Ford County, Illinois Building Permit Guide

To get a building permit in Ford County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Ford County Zoning Office at the Paxton courthouse issues construction permits for new buildings and additions in unincorporated areas and in villages without their own zoning; Gibson City, Paxton and Piper City handle their own.

Authority: Ford County Zoning OfficeRule: Construction permit before any new building or additionPhone: 217-249-4727
Construction permit
$20 + $0.15/sq ftNon-farm work over 200 sq ft
Farm buildings
Permit, no feeNo fee by statute
Late filing
Double feeIf filed after the foundation is in
Septic permit
$250Ford County Public Health Department

Ford County has zoned its rural land since 1972, and the Ford County Zoning Office requires a construction permit before any new building goes up or any existing building gains floor area in the unincorporated county and in villages that have no zoning of their own. Non-farm projects pay $20 for the first 200 square feet and 15 cents a square foot beyond that, farm buildings need a permit but pay nothing, and starting before the permit doubles the fee. The zoning officer works from the courthouse at 200 W. State St., Paxton, by appointment (217-249-4727). Septic systems and wells go through the Ford County Public Health Department, and Gibson City, Paxton and Piper City run their own zoning.

What requires a permit in unincorporated Ford County?

The county’s rule is short: a construction permit is required for all new construction and for every project that increases the square footage of an existing building on the property, and it must be obtained before construction begins. The zoning page for the agricultural district repeats that construction permits are required for all buildings there, farm buildings included.

Construction permit

  • New houses and non-farm dwellings
  • Additions that add floor area
  • Garages, sheds and other accessory buildings
  • Agricultural buildings (permit required, no fee)
  • Commercial and industrial buildings

Zoning board approval

  • Conditional uses, including a non-farm dwelling on under five acres where no homesite exists
  • Special uses such as wind energy conversion systems
  • Variances from yard or parking rules
  • Rezoning and text amendments

The county’s pages describe the permit by new construction and added floor area; they do not list remodels, re-roofing or other work inside an existing footprint as needing a county permit, so ask the zoning officer if your project changes a building without enlarging it. The forms list also includes a notice of completion and a notice of destruction, the county’s forms for reporting finished and demolished buildings.

What the county decides and what the state holds

The county board adopted the zoning ordinance under the state’s county zoning statute (55 ILCS 5/5-12001 and following), revised it in February 2022, and adds wind and solar rules to it; the zoning office administers it. The county’s permit is a zoning construction permit tied to use, lot size and setbacks, and the county publishes no adopted building code. The state supplies the statutory building minimums described in the code section below, the private sewage and water well codes run by the health department, plumbing licensing and roofing licensing.

Ford County building department: who handles permitting

The Zoning Office, run by Zoning Enforcing Officer Brandon Magers, issues construction permits and processes variances, conditional uses, special uses and rezonings. It works from the Ford County Courthouse; call for an appointment.

Short on time to read all of this?

Get a free quote →
Ford County permit offices
OfficeRoleContact
Zoning OfficeConstruction permits, zoning boards, FOIA for zoning recordsFord County Courthouse, 200 W. State St., Paxton, IL 60957; 217-249-4727 (by appointment); courthouse 217-379-9400, 8:30 a.m. to 4:30 p.m.
Ford County Public Health DepartmentSeptic and well permits and inspections1500 W. Ottawa, Paxton, IL 60957; 217-379-9281, fax 217-379-2802; Monday to Friday 8 a.m. to 4:30 p.m.
Highway DepartmentCounty highways305 N. State Route 54, Roberts, IL 60962; 217-395-2206, fax 217-395-2207; 7 a.m. to 3:30 p.m.

Gregory L. Perkinson, P.E., is the County Engineer and the Highway Department’s FOIA officer. The county’s parcel map runs on the Ford County GIS site.

Cities and villages in Ford County

The county zoning ordinance covers the unincorporated county and any village without its own zoning. The county names three towns that zone for themselves:

  • Paxton (4,323 people), the county seat: the city publishes its own building permit application, zoning map, Planning Commission rezoning form and Zoning Board variance and special use form; City Hall is at 145 S. Market St. (217-379-4022).
  • Gibson City (3,371) and Piper City (722): the county sends owners inside their limits to the city or village.
  • Melvin (412), Roberts (340), Sibley (284), Elliott (272), Kempton (176) and Cabery (157 on the Ford County side): the county ordinance applies in any of these villages that has no zoning of its own; ask the zoning officer or the village clerk which applies before you build.

Ford County permit types

The county keeps two construction permit applications, a regular one and one for agricultural use, plus the zoning board applications.

Residential permits

  • House on farmland: in the AG-1 agricultural district a lot must be at least one acre (43,560 square feet) and 150 feet wide, with the house 50 feet back from a township road, 75 feet from a county road or 100 feet from a highway, 20 feet from the sides and 50 feet from the rear.
  • Non-farm dwellings: on less than five acres where no homesite already exists, a conditional use permit comes before the construction permit.
  • Accessory buildings: in the AG-1 and CO-1 districts, total accessory floor area is capped at 2,500 square feet on a one-acre parcel plus 1,000 square feet for each added acre (prorated); parcels of five acres or more have no size cap.
  • Farm buildings: use the agricultural use application; a permit is required, but no fee.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial and industrial buildings use the regular construction permit at the same square-foot fee; where the use is conditional or special in its district, the board approval comes first. Wind energy conversion systems are special uses under Appendix A of the zoning ordinance, amended on May 24, 2023, with a separate appendix for private wind turbines, and the county adopted a solar ordinance by Resolution 23-50; a 2025 resolution (25-19) deals with adding both to the zoning ordinance.

What comes before the construction permit

  • Dividing land: one division of a lot of one to three acres is allowed from a tract that existed on October 1, 1963; after that, divisions must be three acres or more, and lots need one acre and 150 feet of width in AG-1.
  • Board approvals: conditional uses go to the Planning Commission (second Thursday, 7:30 p.m.) and then the Zoning Board of Appeals (first Tuesday, 7:30 p.m.); rezonings also go to the county board (second Monday).
  • Farmland review: on agricultural land, the Soil & Water Conservation District may have to do a LESA study, for its own fee.
  • Septic and well: health department permits for rural lots.
  • Floodway: work in the floodway of a rural stream draining ten square miles or more needs a state permit from the IDNR Office of Water Resources.

Ford County permit fees

Ford County zoning and health fees
ItemFee
Construction permit, non-agricultural$20 for the first 200 sq ft and $0.15 per sq ft for structures over 200 sq ft
Construction permit, agricultural buildingNo fee (permit still required)
Permit applied for after the foundation is built or the structure erectedDouble the normal fee
Conditional use, special use or zoning amendment$100, non-refundable, plus newspaper notice costs
Variance$75, non-refundable, plus newspaper notice costs
LESA study (when required)Set by the Soil & Water Conservation District
Septic permit (Ford County Public Health Department)$250 ($100 permit plus $150 inspection)
Water well permit (state form, county health department)$250; $45 if the department samples the new well

Rather talk it over?

Call 1-855-478-4290 →

The zoning board fees are charged on top of the construction permit. Because the county bills the cost of the required newspaper notice to the applicant, budget for it with any conditional use, variance or rezoning. For a typical new rural home with a septic system and well, the health department fees alone come to $500, before the construction permit. Inside Paxton, Gibson City and Piper City, the town’s own fees apply.

Trade permits and who may pull them

Ford County’s zoning pages describe no county electrical, plumbing or mechanical permit and no county contractor license or registration; the construction permit is a zoning permit. The trade rules that reach rural projects:

  • Septic: the application asks for the installer’s license number, and the health department keeps an affidavit in which the property owner acknowledges responsibility for servicing and maintaining the system under the state private sewage act and code.
  • Sand filters and surface discharge: buried or recirculating sand filters must include the form stating the system does not discharge to waters of the United States.
  • Wells: construction, modification, sealing and closed-loop wells each have their own state application filed with the county health department.
  • Plumbing and roofing: plumbers are licensed by the Illinois Department of Public Health and roofing contractors by the Department of Financial and Professional Regulation.

Inside Paxton, Gibson City and Piper City, the town’s own rules apply to trade work.

How to get a Ford County construction permit

1. Check the jurisdiction and district

Find the parcel on the county GIS map and confirm it is outside Paxton, Gibson City and Piper City; note its zoning district.

2. Call the zoning officer

Book an appointment at 217-249-4727 to confirm setbacks, lot size and whether a conditional use or variance is needed first.

3. Get any board approval

File the conditional use, special use, variance or rezoning application with its fee, and allow for the neighbor opinion survey and the 15-day newspaper notice.

4. Apply for septic and well permits

File with the Ford County Public Health Department, with the soil evaluation and installer details.

5. File the construction permit

Use the regular or agricultural application, with the plans and site details the zoning officer asks for, and pay the fee.

6. Build, then report completion

Start only after the permit is issued, and file the county’s notice of completion when the building is done.

Rather not deal with the Ford County building department?

Get a free quote →

Review, corrections and what causes delay

Most delay comes from projects that need a board decision. Before the Zoning Board of Appeals can grant a conditional use it must refer the application to the Planning Commission, which has 30 days to report, and the board then holds a public meeting in the area after 15 days’ newspaper notice; neighbors within 300 feet in a village, or within 1.5 miles in the country, receive opinion surveys. Variances are narrow: the board may vary only yard rules for an unusual lot condition, or cut parking by no more than 50%. Building before the permit is issued doubles the fee.

Inspections in Ford County

The county’s zoning pages describe no building inspection stages and no certificate of occupancy; the forms list includes a notice of completion for finished buildings. The inspections that are published belong to the health department:

  • Septic systems: the septic application carries a $150 inspection fee, and the owner agrees the department may inspect to confirm the system meets the state code; the department notes that a permit and inspection do not guarantee trouble-free operation.
  • Low-pressure systems: the department uses a dedicated low-pressure piping inspection sheet.
  • Wells: staff inspect the construction or repair of wells and the capping or sealing of old wells; the department will sample a new well for $45, or send a state sample kit.
  • Radon: free radon test kits are available from the department.

Illinois building code in Ford County

Ford County’s published rules are its zoning ordinance (adopted 1972, revised February 2022) with its wind and solar provisions, its nuisance ordinance and the health department’s septic and well programs; no county building code is posted, so the statutory minimums below apply to new homes and commercial buildings on unincorporated land. FEMA’s Community Status Book lists unincorporated Ford County (community 170991) under communities not in the National Flood Insurance Program, with flood maps dated May 17, 2022.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Want this handled start to finish?

Get a free quote →

Ford County permit FAQs

How much is a construction permit in Ford County?

For non-farm work, $20 for the first 200 square feet and 15 cents per square foot for structures over 200 square feet; farm buildings pay nothing.

Do farm buildings need a permit?

Yes. Agricultural buildings require a construction permit, but by statute no fee is charged.

What happens if I start building before I get the permit?

If you apply after the foundation is in or the structure is up, the fee is doubled.

Can I build a house on a small lot in the country?

In AG-1 the lot must be at least one acre and 150 feet wide, and a non-farm dwelling on under five acres without an existing homesite needs a conditional use permit.

Does the county handle permits in Paxton or Gibson City?

No. Gibson City, Paxton and Piper City have their own zoning; Paxton publishes its own building permit application.

How much is a septic permit?

$250 at the Ford County Public Health Department: $100 for the permit and $150 for the inspection.

How do I get a variance?

Apply to the Zoning Board of Appeals with the $75 fee; it meets on the first Tuesday at 7:30 p.m. after a published notice.

Is unincorporated Ford County in the flood insurance program?

FEMA lists it among communities not participating, with flood maps dated May 17, 2022.

Ford County permit records and official resources

Construction permits and zoning board files are kept by the Zoning Office, whose zoning officer is also the Freedom of Information officer for the office and the zoning boards; send records requests to him in writing. Septic and well permits are with the health department, highway records with the County Engineer, and board resolutions on the county’s resolutions page. The county’s forms page lists the zoning ordinance, the wind and solar rules and the permit applications; if a document will not open there, ask the zoning officer for a current copy.

Inspections are where schedules slip.

Get a free quote →

Simplify Ford County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Ford County sooner?

Let Alliance prepare, file, and track your Ford County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Ford County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.