Herrin, Illinois Building Permit Guide

To get a building permit in Herrin, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Herrin’s City Codes Department at City Hall issues building permits inside the city, at 10 cents a square foot under roof on its page and permit form (the city code also carries 2019 valuation tables), and inspects every home before a new water account is opened.

Authority: City of Herrin Code InspectorFiling: Paper application at City HallPhone: 618-942-3175
Permit office
City Codes DepartmentCity Hall, 300 N. Park Ave.
Building permit
10 cents per sq ftUnder roof, per city page and form; code has 2019 valuation tables
Occupancy inspection
$25Weekdays 8:30 a.m. to 2 p.m., by appointment
Rental owners
$25 per unit a yearAnnual property owner’s permit, due April 30

In the City of Herrin, building permits are issued by the Code Inspector of the City Codes Department at City Hall, 300 N. Park Ave. (618-942-3175, weekdays 8 a.m. to 4 p.m.). The city’s page requires a permit for anything over 10 square feet under roof, and its permit form charges 10 cents per square foot, so a 1,200-square-foot building costs $120; the Revised Code still carries 2019 valuation tables, so confirm the fee. Occupancy inspections, booked at 618-942-6004, cost $25.

What requires a building permit in Herrin?

The city’s Code Enforcement page sets a low threshold: anything over 10 square feet under roof needs a building permit. The building permit application covers new buildings, additions and repairs or alterations, for homes, duplexes, apartment buildings, garages, carports and accessory buildings, and for industrial, retail, service, educational, religious and storage uses.

Permit needed

  • New homes, duplexes and apartment buildings
  • Additions, repairs and alterations
  • Garages, carports and accessory buildings over 10 sq ft under roof
  • Manufactured homes (double-wide, over 1,200 sq ft, permanent foundation)
  • Commercial and industrial buildings
  • Signs and awnings; demolition or relocation
  • Any development in the mapped floodplain

Separate city approvals

  • Occupancy inspection before a water account opens ($25)
  • Annual property owner’s permit for rentals ($25 per unit)
  • Rezoning, special use or variance ($50 application)

The codified residential code reads differently from the web page: Herrin’s amendment to the 2012 International Residential Code exempts one-story detached tool and storage sheds and playhouses of up to 200 square feet. Because the city’s own page and form apply the 10-square-foot threshold, ask the Code Inspector before building any small shed without a permit.

What Herrin decides and what the state holds

Herrin is a home-rule city and adopts its own codes in Chapter 6 of its Revised Code of Ordinances: the 2012 International Building, Residential, Existing Building and Mechanical Codes, the 2012 International Energy Conservation Code for commercial buildings, the 2011 National Electrical Code, the Illinois State Plumbing Code and the state accessibility standards. Its residential amendments delete the code’s fire sprinkler requirement for houses and the self-closing door rule between a garage and the house. The building permit form still refers to the older B.O.C.A. codes; the Revised Code governs.

Herrin building department: who handles permitting

The City Codes Department handles building permits, zoning for homes and businesses, the Enterprise Zone, sign placement, demolitions and nuisance complaints such as weeds, trash and inoperable cars. The Code Inspector signs and issues each permit, administers the Flood Plain Code and inspects homes for occupancy. The fire code is enforced by the fire districts that serve the city.

Short on time to read all of this?

Get a free quote →

Herrin permits only inside its city limits. No county building department appears on Williamson County’s website (see the Williamson County guide); neighboring Marion and Carterville run their own permit offices.

Herrin permit contacts
DetailInformation
OfficeCity Codes Department, City Hall, 300 N. Park Ave., Herrin, IL 62948
PhoneCity Hall 618-942-3175; occupancy inspection appointments 618-942-6004
HoursCity Hall Monday to Friday, 8 a.m. to 4 p.m.; inspections 8:30 a.m. to 2 p.m.
ApplicationsPaper forms from the city’s Forms & Documents page
911 addresses911 Administrative Office, Marion Police Department, 1001 W. DeYoung, Marion; 618-997-7541

Herrin permit types

Herrin’s permit forms are on its Forms & Documents page: a building permit application, separate forms for signs and awnings, demolition or relocation, and zoning, variance and special use requests, plus Enterprise Zone and TIF facade program applications for businesses. The city will not accept an incomplete building permit application.

Residential permits

  • Address first. The form needs an accurate 911 address; a new lot without one gets it from the 911 Administrative Office at the Marion Police Department.
  • Plans. A floor plan is required for every single-family home, and single-family homes and duplexes also need a lot drawing showing the building’s dimensions, existing structures and front, side and rear setbacks. Where a subdivision plat sets larger setbacks than the city, the plat governs.
  • Manufactured homes are permitted only if double-wide, over 1,200 square feet and on a permanent foundation.
  • Multi-family buildings follow the site plan rules in Chapter 41.

Commercial permits

Every non-residential use, from retail and service stations to churches, schools and storage buildings, must meet the site plan requirements of Chapter 41, and the application asks for the type of construction, water supply, heating and electrical service, number of stories and the square footage under roof. The city offers Enterprise Zone and TIF facade incentives to businesses on separate applications.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. Rezoning, special use and variance requests go on one zoning application with a $50 fee and a list of the owners of every abutting property. For a variance, the Zoning Board of Appeals holds a public hearing within 30 days of filing, after 15 to 30 days’ notice by newspaper and by mail to abutting owners, and sends a recommendation to the City Council, which alone grants or denies the variation by ordinance.
  • Subdivisions. Plats go to the Plan Commission under the Subdivision Code, and no permit is issued for a lot sold in violation of it.
  • Historic preservation. Alterations, new construction and demolition of designated properties are reviewed by the Historic Preservation Committee under the zoning code.
  • Floodplain. The zoning form asks whether the land is in the floodplain, and development there needs a separate development permit from the Code Inspector. The application needs a scaled site drawing with property lines, existing grades and any cut or fill, the location and size of each building, the elevation of the lowest floor including any basement, and a cost estimate by a licensed engineer or architect (a contractor’s signed estimate may also be accepted). Land shown by survey to sit above the base flood elevation, and not filled since the first flood map, is outside the code.
  • Street cuts. Utility excavation in streets needs the city’s excavation permit under Chapter 33.

Herrin permit costs and fees

Herrin’s official sources give two different ways of pricing a building permit. The city’s Code Enforcement page and its building permit application both charge 10 cents per square foot under roof, with the form’s own example of 1,200 square feet costing $120. The Revised Code of Ordinances, which the city posts as its 2025 code with supplements through January 2026, still carries valuation tables effective October 1, 2019 as Schedule A (residential) and Schedule B (commercial and industrial). Ask the Code Inspector which figure applies before you budget.

Herrin permit and inspection fees
ItemFee
Building permit (web page and application form)10 cents per sq ft under roof
Occupancy inspection before a water account opens$25; $25 again if the owner misses the appointment
Annual property owner’s permit (rentals, non-owner-occupied homes)$25 per dwelling unit
Zoning application (rezoning, special use, variance)$50

Rather talk it over?

Call 1-855-478-4290 →
Codified valuation tables, effective October 1, 2019 (Revised Code, Chapter 6)
Project cost up toResidential (Schedule A)Commercial (Schedule B)
$1,000$54$140
$10,000$315$460
$50,000$527$786
$100,000$899$1,354
$200,000$1,580$2,404
$500,000$3,455$5,291

Worked example on the city form’s basis: a 2,000-square-foot house with an attached 500-square-foot garage has 2,500 square feet under roof, so the permit is $250. Under the codified Schedule A, the same house built for $250,000 would be $1,921. The permit fee must be paid before the permit is issued and before construction begins.

Trade permits and who may pull them

Herrin does not post separate electrical, plumbing or mechanical permit applications; the building permit form records the type of heating, the electrical service size and the water supply. Instead, the city relies on a sign-off at the end of the job: before an occupancy permit is issued, a certificate signed by a licensed plumber and by a residential or journeyman electrician, stating that the plumbing and electrical work meets the codes, must be given to the Code Inspector.

  • Plumbing: the Illinois State Plumbing Code applies, and the certifying plumber must be licensed; plumbers are licensed by the Illinois Department of Public Health.
  • Electrical: work is built to the 2011 National Electrical Code as Herrin adopted it, and the certifying electrician must hold a residential or journeyman credential.
  • Mechanical: the 2012 International Mechanical Code applies.
  • Fire code: the 2012 International Fire Code is enforced by the fire districts serving the city.

Rather not deal with the building department?

Get a free quote →

The city’s pages show no separate contractor registration program for builders; the application asks for the owner’s, contractor’s and any architect’s or engineer’s names and phone numbers.

How to apply for a Herrin building permit

1. Confirm the city has the parcel

Herrin permits only inside its city limits.

2. Get a 911 address

New lots without one get it from the 911 Administrative Office in Marion.

3. Check zoning and floodplain

File a zoning application first if you need a rezoning, special use or variance.

4. Complete the application

Fill in every item and attach the floor plan, lot drawing or site plan the use requires.

5. Pay the fee at City Hall

No permit issues and no work may start until the fee is paid and approved.

6. Close out for occupancy

Hand in the plumber’s and electrician’s certificate and book the occupancy inspection.

Review, corrections and what causes delay

The city publishes no set review time. Applications are refused outright when any item is blank, and the form warns that missing information means denial. Other common causes of delay are a missing 911 address, a manufactured home that does not meet the double-wide, 1,200-square-foot and permanent-foundation rules, a non-residential site plan that does not meet Chapter 41, and a lot in the floodplain that needs its own development permit and elevation data. Allow for City Hall closures when planning a filing or an inspection: the city closes for Presidents’ Day, Good Friday, Memorial Day, the Fourth of July, Labor Day, Veterans Day, Thanksgiving and the Friday after, Christmas Eve and Christmas Day, and New Year’s Eve and Day.

Inspections and occupancy in Herrin

Herrin ties occupancy to its water service. Every property is inspected when an application for water service is made, and the Code Inspector checks it against the city housing code and the International Property Maintenance Code before an occupancy permit is issued. Appointments are made at 618-942-6004 and run every 30 minutes, Monday to Friday, from 8:30 a.m. to 2 p.m. The inspection costs $25, and a further $25 is charged if the owner or agent is not there at the appointed time. A home that fails gets a list of corrections; the inspector may issue a temporary occupancy permit for 30 days while repairs are made, and it cannot be renewed.

Owners who rent out a home, sell on contract for deed or do not live in a property need an annual property owner’s permit at $25 per dwelling unit. The 2023 ordinance and the city’s web page say these permits run to April 30; an older housing code section still gives June 30 for rental permits, so renew by April 30.

Want this handled start to finish?

Get a free quote →

Illinois building code in Herrin

Herrin enforces the 2012 International codes and the 2011 National Electrical Code adopted in its Revised Code, with local amendments, and the Illinois State Plumbing Code. Its Flood Plain Code requires a development permit from the Code Inspector before any building, filling, grading, paving or storage in the floodplain, with the lowest floor raised to the flood protection elevation, which is the base flood elevation plus one foot; floodways are mapped along Hurricane Creek and the Seventeenth Street Ditch. FEMA’s Community Status Book lists the City of Herrin (community 170717, Williamson County) as participating in the National Flood Insurance Program, with its first flood insurance rate map dated April 16, 1990 and the current map dated August 4, 2008; it has no Community Rating System class.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Herrin building permit FAQs

How much is a building permit in Herrin?

The city’s page and form charge 10 cents per square foot under roof ($120 for 1,200 square feet). The Revised Code also carries 2019 valuation tables, so confirm the figure with the Code Inspector.

Do I need a permit for a small shed?

The city page requires one for anything over 10 square feet under roof; the code’s residential amendment exempts sheds up to 200 square feet. Ask before building.

Why does the city inspect my house before turning on water?

Herrin requires a $25 occupancy inspection when water service is requested, to confirm the home meets housing standards.

Can I put a manufactured home on a lot in Herrin?

Only a double-wide over 1,200 square feet on a permanent foundation, according to the permit application.

Who signs off on plumbing and electrical work?

Before occupancy, a licensed plumber and a residential or journeyman electrician must give the Code Inspector a signed certificate that their work meets the codes.

Do landlords need a permit?

Yes. Owners of rental or non-owner-occupied homes need an annual property owner’s permit at $25 per dwelling unit, running to April 30.

How do I ask for a variance?

File the zoning application with the $50 fee and the names and addresses of abutting owners. The Zoning Board of Appeals holds the hearing and the City Council decides by ordinance.

Inspections are where schedules slip.

Get a free quote →

How do I get old permit records?

Submit a Freedom of Information request through the city’s online request portal.

Herrin permit records and official resources

Permit and inspection records are kept by the City Codes Department. Formal requests for records go through the city’s Freedom of Information portal, linked from its forms page. The city’s Revised Code of Ordinances, including the building code chapter, flood plain code, housing code, subdivision code and zoning code, is posted as a single PDF.

Simplify Herrin permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Herrin sooner?

Let Alliance prepare, file, and track your Herrin permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Herrin permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.