Inside the City of Moline, permits come from the Building and Inspections Division at the City Services Center, 1830 6th Avenue (north entrance; 309-524-2370; weekdays 7 a.m. to 3:30 p.m.). Registered contractors apply through the city’s eTRAKiT online portal, and owners use the paper forms. Building fees follow a valuation table, and new buildings, additions and remodels also post a refundable certificate of occupancy deposit of 1% of the job cost. Unincorporated land around the city is permitted by Rock Island County.
What requires a building permit in Moline?
Moline requires a permit whenever an owner, agent or contractor wants to construct, enlarge, alter, repair, move or demolish a building or structure or change its occupancy, and whenever an electrical, gas, mechanical or plumbing system is installed, altered, repaired, removed or replaced. The city’s permit process page lists common jobs:
Permit needed
- Additions such as bedrooms, bathrooms and family rooms
- Remodels: garage conversions, basement finishing, kitchen expansions
- Re-roofing, siding and window replacement
- Decks, carports, garages, fireplaces and pools
- Water heaters, HVAC, electrical and plumbing work
- Sheds over 120 square feet
- Retaining walls over 4 feet
- Solar installations
- Demolitions, including interior demolition, garages, sheds and in-ground pools
Handled elsewhere
- City sidewalks and driveway approaches: Engineering, 309-524-2350
- Zoning relief, signs, subdivisions and floodplain authorization: Zoning and Land Development
- Drainage permits: Public Utilities; stormwater, grading and drainage questions 309-524-2363
No work may start until the permit has been issued and paid for, and work found done without a required permit is charged additional fees or penalties. The city’s exemptions under the adopted codes never authorize work that violates the city code.
What the city decides and what the state holds
Moline adopts its own codes with local amendments: the 2021 International Building, Residential, Property Maintenance, Mechanical and Fuel Gas codes, the 2012 International Fire Code and the 2020 National Electrical Code, along with the 2014 Illinois Plumbing Code with local amendments. The state energy code and the Illinois Accessibility Code apply as well, plumbers and roofers hold state licenses, and commercial work involving life safety or structural changes needs plans stamped by an Illinois licensed design professional.
Moline building department: who handles permitting
The Building and Inspections Division of Community and Economic Development, whose Building Official is Drake Daley, reviews plans, issues permits, inspects construction, registers contractors, licenses and inspects food establishments and enforces the building codes. The Zoning and Land Development Division, in the same department, administers zoning, subdivision, sign and flood hazard codes and supports the Plan Commission and the Zoning Hearing Officer.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| Building and Inspections Division (permits, plan review) | City Services Center, 1830 6th Avenue, Moline, IL 61265; 309-524-2370; Monday to Friday 7 a.m. to 3:30 p.m. |
| Building inspection voicemail | 309-524-2378 |
| Electrical inspection voicemail | 309-524-2372 |
| Mechanical and plumbing inspection voicemail | 309-524-2374 |
| Building Official Drake Daley | 309-524-2371 |
| Zoning: residential / commercial | 309-524-2033 / 309-524-2031 |
| Stormwater, grading and drainage | 309-524-2363 |
| Fire Department | 309-524-2266 |
| Engineering (sidewalks, approaches) | 309-524-2350 |
The division asks applicants to talk through their plans with the Building Official or the relevant trade inspector before starting, to learn whether a permit is needed. Moline sits in Rock Island County; the county’s Zoning and Building Safety office permits only unincorporated land, so it does not issue permits inside the city.
Moline permit types
Moline issues separate building, electrical, mechanical and plumbing permits, each with its own application and fee sheet, plus backflow test and survey forms.
Residential permits
- Owners doing their own work: the city publishes a minimum valuation table, effective April 1, 2023, that sets the lowest value a property owner may declare: $120 per square foot for a house, addition or three-season room, $35 for decks and attached garages, $30 for detached garages and remodels, $30 or $25 for finished or unfinished basements, and per-square rates for roofing and siding. The Building Official sets the final valuation and can deny a permit whose value looks underestimated.
- Accessory structures and fences: the zoning division posts handouts on allowable heights and setbacks for sheds, garages, decks, patios, pools and courts, and on fence heights and placement.
- Sheds and retaining walls: a shed over 120 square feet or a wall over 4 feet needs a permit.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial plans follow the city’s plan review checklist. Projects involving life safety or structural changes need stamped drawings by an Illinois licensed architect or engineer, and complex interior space planning may also need stamped mechanical and electrical drawings at the code manager’s discretion. New privately funded commercial construction must meet the state energy code. Commercial jobs of $20,000 or more pay a plan review fee of 65% of the building permit fee.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning: administrative approvals such as sign permits, landscaping agreements and floodplain development authorizations are often granted on submittal or within a day or two; variances, special uses, rezonings and subdivisions go to public hearings and are due four weeks before the hearing date.
- Right-of-way: sidewalk and approach permits come from Engineering.
- Occupancy deposit: new buildings, additions, remodels and other structures meant to be occupied post a certificate of occupancy deposit or bond before the permit is issued.
Moline permit fees
The city states that its current fee schedule is in Chapter 8 of the Moline Code of Ordinances; the fee sheets posted on its Forms and Fees page are dated January 1, 2012, so check the amounts against Chapter 8 when the permit is assessed. The building permit fee is based on the total cost of construction, and fees are assessed only after the plans are approved, when the office tells you the permit can be paid for and issued.
| Item | Fee |
|---|---|
| Building permit, valuation up to $500 | $24 |
| Valuation $14,001 to $15,000 | $255 |
| Valuation $49,001 to $50,000 | $663 |
| $70,001 to $100,000 | $813 at $70,000 plus $8 per added $1,000 |
| $100,001 to $500,000 | $1,054 for the first $100,000 plus $5 per added $1,000 |
| $500,001 to $1,000,000 | $3,354 plus $4.50 per added $1,000 |
| Over $1,000,000 | $5,942 plus $3 per added $1,000 |
| Commercial plan review (jobs of $20,000 or more) | 65% of the building fee |
| Electrical, new single-family home | $25 plus $0.05 per sq ft of habitable floor area |
| Electrical: service, incidental unit / additions, basements, garages | $17 / $25 |
| Commercial electrical | $50 plus 1% of material and labor |
| Mechanical | $25 up to $700 of value; $147 at $15,000, then $2 per $1,000 |
| Plumbing | $25 including two fixture openings, then $12 each; water heater $25 |
| Demolition: house / garage or shed | $86 / $28 |
| Re-inspection | $50 per hour |
| Certificate of occupancy deposit | 1% of valuation, $250 minimum, $10,000 maximum (refundable) |
Rather talk it over?
Call 1-855-478-4290 →Worked examples: an owner building a 12-by-16-foot deck (192 square feet) must declare at least 192 × $35 = $6,720, which falls in the $6,001 to $7,000 band, so the building permit is $144. A 2,000-square-foot house valued at the owner minimum of $240,000 pays $1,054 + 140 × $5 = $1,754, plus a refundable $2,400 occupancy deposit. The bands on the sheet do not chain exactly at $100,000 and $500,000, so keep any estimate inside one band.
The deposit comes back by check when every final inspection, including trades, sidewalks, approaches, storm water and landscaping, has passed and the certificate of occupancy is requested before the permit expires; otherwise it is forfeited unless a renewal was granted. Zoning applications are priced separately under the 2016 development review fee schedule: $650 for a special use, rezoning or zoning variance, $360 for a sign variance, $250 or $900 for a minor or major subdivision, and $30 for a zoning confirmation letter.
Trade permits and who may pull them
Contractors register with the Building Division each calendar year, January 1 to December 31, before they can pull permits.
- General contractors: registration form, a $5,000 license and permit bond on the city’s form, liability insurance of $100,000 per occurrence for property damage and $300,000 for injury with the city as certificate holder, workers’ compensation proof or a sworn no-employee statement, a $75 annual fee and, for any roofing job, a current state roofing license.
- Electrical contractors: the license is issued only to an individual. Option 1 is an affidavit of passing a master electrical exam through Prometric or the ICC program plus five years’ experience; option 2 is a current electrical license from another Illinois city plus five years as an electrical contractor. Bond and insurance as above; $50 a year.
- Mechanical contractors: the same structure, with a master mechanical exam or another Illinois city’s mechanical license and five years’ experience; $50 a year.
- Plumbing contractors: a copy of the state plumbing license for the individual and the business; no bond, insurance or registration fee.
Moving and wrecking contractors register too. Registered contractors receive a contractor ID from the city before using the online portal and should not create a login until they have it; a contractor holding several license types gets a separate ID for each. Plumbing permits are still submitted by mail. Property owners doing their own work file the paper applications using the owner minimum valuation table.
Rather not deal with the building department?
Get a free quote →How to apply for a Moline building permit
Call 309-524-2370 to confirm whether your project needs a permit and which ones.
Use the zoning handouts for setbacks; file any variance or special use four weeks before its hearing.
Contractors need a current city registration and contractor ID.
Apply in eTRAKiT, by mail or at 1830 6th Avenue; plumbing goes by mail.
Pay the permit fee and any deposit; the permit is issued only once paid.
Book each inspection a day ahead and request the certificate of occupancy before the permit expires.
Review, corrections and what causes delay
The permit process page says the city tries to review all plans within 10 working days, while the plan review page gives a minimum of 15 business days depending on scope and accuracy. Incomplete submittals are not reviewed and are returned with a request for complete plans, and review starts only when every document is in. Contractor accounts with expired licenses, bonds or insurance cannot apply online until updated.
Inspections in Moline
Once a permit is issued, schedule inspections by leaving a message on the right trade inspector’s voicemail at least 24 hours ahead: building 309-524-2378, electrical 309-524-2372, mechanical and plumbing 309-524-2374. Re-inspections, inspections outside business hours (two-hour minimum) and extra plan review on revised plans are billed at $50 an hour.
Inspections are performed the next business day after the request. Subcontractors pull and pay for their own electrical, plumbing and heating or air-conditioning permits, and the building permit must be posted where it can be seen at the job site throughout construction.
For occupied buildings the last step is the certificate of occupancy, which the Building Official issues on projects that paid occupancy fees once the work is complete and code compliance is confirmed. Request it after all building and trade finals, sidewalk, approach, storm water and landscaping inspections are approved and before the building permit expires, so the occupancy deposit is refunded in full.
Illinois building code in Moline
FEMA’s Community Status Book lists Moline (community 170591) as participating in the National Flood Insurance Program, with its first flood insurance rate map dated February 1, 1980 and the current map April 5, 2010. The city joined the Community Rating System on October 1, 2010 and is class 8, worth a 10% discount on flood insurance.
Want this handled start to finish?
Get a free quote →Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Permit search and official resources
Registered contractors can view and print their permits in the city’s eTRAKiT portal. Older permit and inspection records are requested from the City Clerk’s Office under the Freedom of Information Act: the city answers in writing within 5 business days (up to 10 with notice, 21 for commercial requests), may charge 15 cents a page for requests of 50 pages or more, and offers an optional certified response for $1.
- Moline permits and inspections
- Building and Inspections Division
- When is a permit required
- Steps to obtain a permit
- Permit process and occupancy deposit
- Permit contact phone numbers
- Plan review and submittal
- Online permitting system
- Permit forms and fees
- Building permit fee schedule
- Property owner minimum valuations (April 2023)
- Current codes
- General contractor registration
- Electrical contractor registration
- Plumbing contractor registration
- Zoning and land development
- Development review fee schedule
- Freedom of Information requests
- FEMA Community Status Book, Illinois
Inspections are where schedules slip.
Get a free quote →Moline permit FAQs
Do I need a permit for a shed in Moline?
Yes, if it is over 120 square feet.
Do I need a permit to replace my roof or siding?
Yes. Moline lists re-roofing, roofs, siding and windows among residential work that needs a permit.
How long does plan review take?
The city aims for 10 working days; its plan review page says at least 15 business days, depending on the project and the completeness of the plans.
What is the certificate of occupancy deposit?
A refundable deposit of 1% of the job value, at least $250 and at most $10,000, posted before the permit for new buildings, additions and remodels.
Can a homeowner pull a permit in Moline?
Yes. The city publishes minimum valuations that property owners must use when applying for their own work.
How do I schedule an inspection?
Leave a message on the trade inspector’s voicemail at least 24 hours ahead: building 309-524-2378, electrical 309-524-2372, mechanical and plumbing 309-524-2374.
Does Rock Island County issue permits in Moline?
No. The county permits only unincorporated land; Moline issues its own permits.
Simplify Moline permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Moline sooner?
Let Alliance prepare, file, and track your Moline permits while your crew stays on the job.
More Illinois permitting guides
Rock Island County
Read guide →Rock Island
Read guide →East Moline
Read guide →Monroe County Building Permit Guide
Read guide →Montgomery Building Permit Guide
Read guide →Montgomery County Building Permit Guide