs from 25 to 50 feet depending on the zoning district; on a corner lot nothing taller than 2 feet may stand in the 30-foot sight triangle. A small shed should still be shown on a site layout so staff can check setbacks and easements.
What Shiloh decides and what the state holds
The village sets its own permit rules, zoning districts and setbacks in its Municipal Code, published on American Legal and linked from the village’s Code page; the village’s own web pages do not list the building code editions it has adopted. The basement sheet (revised July 2023) applies the 2017 National Electrical Code, including tamper-resistant outlets, and the Illinois Plumbing Code. The state’s part is the plumbing code and plumber licensing, roofing contractor licensing, and the energy and accessibility codes.
Shiloh building department: who handles permitting
The Village of Shiloh issues building permits and runs its own inspections inside the village limits. The village’s information sheets come from its Administrative Department, its EV charger guide lists the Building Department at extension 112 of the main line, and fence and property questions go to Village Code Enforcement at extension 116. The Building Permits page asks applicants to email a short description of the proposed project to the staff address it lists, so the village can send the correct application and any matching information flyers.
Short on time to read all of this?
Get a free quote →Zoning cases are heard by the Planning Commission, which holds public hearings, and decided by the Village Board of Trustees; both meet at the Shiloh Municipal Building, generally at 7 p.m., with agendas posted 48 hours in advance. On November 2, 2026, for example, the Board’s agenda carried an ordinance granting a special use permit, a size variance and architectural appearance approval for a pole barn.
| Detail | Information |
|---|---|
| Office | Shiloh Municipal Building, #1 Park Drive, Shiloh, IL 62269 |
| Phone | 618-632-1022 (Building Department ext. 112; Code Enforcement ext. 116) |
| Fax | 618-632-8942 |
| Hours | Monday to Thursday, 7 a.m. to 5 p.m. |
| Village sewer | Call the village, 618-632-1022 |
| Water | Illinois American Water, 800-422-2782 |
| Outside village limits | St. Clair County Building & Zoning (see the St. Clair County guide) |
Shiloh permit types
The village’s pages point to no online permit portal: applications are obtained at the Village Hall or sent by staff once they know the project. The forms page lists the information sheets that go with them, plus applications for home occupations and a public record request form.
Residential permits
- Basement finish. No architect’s plan is needed, but the application must carry a sketch showing room sizes and uses, the water heater, floor drains, furnace and exits. A room used as a bedroom needs a window opening of at least 5.7 square feet net clear, 24 inches high and 20 inches wide, with the sill no more than 44 inches above the floor, and the floor drain must be in the same room as the water heater and furnace. Owners doing their own work include labor in the cost estimate, or list material costs and let staff add the rest; changes to steel beams, posts, joists or exterior walls need more detail and possibly a design professional.
- Decks. A site plan shows lot lines, easements, any private sanitary system and the distance from the house. Attached decks meet the house setbacks (front 25 to 50 feet, rear 5 to 50 feet, side 5 to 25 feet by district); detached decks are accessory structures 10 to 20 feet from the house. Decks may not be built in easements or over a private sewage system, and a deck more than 15 inches above grade needs a guard at least 36 inches tall.
- Pools, hot tubs and spas. Water over 24 inches deep needs a permit and a 48-inch barrier that a 4-inch sphere cannot pass, with alarms on doors opening to the pool area. Pools stay at least 6 feet from side and rear lines (10 or 25 feet in some districts), 10 feet from the house (up to 20 feet by district) and 25 feet from front and side street lines (up to 50 feet by district), and never in an easement.
- EV chargers. The village’s resource guide asks for conductor and raceway details, electrical load calculations, the charger’s specification sheet and an acknowledgement that smoke and carbon monoxide alarms will be brought up to current code.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
The village publishes no separate commercial checklist; commercial and multi-family projects start the same way, with a project description to the building permit staff, and larger developments go through the Planning Commission and Village Board when they need a special use, variance, plat or architectural appearance approval.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. The 2024 Zoning Map and the Comprehensive Plan adopted in 2018 are posted on the village site; special uses, variances and plats go to a Planning Commission public hearing and then the Village Board.
- Subdivision rules. Depending on the subdivision, a neighborhood architectural committee or homeowner association may have to sign off; the village’s sheets ask owners to check before applying.
- Easements. Work in an easement needs its own easement permit, because many easements carry or store storm water.
- Utilities. Illinois American Water supplies all water and some sewer systems in Shiloh; other areas use the St. Clair Township, Belleville, Caseyville Township or Swansea systems or a private aeration system, so ask the village which serves the lot. Every dig starts with a JULIE locate at 811.
- Flood areas. Shiloh takes part in the National Flood Insurance Program, so ask staff whether a lot lies in a mapped flood hazard area before designing.
Shiloh permit costs and fees
Shiloh’s web pages and information sheets do not print a building permit fee schedule, so ask the building permit staff for the fee when the application is reviewed. The basement sheet adds that the cost estimate on the application includes labor even when owners do the work themselves. The fees the village does publish are for the occupancy inspection and public records.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Home occupancy inspection (change of occupant) | $50, paid at the inspection by cash or check |
| Occupancy re-inspection after a failed item | $35 |
| Public records: first 50 black-and-white pages | Free |
| Public records: page 51 and up | 15 cents a page |
| Village record certified by the Village Clerk | $1 per document |
| Village maps, Municipal Code or Development Code copies | Actual reproduction cost |
Water and sewer connection charges are separate from the permit. Water is supplied by Illinois American Water, so its connection terms come from that company, while sewer questions go to the village office; owners on the village collection system who want a separate water meter for a pool are referred to section 50.086 of the code.
Trade permits and who may pull them
- Electrical: any new or upgraded electrical service needs a permit, a shed with power needs an electrical permit even when the shed itself is permit-free, and EV chargers are checked at rough and final electrical inspections. The basement sheet cites the 2017 National Electrical Code.
- Plumbing: work follows the Illinois Plumbing Code; plumbers are licensed by the Illinois Department of Public Health.
- Roofing: roofing contractors hold a state license from the Illinois Department of Financial and Professional Regulation.
- Private sewage: homes on a private system must show an aeration service record from within the past year at the occupancy inspection, and the septic system itself is inspected by the St. Clair County Health Department, scheduled and paid for by the owner.
The village’s pages do not publish a local contractor license or registration rule for builders or electricians, so ask the building permit staff what contractor details the application needs. The basement and deck sheets are written with owner-builders in mind and ask them to include labor in the cost estimate.
How to apply for a Shiloh building permit
Make sure the property is inside the village; unincorporated parcels go to St. Clair County Building & Zoning.
Open the sheet for your project (basement, deck, shed, pool, fence or EV charger) on the village forms page.
Email the building permit contact on the Building Permits page, or call 618-632-1022, with a short description so staff can send the correct application.
Get any homeowner association or architectural committee approval the subdivision requires.
Add a site plan with lot lines, easements and setbacks, plus a sketch or plans and a cost estimate that includes labor.
Return the application to the Shiloh Municipal Building, #1 Park Drive, Monday to Thursday, 7 a.m. to 5 p.m., and pay the fee the village quotes.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The village does not publish a review time. Going by the village’s sheets, applications are held up by a site plan that does not show easements or setbacks, a project that needs a zoning variance or special use first (those wait for the next Planning Commission hearing and Village Board vote), and structural changes to beams, posts or foundation walls that call for a design professional’s details. Decks may not go in an easement or over a private sewage system, and pools may never sit in an easement.
Inspections and occupancy in Shiloh
The village publishes no online inspection scheduler; its EV charger guide gives the Building Department line, 618-632-1022 extension 112. For an EV charger the village lists a rough electrical inspection when new wiring will be concealed, a final electrical inspection and a final building inspection. For decks, the village’s sheet sets the construction points plans should show, such as pier holes reaching at least 30 inches below finished grade and a ledger lag-bolted to the house studs.
Shiloh also inspects every home when its occupant changes. The occupancy permit and certificate of occupancy must be in place before electric and water service is started for the new occupant, an appointment and the fee are required, the owner or renter must be present, and the visit generally takes 15 to 20 minutes. The 2026 checklist covers house numbers at least 3 inches tall, ground-fault protected exterior outlets, smoke detectors on every floor, in bedrooms and within 15 feet of bedrooms, carbon monoxide detectors, guards with balusters no more than 4 inches apart, and pool fences with self-latching gates. All utilities must be on for the inspection; it costs $50, and a re-inspection after a failed item costs $35.
Illinois building code in Shiloh
Shiloh’s Municipal Code is organized in titles, with land use in Title XV, and the village links each title from its Code page. The village’s own sheets refer to the 2017 National Electrical Code and the Illinois Plumbing Code; for other editions, ask the building permit staff. FEMA’s Community Status Book lists the Village of Shiloh (community 171043) as participating in the National Flood Insurance Program, with a flood map effective November 5, 2003, and no Community Rating System class.
Want this handled start to finish?
Get a free quote →Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Shiloh building permit FAQs
Do I need a permit for a shed in Shiloh?
Only if it is larger than 10 by 12 feet or will have electric. A smaller shed with no power needs no permit, but the village asks for a site layout so it stays out of easements and meets setbacks.
Do I need a permit for a fence?
No, according to the village’s fence sheet, but contact the village first. Fences are limited to 6 feet, cannot sit in easements or the right-of-way, and must stay behind the building setback line except decorative fences.
Does finishing a basement need a permit?
Yes. A sketch of the rooms, water heater, floor drains, furnace and exits is enough; an architect’s plan is not required.
What does the occupancy inspection cost?
$50, paid by cash or check at the inspection, and $35 for a re-inspection. Every home is inspected when its occupant changes, before electric and water service is set up.
Do I need a permit for a hot tub or pool?
Yes, for any pool, hot tub or spa holding water more than 24 inches deep, with a 48-inch barrier and alarmed doors to the pool area.
Can I work in a utility easement?
Only with an easement permit. Many easements carry or store storm water, so they are closely regulated.
Does Shiloh issue permits outside the village?
No. Unincorporated land around Shiloh is permitted by St. Clair County Building & Zoning.
Shiloh permit records and official resources
Permit and inspection files for Shiloh addresses are village records. They can be requested at the Village Clerk’s office with the village’s public record request form; the form says requests are answered within 5 working days, or 21 working days for commercial requests, and that records are available there Monday to Friday, 8 a.m. to 4 p.m.
Inspections are where schedules slip.
Get a free quote →- Shiloh building permits page
- Village forms and information sheets
- Basement finish information sheet
- Deck building information sheet
- Shed building information sheet
- Swimming pools, hot tubs and spas information sheet
- Fences, walls and natural barriers information sheet
- Single-family EV charger resource guide
- Occupancy inspection checklist (2026)
- Village welcome guide (2024)
- Shiloh zoning map (2024)
- Shiloh Municipal Code (village code page)
- Agendas and notices
- Public record request form
- FEMA Community Status Book, Illinois
- Illinois Department of Public Health plumbing
Simplify Shiloh permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Shiloh sooner?
Let Alliance prepare, file, and track your Shiloh permits while your crew stays on the job.
More Illinois permitting guides
St. Clair County
Read guide →Swansea
Read guide →Belleville
Read guide →Shorewood Building Permit Guide
Read guide →Skokie Building Permit Guide
Read guide →South Elgin Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Shiloh permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.