Hanover Park, Illinois Building Permit Guide

To get a building permit in Hanover Park, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

In Hanover Park, building permits come from the Fire Department’s Inspectional Services Division at 2121 West Lake Street, priced at $12 per $1,000 of construction value plus a refundable bond on jobs of $5,000 or more, and Village Hall is closed on Wednesdays.

Authority: Inspectional Services Division (Fire Department)Fees: Municipal Code Sec. 18-200Phone: 630-823-5860
Authority
Inspectional Services2121 West Lake Street
Permit fee
1.2% of valueMinimum $50 residential, $100 commercial
Refundable bond
1% up to $50,000Then 0.5%; none under $5,000
Office days
Mon, Tue, Thu, Fri8 a.m. to 4:30 p.m.; closed Wednesday

The Village of Hanover Park, which straddles Cook and DuPage counties, issues its own building permits through the Inspectional Services Division of the Fire Department at Village Hall, 2121 West Lake Street (630-823-5860, iservices@hpil.org). You can apply online or on the paper form, with a project handout for most common jobs. The permit fee is $12 for every $1,000 of construction value, with a $50 minimum for residential work, and jobs of $5,000 or more may also need a refundable bond, returned after the final inspection passes.

What requires a building permit in Hanover Park?

The village requires permits for many remodeling projects, repairs, replacements, new structures and additions, and asks owners to call Inspectional Services before any home improvement job starts. Work may begin only after the permit is issued, and the permit placard must hang in a window visible from the street until the job is done. Starting without a permit brings a permit penalty and a stop-work order.

Projects with village handouts

  • Room additions, remodels, detached garages, sheds and decks
  • Driveways, parking lots, patios, service walks and stoops
  • Fences, flag poles, mailboxes, swimming pools and temporary tents
  • Roofs, windows and energy-code upgrades
  • Furnaces, air conditioners, water heaters, water services and sanitary sewer repairs
  • Electric service upgrades, EV chargers, solar panels and low-voltage alarms
  • Permanent and temporary signs

No permit

  • Plastic storage bins of non-decaying material under 25 square feet, up to two per lot

The handouts set the local rules. A shed may be no bigger than 200 square feet and 15 feet tall, only one is allowed per lot, and it must sit 10 feet from the rear lot line and the house and 5 feet from the side line. Wood, vinyl or masonry fences in side and rear yards may be 6 feet high, other types 5 feet, and only decorative fences up to 3 feet are allowed in front yards. Re-roofing is limited to two layers of shingles, with ice and water shield at all eaves and valleys.

Energy work has its own checklist, which lists the building envelope values the village checks: walls must reach R-20 (or R-13 plus R-5 continuous), attics R-49, basement walls R-15 continuous or R-19 in the cavity, and new windows a U-factor below 0.30. Any furnace or air conditioning system that is replaced or modified must get a programmable thermostat, and continuously burning gas lights are not allowed.

What Hanover Park decides and what the state holds

Hanover Park writes its own permit fees (Municipal Code Section 18-200), zoning code (Chapter 110), contractor registration and local building amendments, such as minimum roof sheathing thicknesses and R-8 duct insulation in unheated spaces. Its energy handout applies the International Energy Conservation Code as adopted by the state and the village, and plumbing work must meet the Illinois Plumbing Code, which the village adopts by reference.

Short on time to read all of this?

Get a free quote →

Hanover Park building department: who handles permitting

In Hanover Park, permits and inspections sit in the Fire Department: its Inspectional Services Division reviews applications, issues permits and inspects. The Community and Economic Development Department handles planning, zoning and development applications, and Public Works and Engineering reviews site and utility work. Because Hanover Park lies in both Cook and DuPage counties, some water, sewer and impact fees depend on which county the lot is in.

Hanover Park permit contacts
OfficeDetails
Inspectional Services DivisionVillage Hall, 2121 West Lake Street, Hanover Park, IL 60133; 630-823-5860; iservices@hpil.org; fax 630-823-5782
HoursMonday, Tuesday, Thursday and Friday, 8 a.m. to 4:30 p.m.; closed Wednesday and weekends
Community and Economic Development (zoning)630-823-5780; CDevelopment@hpil.org
Public Works and Engineering630-823-5700
Village Hall main line630-823-5600

Hanover Park permit types

One building permit application covers new structures, accessory structures, remodeling and room additions. It asks for the construction value including materials and labor, ticks for mechanical work (furnace, air conditioner, water heater), building work (deck, roof, windows and doors, concrete, pavers) and fences, and whether the homeowner or a contractor will do the work. Apply online through the village’s web form or in person.

Residential permits

  • Decks, sheds and garages: a full-size plat of survey showing the structure and its distances to the lot lines and house, plus construction or manufacturer’s drawings with the foundation, size, height and framing.
  • Fences: a plat of survey marked with the fence location, type and height, and the contractor’s signed proposal or the owner’s scope and materials list. Fences go on the property line except along a corner side yard, the finished side faces out, posts go 42 inches deep (36 inches for 3-foot fences), and chain link may not have slats.
  • Roofs: the signed agreement or estimate and the materials list. Rotted decking must be replaced, only one layer of decking is allowed, and the village requires at least 1/2-inch CDX plywood or 5/8-inch exterior OSB sheathing on rafters 16 or 24 inches apart. Attic vent area must be 1/150 of the vented space, or 1/300 with soffit vents and 40% to 50% of the venting near the ridge.
  • Digging: for sheds, fences and other excavation, call JULIE at 800-892-0123 first; the shed handout says the dig number must be on the permit before it issues.
  • Owner work: owners doing their own work give a scope summary and materials list and sign an owner affidavit.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial work uses the same application and the commercial fee minimums. Sign permits, parking lot work and temporary tents have their own handouts, and fire sprinkler and fire alarm plans are reviewed by consultants whose fees are passed on to the applicant. Large projects usually start with the development review process described below.

What comes before the building permit

  • Pre-application meeting. The village requires one for development projects, with staff from Fire and Inspectional Services, Public Works and Engineering, and Community Development, and also offers an informal concept plan review before the Development Commission or Village Board.
  • Development Commission. Rezonings, variations, special uses, subdivisions and planned developments go to the staff Development Review Committee (first and third Fridays), then a public hearing before the Development Commission, typically the second Thursday at 7 p.m., and final action by the Village Board about three weeks later. The whole process takes at least three months. If no zoning relief is needed, the building permit is simply reviewed for code compliance.
  • Utilities. New water and sewer connections carry tap-on, meter and account fees set by village ordinance for the Cook or DuPage side of the village.

Hanover Park permit costs and fees

All permit fees are in Municipal Code Section 18-200, and staff tell you the total when you apply. New construction is valued from the latest International Code Council Building Valuation Data; remodeling, repairs and demolition use the actual cost, which the building official can adjust if the figure on the application looks low. Round each fee up to the nearest $5.

Hanover Park building permit fees (village fee pages)
ItemFee
Building permit$12 per $1,000 of value (1.2%); minimum $50 residential, $100 commercial
Refundable bondNone under $5,000; $10 per $1,000 up to $50,000, then $5 per $1,000 above
Plan review, new construction10% of the permit fee; minimum $75 residential, $150 commercial
Plan review, remodeling over $50010% of the permit fee; minimum $50 residential, $75 commercial
Supplemental plan review (electric, HVAC, plumbing; health for commercial)Each 25% of the standard plan review fee, mainly on jobs over $75,000
Water and sewerConstruction water, new account, sewer tap-on, water tap-on and meter fees
OtherRecapture fees, consultant review fees, DuPage impact fee receipt, school, park and library donations

Rather talk it over?

Call 1-855-478-4290 →

The village’s own worked example for $114,000 of work gives a permit fee of $12 × 114 = $1,368 and a refundable bond of $500 on the first $50,000 plus $320 on the remaining $64,000, or $820. Its plan review examples start from a $114 base (totals of $201 residential and $230 commercial with supplements), which does not match 10% of that $1,368 permit fee, so confirm the plan review amount with staff. New subdivisions also owe park, school and library land or cash contributions under Sections 90-97 and 90-98.

Trade permits and who may pull them

Contractors must register with the village, and most must post a bond, before they can work on a permitted job. A contractor registering for more than one trade pays $10 for each added trade.

Hanover Park contractor registration
ContractorFee and bond
General$105; $10,000 bond
Carpentry, concrete, fence, HVAC, sign$50 each; $10,000 bond
Electrical$50; $10,000 bond; license from the place where tested
Fire sprinkler$50; $10,000 bond; state license
Roofing$50; no bond; Illinois roofing license
Sewer$50; $20,000 bond
PlumbingNo fee; state 055 and 058 licenses and a letter of intent
AlarmNo fee; state license

Plumbing in Illinois is done by state-licensed plumbers. The village’s homeowner plumbing affidavit covers an owner doing plumbing in the home they live in, who must swear that it will remain their sole residence for at least six months after the work and will not be rented in that time. The village checks this when the house is sold and the transfer stamp is bought. For other trades, owners doing their own work sign the general owner affidavit.

Rather not deal with the building department?

Get a free quote →

How to apply for a Hanover Park building permit

1. Call or read the handout

Phone Inspectional Services at 630-823-5860 or download the handout for your project in English or Spanish.

2. Check zoning

If the project needs a variation or other relief, start with Community and Economic Development and the Development Commission.

3. Register contractors

Every contractor on the job registers and posts any required bond before the permit issues.

4. Get a JULIE dig number

Call 800-892-0123 before any digging work and put the number on the application.

5. Apply

Use the online building permit form or the paper application, with the plat of survey, drawings, estimate and materials list.

6. Pay and post

Pay the permit, plan review and bond amounts, then put the placard in a front window before work starts.

Review, corrections and what causes delay

Typical holdups are an unregistered or unbonded contractor, a reduced or missing plat of survey, a missing dig number and a valuation the building official decides to adjust. Remember that the office is closed on Wednesdays. For projects that go through the Development Commission, the village asks for revised drawings within about a week of staff comments so a hearing date can be set; hearings are scheduled only after the application is complete.

Inspections and bond refunds in Hanover Park

Give at least 24 hours’ notice for every inspection by calling Inspectional Services at 630-823-5860. Ask the division which inspections your permit needs, and call it to schedule the final inspection when the work is complete.

The refundable bond is held until every final inspection on the project has been approved. The village suggests getting the final inspection passed before you make the last payment to your contractor, so any corrections are made while the contractor still has a reason to come back.

Illinois building code in Hanover Park

Hanover Park adopts its building codes and local amendments in its Municipal Code; the energy handout applies the state energy code as the village adopted it. FEMA’s Community Status Book lists Hanover Park (community 170099, in both DuPage and Cook counties) as participating in the National Flood Insurance Program, with current flood maps effective January 23, 2026.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Want this handled start to finish?

Get a free quote →

Hanover Park building permit FAQs

How much is a building permit in Hanover Park?

$12 for each $1,000 of construction value, with a $50 minimum for residential and $100 for commercial work, plus plan review where it applies.

Why do I have to pay a bond?

Jobs of $5,000 or more may carry a refundable bond, 1% of the first $50,000 and 0.5% above that, returned after every final inspection is approved.

Do I need a permit for a shed or plastic storage bin?

A shed needs a permit and can be no larger than 200 square feet; a plastic bin under 25 square feet does not, up to two per lot.

How tall can my fence be?

Up to 6 feet in side and rear yards for wood, vinyl or masonry, 5 feet for other types, and 3 feet for decorative fences in the front yard.

Can I do my own plumbing?

Only in the home you live in, after signing the homeowner plumbing affidavit promising to live there for at least six months afterwards and not rent it.

Is the permit office open every weekday?

No. Village Hall and Inspectional Services are open Monday, Tuesday, Thursday and Friday from 8 a.m. to 4:30 p.m. and closed on Wednesdays.

How long does a zoning variation take?

The development application process takes at least three months, from staff review through a Development Commission hearing to the Village Board vote.

Hanover Park permit search and official resources

To look up an old permit, inspection or plan, file a written Freedom of Information Act request. Submit it online through the village’s NextRequest portal, or pick up a form at the Village Clerk’s Office, the Finance counter, the Police lobby or the Manager’s Office. The FOIA officer is the Village Clerk at 2121 Lake Street (630-823-5602); answers are due within five business days, or 21 working days for requests made for a commercial purpose.

Inspections are where schedules slip.

Get a free quote →

Simplify Hanover Park permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Hanover Park sooner?

Let Alliance prepare, file, and track your Hanover Park permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Hanover Park permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.