Edgar County, Illinois Building Permit Guide

To get a building permit in Edgar County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Edgar County has no county building department: in unincorporated areas its permits are septic and well permits from the Edgar County Public Health Department and county ordinances for commercial solar and wind farms, while Paris and the other towns handle their own building permits.

Authority: Edgar County Public Health Department (septic, wells)Filing: Paper applicationPhone: 217-465-2212
Septic permit
$125Inspection included; soil test required
Well permit
$125New, modified or sealed wells
Solar farms
Special use permitOrd. 2026-43; wind: Ord. 2025-100
City of Paris permits
217-465-7601Code Enforcement Office, City Hall

Edgar County government lists no building, zoning or planning office, and on unincorporated land the permits it publishes come from two places: the Edgar County Public Health Department at 502 Shaw Avenue, Paris (217-465-2212), which issues private sewage disposal (septic) and water well permits for $125 each, and the county’s energy ordinances: a special use permit for commercial solar energy facilities under the ordinance adopted July 22, 2026, and a separate ordinance for commercial wind energy facilities adopted December 10, 2025. Inside Paris, building, electrical and plumbing permits come from the city’s Code Enforcement Office at City Hall.

What requires a permit in unincorporated Edgar County?

Outside the cities and villages, the county’s published permit requirements center on wastewater, wells and large energy projects. The county website’s list of offices includes no building, zoning or planning department, and its posted ordinances do not set up a county building permit for houses, garages or farm buildings.

County permits on unincorporated land

  • A private sewage disposal system, new or renovated, for a house, a business or several systems on one site
  • Constructing, modifying or sealing a water well
  • A commercial solar energy facility, its substation, battery storage or supporting facilities (special use permit, then a county building permit)
  • A commercial wind energy facility (County Board ordinance)
  • Building or remodeling a food establishment (Health Department plan review)

Handled elsewhere

  • Building, electrical and plumbing permits inside Paris: the City of Paris
  • Permits inside Chrisman and the villages: each town’s own office
  • Plumbing work itself: the state plumbing code and a state-licensed plumber
  • Roofing contractors: the state roofing license

What Edgar County decides and what the state holds

The County Board adopts the county’s ordinances, including the Edgar County Private Sewage Disposal Ordinance that the septic application cites, the Commercial Wind Energy Facility Ordinance (Ordinance 2025-100, adopted December 10, 2025) and the second amended Commercial Solar Energy Facility Ordinance (Ordinance 2026-43, adopted July 22, 2026). The Public Health Department, formed by County Board resolution in 1994, works under the Edgar County Board of Health. Septic systems must also meet the state Private Sewage Disposal Licensing Act and Code, and well permits are issued on the Illinois Department of Public Health’s application form.

Short on time to read all of this?

Get a free quote →

Edgar County building department: who handles permitting

For a parcel in unincorporated Edgar County, the Public Health Department’s Environmental Health staff issue septic and well permits and inspect the work, the county holds the public hearing and decides special use permits for commercial solar facilities, and the Highway Department maintains 167 miles of county highway and helps the 15 townships with their 885 miles of roads and their bridges. Inside a city or village, the town’s own office decides what permits apply. To check whether an address is inside a town, look the parcel up by its property identification number on the county’s GIS, linked from the Property Records page, or call the Office of Assessment.

Edgar County offices for permits and property questions
OfficeHandlesContact
Public Health Department, Environmental HealthSeptic and well permits, food plan review, nuisance complaints502 Shaw Avenue, Paris; 217-465-2212; fax 217-465-1121; Monday to Friday 8 a.m. to 4 p.m.
Highway DepartmentCounty highways, township road and bridge assistance12637 E. 950th Road, Paris; 217-465-4139; County Engineer Aaron Lawson, P.E.
Office of AssessmentProperty records and parcel GISCourthouse Annex, 111 Sheriff Street, Suite A, Paris; 217-466-7418
Clerk & RecorderCounty Board records, recording of deeds and ordinances115 W. Court Street, Room J, Paris; 217-466-7433; Monday to Friday 8 a.m. to 4 p.m.
911 ServicesEmergency telephone system228 N. Central Avenue, Paris; 217-465-4166

Cities and villages in Edgar County

Who handles building permits in each Edgar County town
TownBuilding permits
Paris (city, county seat)City Code Enforcement Office, City Hall, 206 S. Central Avenue; 217-465-7601; weekdays 8 a.m. to noon
Chrisman (city)The published sources do not say; ask the city clerk
Brocton, Hume, Kansas, Metcalf, Redmon and Vermilion (villages)The published sources do not say; ask the village clerk

In Paris, the Code Enforcement Office inspects building, electrical, plumbing, mechanical and fire work, administers the zoning ordinance and supports the Planning Commission. The city’s 2026 permit form covers building, alterations, electrical, plumbing and signs, lists water and sewer tap fees, and states that Paris has adopted the current International Building Codes and National Electrical Code, the state plumbing code, the International Fire Code and the 2000 International Energy Conservation Code.

Edgar County permit types

All county permits are paper applications filed with the office that issues them; the Health Department posts its septic, well and food forms online, and the energy ordinances are on the county’s downloads page.

Not sure this scope needs a permit?

Get a free quote →

Residential permits

  • Septic systems. The Private Sewage Disposal System Plan Review Application asks for the owner, the contractor and license number, the site’s township, range and section, directions, the number of bedrooms and residents, any garbage grinder, water softener or hot tub, and the water supply. A soil test by a soil investigator sets the loading rate (percolation tests are not accepted), and the soil report goes with the application, along with a scaled lot diagram showing the system, wells (including a neighbor’s near the line), water lines, buildings and elevations.
  • Who may install it. A homeowner who owns and lives in the single-family house may do the work; anyone else must be a licensed contractor.
  • Setbacks. The septic tank must sit at least 5 feet from the building, 50 feet from a well, 10 feet from a pressure water line and 50 feet from a suction line; the seepage field at least 10 feet from the building, 75 feet from a well and 5 feet from the property line.
  • Wells. New, modified or abandoned wells use the state well permit application, which asks for the county property identification number and the signatures of the licensed well and pump contractors or the property owner. The department no longer does general well water testing.

Commercial permits

Commercial septic systems use the same application and $125 fee. Food establishments pay the Health Department $150 for plan review of new construction or $100 for a remodel, plus a food permit. Commercial solar facilities follow a multi-step county process: under the solar ordinance, no facility, substation, battery storage or supporting facility may be built without a special use permit followed by a county building permit for the facility, and solar farms are allowed only in agricultural or industrial zoned districts. The ordinance does not cover battery storage that is not part of a solar facility.

Rather talk it over?

Call 1-855-478-4290 →

What comes before the building permit

  • Incorporated or not. Confirm on the county GIS whether the parcel is inside Paris, Chrisman or a village; if it is, start with that town.
  • Septic before construction. On a rural lot the septic design depends on the soil test, so order it before settling the house plan.
  • Solar projects. Hold a public meeting in the township at least 60 days before filing, notify every landowner and resident within 1.5 miles, sign an agricultural impact mitigation agreement with the Illinois Department of Agriculture, and include IDNR and U.S. Fish and Wildlife reviews, a decommissioning plan and a site plan showing residences within 1,500 feet. File 20 paper copies plus an electronic copy; the hearing must end within 60 days of filing and the county decides within 30 days after it.
  • Floodplain and roads. FEMA lists unincorporated Edgar County as a National Flood Insurance Program community, so building in a mapped flood zone is subject to the county’s flood rules; for work along a county highway or township road, the Highway Department maintains those roads.

Edgar County permit costs and fees

The county publishes no general building permit fee for unincorporated land. The fees that do apply there are the Public Health Department’s current fee schedule:

Edgar County Public Health Department fees (current fee schedule)
WorkFee
Septic permit (residential, commercial or multi-system)$125, including a $25 inspection fee
Water well permit$125
Food establishment plan review, new construction$150
Food establishment plan review, remodel$100
Food permit, category I / II / III$250 / $200 / $100
Temporary food permit, single event / annual$30 / $75
Re-inspection$25

Worked example: a new house on a rural lot that needs both a well and a septic system pays $125 plus $125, or $250, to the Health Department, plus the soil test and contractor costs set privately. Inside Paris, the city’s building permit rate chart charges by estimated value, for example $100 for work valued between $49,001 and $50,000, with electrical, plumbing, sign and tap fees listed separately on the permit form.

Trade permits and who may pull them

On unincorporated land, the trade work the county regulates is wastewater and wells. A septic system must be installed by a licensed contractor unless the homeowner owns and occupies the single-family house, and the installer works to the state Private Sewage Disposal Code and the county ordinance. Wells and pumps are signed off by licensed water well and pump installation contractors or by the property owner on the state form. Plumbing follows the state plumbing code and is done by a state-licensed plumber, and roofers carry the state roofing license. The county’s pages show no county contractor registration or electrician license. In Paris, the permit form records the general contractor, electrician, roofer and plumber, with license numbers for the roofer and plumber.

Rather not deal with the Edgar County building department?

Get a free quote →

How to get a permit in Edgar County

1. Confirm the jurisdiction

Find the parcel on the county GIS or call the Office of Assessment at 217-466-7418.

2. Inside a town, go to the town

In Paris, pick up or download the building permit application and return it to City Hall.

3. Order the soil test

For a rural septic system, have a soil investigator test the site and write the report.

4. File with the Health Department

Submit the septic or well application, lot diagram and fee at 502 Shaw Avenue.

5. Notify before building

The septic contractor notifies the department 48 hours before work starts; well work needs notice at least two days ahead.

6. Final inspection

Call for the septic final before any part of the system is covered.

Review, corrections and what causes delay

A septic application without a soil report cannot be approved, because percolation results are not accepted, and the lot diagram must show the wells, water lines, buildings and elevations the setback rules are checked against. Material changes to a commercial solar application are not allowed once the hearing notice is published, unless the county requests or permits them.

Inspections and final approval

The Health Department inspects septic systems as part of the $125 permit. The contractor must notify the department 48 hours before construction and call for final inspection and approval before covering the system, and the owner’s signature on the application consents to inspections. The department warns that a permit and final approval do not guarantee trouble-free operation; the owner is responsible for servicing and maintaining the system, and a developer or contractor selling the property must tell the buyer and the department about the transfer. In Paris, the person who applied for the permit, owner or contractor, schedules inspections through City Hall at 217-465-7601.

Illinois building code in Edgar County

The county’s posted ordinances adopt no building code for unincorporated land; Paris enforces the codes listed on its own permit form. FEMA’s Community Status Book lists Edgar County’s unincorporated areas (community 170985) as participating in the National Flood Insurance Program, with flood maps effective January 19, 2011.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Edgar County permit FAQs

Do I need a county building permit to build a house in rural Edgar County?

The county lists no building department and its posted ordinances set no county building permit for houses; the county permits that apply are septic and well permits from the Public Health Department.

How much is a septic permit in Edgar County?

$125, which includes a $25 inspection fee; a well permit is also $125.

Can I install my own septic system?

Yes, if you own and live in the single-family house; otherwise a licensed contractor must do it.

Does Edgar County accept percolation tests?

No. A soil test must set the loading rate, and the soil report goes with the application.

Who issues building permits in Paris?

The City of Paris Code Enforcement Office at City Hall, 206 S. Central Avenue (217-465-7601), open weekday mornings.

How are commercial solar farms approved?

By a county special use permit under Ordinance 2026-43, after a township public meeting at least 60 days before filing, then a county building permit for the facility.

How do I know if my property is inside a town?

Search the parcel on the county GIS from the Property Records page or call the Office of Assessment at 217-466-7418.

Edgar County permit search and official resources

County records are requested on the county’s FOIA request form, which can be sent by email, mail or fax or delivered in person; say whether you want paper or electronic copies and whether the request is for a commercial purpose. The Public Health Department keeps its own FOIA page, and recorded ordinances and deeds are kept by the Clerk & Recorder.

Inspections are where schedules slip.

Get a free quote →

Simplify Edgar County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Edgar County sooner?

Let Alliance prepare, file, and track your Edgar County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Edgar County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.