Logan County, Illinois Building Permit Guide

To get a building permit in Logan County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Logan County Zoning Office in Lincoln issues building permits for unincorporated Logan County and for villages with no zoning ordinance of their own; the county has adopted no building code.

Authority: Logan County Zoning OfficeFiling: Paper application, 529 S. McLean StreetPhone: 217-732-4773
New home permit
$4 per $1,000Of construction cost, $25 minimum
Building code
None adoptedZoning permit and inspections
Start of work
Within 90 daysOr a new permit is needed
Sewage permit
$200Logan County Department of Public Health

In unincorporated Logan County, and in villages that have no zoning ordinance of their own, building permits come from the Logan County Zoning Office at 529 S. McLean Street in Lincoln (217-732-4773). The county has not adopted a building code: its permit, formally a certificate of zoning compliance, checks setbacks, lot size and use under the zoning ordinance, and a new house cannot be occupied until a state-licensed home inspector’s reports support a certificate of occupancy. Fees run $4 per $1,000 of construction cost for new homes and $2 per $1,000 for additions, each with a $25 minimum.

What requires a building permit in Logan County?

The zoning ordinance makes it unlawful to start excavating for, building, moving or altering any building, accessory buildings included, until the County Zoning Officer issues a building permit. The office’s answers to common questions spell out what that covers:

Permit required

  • All new construction, additions and remodeling
  • Accessory structures such as sheds, storage buildings, grain bins, decks and sunrooms
  • Portable structures
  • Above-ground and inground pools
  • Fences in a required front yard in residential, business or manufacturing districts, and anything in a sight triangle at an intersection
  • Signs, towers and transmission poles
  • Residential solar and battery storage; commercial wind and solar farms (siting approval)
  • Development in a floodplain (floodplain development permit)

No permit needed

  • Routine maintenance or repair, such as repainting or re-roofing
  • Alterations to existing buildings with a replacement value under $300
  • A service connection to a utility system
  • Highways, roads and similar transportation structures (not buildings)

Agricultural buildings still need a permit, but no fee is charged for one used solely for agricultural purposes. When construction starts before the permit is issued, the ordinance increases the permit fee by 100%, or a minimum of $200, whichever is greater.

What the county decides and what the state holds

The County Board adopts the zoning ordinance, sets permit fees by resolution and has not adopted a building code, so the county permit is a zoning check rather than a structural plan review. State law fills part of that gap, as the county’s permit packet notes: new homes must comply with the Illinois Residential Building Code Act, and since January 1, 2025 new non-farm commercial buildings must meet the state’s inspection certification law for areas without a building code. Septic systems and wells follow state codes enforced by the county health department, plumbing follows the Illinois Plumbing Code, and plumbers and roofers hold state licenses.

Logan County building department: who handles permitting

The Logan County Zoning Office administers the zoning ordinance, reviews and issues building permits, and processes variances, conditional uses, special use permits and rezonings. It sits in the Logan County Highway Department building, four blocks south of the courthouse in downtown Lincoln.

Short on time to read all of this?

Get a free quote →
Logan County offices for rural building projects
OfficeContact
Logan County Zoning Office (building permits, zoning)529 S. McLean Street, Lincoln, IL 62656; 217-732-4773; zoning@logancountyil.gov; Monday to Friday 8:30 a.m. to 4:30 p.m.; Zoning Officer Allan M. Green
Logan County Department of Public Health, Environmental Health (sewage, wells)109 Third Street, Lincoln; 217-735-2317
County Engineer or township highway supervisor (driveways)The road authority for the road the driveway joins

Zoning maps, listed by township, show a parcel’s district and therefore its setbacks. The county seat, Lincoln (population 12,981), is a separate city government with its own building and zoning office. Atlanta (1,626), Mount Pulaski (1,499), Emden (452), Elkhart (437), Latham (321), Middletown (317), New Holland (262), Hartsburg (255), Broadwell (138) and the Logan County part of San Jose (183) are separate municipalities; where a village has no zoning ordinance of its own, the county ordinance and its permits apply there, so ask the Zoning Office which case your village is in.

Logan County permit types

The county’s 2025 building permit packet uses one application for houses, accessory buildings and commercial construction. It asks for the owner and applicant, the address and parcel number, what is being built and its use, the width, length and height, the front, side and rear setbacks, whether public water and sewer are available, and the cost of construction excluding land. The ordinance asks for applications in triplicate with a plat of survey by a registered land surveyor showing the site, existing and proposed structures, easements, parking, driveways and highway access restrictions, and abutting land within 40 feet.

Residential permits

  • New homes: the application, plat, Health Department sewage and well approvals where public service is not available, the driveway approval, and the signed acknowledgment of inspections and certificate of occupancy.
  • Setbacks: in the agricultural district, 100 feet from a federal highway right-of-way, 50 feet from a state highway and 35 feet from a county or township road right-of-way; in R-1 to R-3 districts, 25 feet front, 30 feet rear and side yards of 10% of lot width.
  • Lot size and dwellings: new agricultural lots need five acres (one acre for an existing farmstead), and only one dwelling is allowed per parcel.
  • Fences: residential fences may sit on property lines but no closer than 2 feet to a public right-of-way; security fences may reach 10 feet and must be an open type such as woven wire or wrought iron.
  • During construction: an RV may be used on the site while a new or fire-damaged home is built, at no charge, if requested with the permit and placed at least 10 feet from the dwelling.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial buildings use the same application and pay higher rates. Business districts B-2 and B-3 need 20-foot rear yards (B-3 also 25 feet front and 10 feet side), and manufacturing districts need 50 feet from any street right-of-way and 20 feet from other lot lines, with one-acre minimum lots. Commercial wind and solar energy facilities need siting approval under their own ordinance appendices, and towers and poles have flat fees.

What comes before the building permit

  • Driveway approval: a new driveway must be reviewed by the County Engineer for a county road or the township highway supervisor for a township road, using the private access permit form; no building permit is issued until that approval is in hand.
  • Sewage and water: where municipal sewer or water is not available, the Health Department must approve the sewage disposal plan and well plan first.
  • Zoning relief: variances go to the Zoning Board of Appeals; conditional uses, special uses and map or text amendments go to the Planning Commission first, then the ZBA.
  • Floodplain: development in a flood area needs the county’s floodplain development permit.

Logan County permit fees

The County Board sets fees by resolution under Section 14 of the zoning ordinance, and the Zoning Office posts the current schedule:

Logan County zoning and building permit fees
ProjectFee
General application fee$25
Residential construction$4 per $1,000 of construction cost, $25 minimum
Residential additions or alterations$2 per $1,000, $25 minimum
Above-ground pool / inground pool$25 / $50
Commercial construction$8 per $1,000, $500 minimum
Commercial additions or alterations$4 per $1,000, $250 minimum
Residential sign / commercial sign$10 / $1 per $1,000, $25 minimum
Residential solar and battery storage$15 per kW DC
Communication or energy transmission tower or pole$2,000 each; $750 to alter an existing one
Commercial wind or solar and storage farm$5,000 per MW DC nameplate output
Zoning Board of Appeals hearing application$500

Rather talk it over?

Call 1-855-478-4290 →

Under the residential rate, a new house costing $250,000 carries a permit fee of $1,000 ($4 × 250), and a $40,000 addition $80 ($2 × 40); the schedule lists the $25 general application fee as a separate line. Agricultural buildings pay no permit fee. Checks are payable to Logan County, newspaper notice costs for hearings are paid by the applicant before the case is heard, and permit fees are not refunded once a permit is issued. Health Department fees are separate: $200 to apply for a sewage permit and $100 for a well permit.

Trade permits and who may pull them

With no county building code, the county’s zoning pages list no electrical, plumbing or mechanical permits and no contractor registration for building trades. The trade checks on a new house come through the owner’s home inspector, whose pre-drywall inspection covers the plumbing, electrical and HVAC rough-in.

  • Septic installers and pumpers: must register every year with the Health Department’s Division of Environmental Health, at no charge, with a copy of their current Illinois license; unregistered contractors cannot get installation permits.
  • Who may install a septic system: only Illinois licensed private sewage installation contractors, or property owners installing their own systems.
  • Wells: qualified installers apply for the $100 well permit and must notify the Health Department at least two days before starting; licensed pump installers file their own report.
  • Plumbing and roofing: plumbers and roofing contractors hold state licenses, and plumbing follows the state plumbing code.

Inside Lincoln and villages with their own ordinances, trade and contractor rules are set by that municipality.

How to apply for a Logan County building permit

1. Check the zoning district

Find the parcel on the township zoning maps to learn its setbacks and minimum lot size.

2. Get the driveway approved

Have the County Engineer or township highway supervisor sign the private access permit for any new driveway.

3. Clear sewage and water

Apply to the Health Department with a soil classifier’s report ($200) and for a well permit ($100) where public service is not available.

4. Prepare the plat and application

Complete the 2025 application with a surveyor’s plat, dimensions, setbacks and cost of construction.

5. File and pay

Submit at 529 S. McLean Street with a check payable to Logan County; sign the inspection acknowledgment for a new home.

6. Start within 90 days

Work not substantially started within 90 days needs a new permit.

Rather not deal with the Logan County building department?

Get a free quote →

Review, corrections and what causes delay

The most common hold-ups are a missing driveway approval, which blocks issue of the permit, and an unapproved sewage plan. A project that breaks a setback needs a variance before a permit can issue, and the office’s own example is an addition to an older house that already sits in a required setback. The ZBA generally meets the first Thursday of the month at 7:30 p.m., and petitions that need Planning Commission review first are heard the Thursday after that commission’s first-Wednesday meeting. False or inaccurate information voids the application, and the Zoning Officer revokes a permit when its rules are being broken.

Inspections and occupancy in Logan County

No single-family home, and no addition of more than 750 square feet to one, may be occupied until the Zoning Officer issues a certificate of occupancy. That needs inspections by an Illinois state-licensed home inspector, hired by the owner, whose reports state that the work meets ASHI or InterNACHI standards:

  • Pre-drywall: foundation components; floor, wall and roof structure; plumbing, electrical and rough-in work; windows and exterior doors; HVAC systems.
  • Final: exterior stairs and handrails, surface drainage, porches, decks, entrance steps and patios.
  • Proof of corrections: the owner or inspector submits each phase’s findings with before-and-after photographs.
  • Manufactured and modular homes: exempt for the structure, but the foundation, stairs, drainage, porches, decks, steps and patios are still inspected.

The Health Department inspects each septic system before it is backfilled and inspects and samples new wells. Violations of the zoning ordinance can bring a fine of up to $500, with each week a separate offense.

Illinois building code in Logan County

Logan County has not adopted a building code, so its permits apply the zoning ordinance, with the state’s residential and commercial inspection laws as the county packet cites them. FEMA’s Community Status Book lists Logan County (community 170427, unincorporated areas) among participating communities in the National Flood Insurance Program, with a program date of September 2, 1988 and no flood map dates shown; the county has no Community Rating System class.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Permit search and official resources

The Zoning Office files every application and permit for reference. To get copies, print the Logan County General FOIA Form from the county’s FOIA page and mail or deliver it to the Zoning Office; for a septic system map, the Health Department takes requests through its online form.

Inspections are where schedules slip.

Get a free quote →

Logan County permit FAQs

Does Logan County enforce a building code?

No. The county has not adopted a building code; its permit enforces the zoning ordinance, and new homes need home-inspector reports before a certificate of occupancy.

How much is a building permit for a new house?

$4 per $1,000 of construction cost with a $25 minimum, so a $250,000 house pays $1,000; the schedule also lists a $25 general application fee.

Do I need a permit to re-roof or paint?

No. Routine maintenance or repair, such as repainting or re-roofing, needs no permit; nor do alterations with a replacement value under $300.

Do farm buildings need a permit?

Yes, a permit is still issued, but no fee is charged for buildings used solely for agricultural purposes; grain bins are on the permit list.

Can I put a second house on my rural property for family?

No. Only one dwelling is allowed per parcel; another home needs its own parcel meeting the district’s minimum lot size.

How much is a septic permit in Logan County?

$200 to apply to the Logan County Department of Public Health, with a soil classifier’s report; a well permit is $100.

Does the county issue permits inside Lincoln?

No. Lincoln runs its own building and zoning office; the county covers unincorporated land and villages with no zoning ordinance of their own.

Simplify Logan County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Logan County sooner?

Let Alliance prepare, file, and track your Logan County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Logan County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.