Livingston County, Illinois Building Permit Guide

To get a building permit in Livingston County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Livingston County’s Regional Planning and Zoning office in the Pontiac courthouse issues improvement location permits and certificates of occupancy for rural land; Pontiac and the villages handle their own permits.

Authority: Livingston County Regional Planning and ZoningPermit: Improvement location permitPhone: 815-844-7741
Location permit fee
$20 to $150By type and size of work
Start of work
Within 120 daysOr the permit is void
Septic permit
$300Livingston County Health Department
Office hours
8 a.m. to 4:30 p.m.Weekdays, Historic Courthouse

For land outside Livingston County’s cities and villages, the county’s permit is an improvement location permit and certificate of occupancy from the Regional Planning and Zoning office at the Historic Courthouse, 112 W. Madison Street, Pontiac (815-844-7741). It checks that a house, shed, pole barn, grain bin, solar array or other structure fits the county zoning ordinance and comprehensive plan, costs $20 to $150 depending on the type and size of the work, and lapses if construction does not start within 120 days. Septic systems and wells need separate Livingston County Health Department permits.

What requires a permit in unincorporated Livingston County?

The county code requires an improvement location permit to alter, change, place, erect or locate a structure or improvement, or to change the use of land, on platted or unplatted land. The permit application lists the projects the office sees most often:

County location permit

  • Single-family dwellings and dwelling additions
  • Attached and detached garages, carports, breezeways and porches
  • Garden sheds, machine sheds and pole barns
  • Decks and pools
  • Grain bins
  • Ground-mount and roof-mount solar arrays, and solar farms
  • Wind farms, meteorological towers and cell towers, and upgrades to them
  • Advertising structures and commercial buildings

Separate approvals

  • Septic systems, wells, geothermal loops and surface water use: Health Department
  • Work in a county highway right-of-way: Highway Department construction or utility permit
  • Variations, special uses, rezonings and subdivisions: hearings before the county boards
  • Work inside a city or village: that municipality

The application warns that a permit gives no right to build anything that does not conform to the county comprehensive plan, the code of ordinances or other local, state or federal rules, and that a permit issued on inaccurate information may be revoked without notice.

What the county decides and what the state holds

The county board sets the zoning ordinance, subdivision code, comprehensive plan and special ordinances for commercial solar and battery storage, commercial wind energy facilities and youth camps. The county’s permit checks location, size, setbacks and use; its application asks for a site plan and dimensions rather than construction drawings. Private sewage systems follow the Illinois Private Sewage Disposal Code and wells the state water well rules, both enforced by the county health department, while plumbing follows the state plumbing code and plumbers and roofers hold state licenses.

Livingston County building department: who handles permitting

The Regional Planning and Zoning office plans the county’s physical growth, administers the zoning ordinance and subdivision code, and supports the Regional Planning Commission and the Zoning Board of Appeals. Its staff are led by the Planning and Zoning Administrator, Brittney Miller.

Short on time to read all of this?

Get a free quote →
Livingston County offices for rural projects
OfficeContact
Regional Planning and Zoning (location permits, zoning)Historic Courthouse, 112 W. Madison Street, Pontiac, IL 61764; 815-844-7741, fax 815-844-6662; Monday to Friday 8 a.m. to 4:30 p.m.
Health Department, Environmental Health (septic, wells)310 E. Torrance Avenue, Pontiac; 815-842-5916, fax 815-842-4070
Highway Department (county highways)1705 S. Manlove Street, Pontiac; 815-842-1184; Monday to Friday 7 a.m. to 3:30 p.m.; County Engineer Clay Metcalf

Livingston County has 16 cities, villages and towns in whole or part. The county seat, Pontiac (population 10,806), runs its own Building and Zoning Office at 115 West Howard Street (815-844-1038). The other municipalities, including Dwight (the Livingston County part has 3,991 people), Fairbury (3,597), Chatsworth (1,156), Flanagan (1,022), Forrest (1,015) and Odell (974), and the smaller villages of Cullom, Cornell, Saunemin, Long Point, Campus, Strawn and Emington, plus the slivers of Streator and Reddick, are separate governments; ask the city or village hall about permits inside their limits.

Livingston County permit types

The county uses one form, the application for improvement location permit and certificate of occupancy, for every structure type. It asks for the owner and applicant or contractor, the site address and parcel number, what is being built and its use, the width, length and height, the front, side and rear setbacks, and the cost of construction excluding land. You choose whether the permit is mailed or emailed to you.

Residential permits

  • Houses and additions: the location permit, with Health Department septic and well permits where the home is not on public sewer or water.
  • Accessory buildings: garages, garden sheds, pole barns, carports, decks and pools each use the same form with a site plan.
  • Solar: roof-mount and ground-mount arrays are permit categories of their own.
  • Site plan: show the buildings, their location, setback distances and roads; every measurement is taken from the public road right-of-way line or the road centerline.

Commercial permits

Commercial buildings, advertising structures and cell towers use the same location permit. Large energy projects follow the county’s commercial solar and battery storage and commercial wind energy ordinances, and under the zoning efficiency ordinance adopted in April 2024 the Regional Planning Commission reviews special use applications for commercial solar or wind facilities of 6 megawatts AC or more, airports and heliports, and mineral extraction, along with text and map amendments, subdivisions and planned unit developments. The office’s document center posts the full special use filing for the proposed Panther Grove 2 wind farm.

Not sure this scope needs a permit?

Get a free quote →

Work along county highways

The Highway Department maintains 257 miles of county highways and helps the 30 townships plan work on their 1,610 miles of roads, which are run by township road commissioners. Its construction or utility permit sets firm conditions: roadways may not be open-cut, so pipes, cables and field tiles crossing a county highway or an intersection with another public road must be directionally bored or jacked, and tiles under a county highway are bored from right-of-way line to right-of-way line. Tile under the road must be at least SDR 35 pipe where the cover at the centerline is under 10 feet, and SDR 26 where it is deeper. Because the county does not own the ground under the right-of-way, utility applicants must first contact the adjacent landowners, as state highway law requires, and ask about buried drainage tiles that a JULIE locate may miss; the applicant pays for any damage and for moving the line if the road is later rebuilt.

What comes before the location permit

  • Health approvals: septic and well permits from the Health Department for unsewered homes.
  • Zoning relief: a variation application with a scaled map of the area within 200 feet goes to the Zoning Board of Appeals; special uses for large energy projects, airports and mineral extraction also go to the Regional Planning Commission.
  • Road work: driveways, tiles or utilities in a county highway right-of-way need the Highway Department’s construction or utility permit.
  • Utility locates: call JULIE at 811 before digging.
  • Flood maps: FEMA’s map for unincorporated Livingston County is dated December 18, 2007.

Livingston County permit fees

The county’s variation packet gives its fee examples. The improvement location permit costs $20 to $150, with the exact amount set by the type and size of the improvement, and checks are payable to the Livingston County General Fund. Health Department amounts come from its 2026 fee schedule (September 2026).

Rather talk it over?

Call 1-855-478-4290 →
Livingston County permit and health fees
ItemFee
Improvement location permit$20 to $150, by type and size
Variation application filing fee$125
Variation publication feeUsually $40 to $70, by notice length
Septic permit (Health Department)$300
Water well permit$100
Water well modification$100
Well sealingNo charge
New well water sample$50
Geothermal exchange system$100 per 5 loop wells
Surface water use permit$100
Real estate inspection: well / septic / both$150 / $150 / $300

A new rural home on a septic system and private well therefore pays the location permit fee, the $300 septic permit and the $100 well permit, plus $50 for the new-well water sample. The county code of ordinances, linked from the office’s page, holds the full fee rules; the office notes that the online copy may not be the most current version, so confirm the location permit amount when you file.

Trade permits and who may pull them

The county’s location permit application has no trade permit sections and no contractor registration; it names the applicant or contractor and needs both the owner’s and the applicant’s signatures.

  • Septic installers: the Health Department tests and licenses installers, approves plans for new systems, issues permits and inspects; its 2026 forms cover construction permits, subsurface systems and commercial systems, and each must be completed in full and mailed with the fee.
  • Well drillers: well permits are issued under state statute by the Health Department, which also permits modifications and seals wells at no charge.
  • Plumbing and roofing: plumbers and roofing contractors hold state licenses, and plumbing follows the Illinois Plumbing Code.
  • Road and utility contractors: roadways may not be open-cut, lines crossing a county highway must be bored or jacked, and traffic control follows the state manual.

Inside Pontiac, every contractor and subcontractor registers with the city; other municipalities set their own rules.

Rather not deal with the Livingston County building department?

Get a free quote →

How to get a Livingston County location permit

1. Confirm the jurisdiction

Make sure the parcel is outside Pontiac and the villages; inside them, apply to the municipality.

2. Sort out septic and well

File the Health Department’s septic and well applications by mail with their fees.

3. Draw the site plan

Show buildings, setbacks and roads, measuring from the road right-of-way line or centerline.

4. Complete the application

Fill in the structure type, size, setbacks and cost, and sign as owner and applicant.

5. File and pay

Bring or send it to the Historic Courthouse with a check to the Livingston County General Fund.

6. Start within 120 days

Begin construction within 120 days and notify the Zoning Administrator at each stage listed on the permit.

Review, corrections and what causes delay

A project that does not meet setbacks or the zoning district rules needs a variation or special use before a permit, which means a public hearing and newspaper notice; the Regional Planning Commission meets in the evening on the first Monday of each month. Inaccurate information on the application can lead to revocation. If construction does not start within 120 days, the permit is void unless the Zoning Board of Appeals grants an extension.

Inspections and occupancy in Livingston County

The improvement location permit lists the stages of construction at which you must notify the Zoning Administrator, and the same form issues the certificate of occupancy. The other inspections on a rural build come from the Health and Highway Departments:

  • Septic systems: the Health Department inspects private sewage systems it permits and maintains oversight of EPA-regulated treatment systems.
  • Wells: a new well is sampled for $50.
  • Road work: notify the Highway Department 48 hours before starting; no work on weekends or holidays, daylight only, and damaged field tiles must be restored.
  • Home sales: real estate inspections cost $150 for a well or septic system, $300 for both with a water sample.

Illinois building code in Livingston County

The county regulates rural construction through its zoning ordinance, subdivision code and the location permit described above. FEMA’s Community Status Book lists Livingston County (community 170929, unincorporated areas) as participating in the National Flood Insurance Program, with its first flood map and current map both dated December 18, 2007; the county has no Community Rating System class.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Want this handled start to finish?

Get a free quote →

Permit search and official resources

For past permits or zoning files, send a written Freedom of Information Act request by mail, fax, email or in person to the county; no standard form is required. The county answers within five business days, and the first 50 black-and-white pages are free, then 15 cents a page.

Inspections are where schedules slip.

Get a free quote →

Livingston County permit FAQs

Does Livingston County issue permits inside Pontiac or Fairbury?

No. The county’s location permit covers land outside the cities and villages; Pontiac has its own Building and Zoning Office, and other municipalities handle permits inside their limits.

How much is a county location permit?

$20 to $150, depending on the type and size of the improvement, payable to the Livingston County General Fund.

Do I need a county permit for a pole barn or grain bin?

Yes. Machine sheds, pole barns and grain bins are listed on the improvement location permit application.

How long do I have to start building?

120 days from issue; after that the permit is void unless the Zoning Board of Appeals extends it.

How much is a septic permit?

$300 from the Livingston County Health Department; a new well permit is $100.

How do I ask for a variance?

File the variation application with a scaled map of the area within 200 feet; the filing fee is $125 plus newspaper publication, usually $40 to $70.

Who do I call about a culvert or utility line along a county highway?

The Livingston County Highway Department at 815-842-1184, which issues construction or utility permits.

Simplify Livingston County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Livingston County sooner?

Let Alliance prepare, file, and track your Livingston County permits while your crew stays on the job.