Effingham County, Illinois Building Permit Guide

To get a building permit in Effingham County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Effingham County has no zoning and issues no building permits or certificates of occupancy for unincorporated land; its Highway Department handles road right-of-way work and subdivisions, and the county health department permits septic systems and wells.

Authority: No county building permit (Highway Department for roads and plats)Septic and wells: Effingham County Health DepartmentPhone: 217-342-6550
County building permit
Not requiredNo county zoning in unincorporated areas
Highway setback
90 ftFrom centerline, most county and state highways
Well permit
$100Payable to IDPH, via the health department
Plat review
$100 + $10/lotSubdivision Ordinance, 2009

Unincorporated Effingham County has no zoning, and the County Engineer’s published letter says building permits and certificates of occupancy are therefore not required there. What still applies on rural land is road-side: a 90-foot setback from the centerline of most county and state highways, permits for any work in county or township right-of-way, and the 2009 Subdivision Ordinance, all run by the Highway & Engineering Department (101 N. Fourth St., Suite 304, Effingham, 217-342-6550). The Effingham County Health Department permits septic systems and wells. Effingham, Teutopolis and other cities and villages govern building inside their limits, and some reach 1.5 miles beyond them.

What requires a permit in unincorporated Effingham County?

The county’s no-zoning letter, signed by the County Engineer, is the clearest statement of the rule: because zoning does not exist in Effingham County, building permits and certificate of occupancy permits are not required in its unincorporated areas. A house, shed or barn on rural land therefore goes up without a county building permit, but several approvals still sit around it.

Still needs approval

  • Any work in a county highway or township road right-of-way, including utility lines and driveway culverts
  • Land divisions that create a subdivision under the 2009 Subdivision Ordinance
  • A private sewage (septic) system, before it is installed
  • A new water well, before it is drilled
  • Commercial solar energy facilities and wind projects, through the county’s special use process
  • Floodway construction on larger streams, through the state

No county permit

  • Houses, garages, sheds and farm buildings outside any town’s reach
  • Additions, decks, pools and remodels on unincorporated parcels
  • Certificates of occupancy for new rural buildings

Limits remain. The county’s setback resolution keeps buildings back from the highway, and the County Engineer recommends staying at least 40 feet from the centerline of township roads even though no formal setback applies there. The letter also warns that land within one and a half miles of Effingham or Teutopolis may fall under those municipalities’ extraterritorial zoning, so an owner near either town should ask the town first. Height limits also apply around the Effingham County Memorial Airport, about a mile south of Effingham; the letter sends questions on those to the Illinois Division of Aeronautics.

What the county decides and what the state holds

The county board decides whether to zone or adopt a building code and has done neither; its rules are a subdivision ordinance, a setback resolution and solar and wind ordinances. The state holds the private sewage and well codes (run locally by the health department), plumbing and the statutory building minimums in the code section below.

Effingham County building department: who handles permitting

No county office issues building permits. The county offices a rural builder deals with are these:

Short on time to read all of this?

Get a free quote →
Effingham County offices for rural projects
OfficeRoleContact
Highway & Engineering DepartmentRight-of-way permits, culverts, highway setbacks, subdivision review101 N. Fourth St., Suite 304, Effingham, IL 62401; 217-342-6550
Effingham County Health DepartmentSeptic system and water well permits and inspections901 W. Virginia Ave., Effingham; 217-342-9237; Monday to Friday 8 a.m. to 4 p.m.
County Board officeOrdinances, solar and wind special use applications101 N. Fourth St., Suite 301; 217-342-4990
GIS DepartmentParcel map (ECOMS), flood map layerEffingham County Office Building; 217-342-8519

The County Engineer, Greg A. Koester, P.E., heads the Highway & Engineering Department, which maintains 148 miles of county highway; township road commissioners, listed in the county directory, look after township roads.

Cities and villages in Effingham County

The county has ten incorporated places, and building rules inside them are their own:

  • Effingham (12,406 people): the city’s Building and Zoning division at City Hall, 201 E. Jefferson Ave., issues building, electrical, plumbing and other permits; see our Effingham building permit guide. Its zoning reach beyond the city limits is noted in the county’s letter.
  • Altamont (2,186): the city’s Department of Zoning issues a combined certificate of zoning compliance and building/construction permit; the Municipal Building is at 202 N. Second St. (618-483-5212).
  • Teutopolis (1,721): the village runs its own permitting, zoning and floodplain programs through a Building Official (a post advertised in October 2026), and the county lists Teutopolis among the towns that enforce extraterritorial zoning.
  • Dieterich (882): the village keeps its own code book; Village Hall is at 103 W. Section St.
  • Watson (658), Beecher City (425), Edgewood (390), Mason (321), Montrose (209 in this county; the village also lies in Cumberland County) and Shumway (185): the county’s pages do not say whether these villages issue building permits, so ask the village hall before building.

Effingham County permit types

With no county building permit, the approvals on unincorporated land come from the highway, health and board offices.

Residential permits

  • Private sewage system: the health department regulates every system treating 1,500 gallons a day or less; a plan review application and fee go in before installation, and the permit is granted when the design meets the state private sewage code and licensing act.
  • Water well: an application and $100 fee, made payable to the Illinois Department of Public Health, go to the county health department before drilling.
  • Culvert for a driveway: the landowner asks the Highway Department, which approves the location, sizes the pipe (at least 12 inches by 30 feet), invoices the cost and installs it, or lets an approved contractor do so.
  • Work in the right-of-way: the county highway/utility permit (revised April 2020) covers county highways only; township roads use a separate township form.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial buildings on unincorporated land also need no county building permit, but they fall under the statewide minimums in the state note below, and their septic systems go through the same health department review. Large energy projects are the exception: a commercial solar energy facility needs a special use permit from the county board under the Commercial Solar Energy Facility Ordinance, which the board updated on September 21, 2026 by a 7-0 vote, and the wind ordinance was updated the same night. A public hearing on one solar application was held on October 15, 2026; its transcript is posted.

What comes before construction

  • Check which government has the parcel. Look it up on the ECOMS parcel map, and ask Effingham or Teutopolis if the site is within 1.5 miles of their limits.
  • Subdivision approval. Dividing land into lots under five acres usually needs a surveyed plat approved under the Subdivision Ordinance; the road and bridge committee acts as the subdivision committee outside municipal reach.
  • Septic and well approvals. Get them before the system or well goes in.
  • Road access. Arrange any culvert or right-of-way permit with the Highway Department or the township road commissioner.
  • Flood areas. Under the state’s Part 3700 rules, building in the floodway of a rural stream draining ten square miles or more needs an Illinois Department of Natural Resources permit first.

Effingham County permit costs and fees

There is no county building permit fee to budget for. The published county charges are these:

Effingham County fees for rural development
ItemFeeSource
Preliminary plat review$100 plus $10 per lotSubdivision Ordinance, Sec. 309, adopted September 21, 2009
Inspection and review of subdivision public improvements1% of the estimated cost, or $500, whichever is lessSubdivision Ordinance, Sec. 309
New water well$100, payable to the Illinois Department of Public HealthHealth department well page
Driveway culvertMaterial and installation cost, estimated and invoiced by the countyHighway Department culvert policy
Lengthening an existing culvertAll material and installation costs, invoiced before the workHighway Department culvert policy
Selling lots before plat approvalPetty offense, fine of at least $500 per lotSubdivision Ordinance, Sec. 704

Rather talk it over?

Call 1-855-478-4290 →

A ten-lot preliminary plat, for example, costs $100 plus 10 × $10, or $200, paid to the Highway Department before review starts; the ordinance says these fees do not include charges by other agencies. The septic plan review fee is set by the health department, whose page asks for an application fee with the plan but does not list the amount, so ask the department at 217-342-9237. Inside a city or village, that town’s own permit fees apply; in Altamont, approved projects in the Altamont/Effingham County Enterprise Zone (certified through December 31, 2035) can have the building permit fee waived.

Trade permits and who may pull them

The county issues no electrical, plumbing or mechanical permits on unincorporated land and publishes no county contractor license or registration. What it does control is who digs septic systems and wells:

  • Septic systems: a person who owns and occupies a single-family dwelling may receive a permit and do the work; anyone else must be a licensed private sewage disposal system installation contractor or work under one’s direct supervision.
  • Surface discharge: a new or replacement system whose effluent reaches waters of the United States needs coverage under NPDES general permit ILG62, in force since February 10, 2014; the owner is responsible for deciding whether that applies.
  • Plumbing and roofing: plumbers hold state licenses from the Illinois Department of Public Health and roofers state licenses from the Department of Financial and Professional Regulation, wherever the job is.

In Effingham and the other towns, local rules on electrical permits and contractor registration apply; the city of Effingham, for example, requires everyone working on a building, homeowners included, to register with it, and keeps a separate registration for electrical contractors.

Rather not deal with the Effingham County building department?

Get a free quote →

How to get permits for a rural Effingham County project

1. Confirm the parcel is unincorporated

Search the ECOMS tax parcel map by parcel number, owner or address, and check whether the site lies within 1.5 miles of Effingham or Teutopolis; if so, ask that town about its zoning first.

2. Plan the setback and access

Keep buildings 90 feet from the centerline of most county and state highways, and about 40 feet from township roads. Call the Highway Department at 217-342-6550 about a culvert or any right-of-way work.

3. Plat the land if you are dividing it

Have a licensed land surveyor prepare the plat and file four copies of the preliminary plat with the review fee; the ordinance gives the county 45 days to respond.

4. Get the septic permit

Submit the private sewage plan review application and fee to the health department at 901 W. Virginia Ave., and give at least 24 hours’ notice before installation.

5. Get the well permit

File the well application with the $100 fee payable to IDPH, and notify the department 24 hours before drilling.

6. Check flood and airport limits

Open the FEMA flood layer on the county GIS page, and for floodway work contact IDNR; near the airport, ask the Illinois Division of Aeronautics about height.

Review, corrections and what causes delay

A plat that misses the Subdivision Ordinance can be disapproved or approved with conditions, and preliminary approval lasts one year. The ordinance bars soil-absorption septic systems where high groundwater, flooding or poor soil would stop them working, and lots on private sewage need at least one acre of suitable land. Right-of-way work is restricted in spring, when many county highways carry weight limits from January 15 to April 15, and road crossings must be bored unless the Highway Department approves an open cut in writing.

Inspections in Effingham County

Because the county issues no building permits, it makes no building inspections and issues no certificates of occupancy on unincorporated land. The inspections that do happen are these:

  • Septic: the health department inspects new and existing private sewage systems; call at least 24 hours before installation starts.
  • Wells: staff inspect new well construction; notify the department 24 hours ahead. Since June 2025 the state laboratory tests private well water only in listed cases, such as the first test of a new well; routine testing goes to accredited commercial labs.
  • Culverts and right-of-way: the county installs most culverts itself, and work under a highway permit must meet its conditions on depth, boring and restoration.

Inside Effingham, Altamont, Teutopolis and the villages, inspections and occupancy approvals follow each town’s own rules.

Illinois building code in Effingham County

Effingham County has adopted no building code for its unincorporated areas, so the statutory minimums described below apply there, alongside the state private sewage and water well codes enforced by the health department. FEMA’s Community Status Book lists unincorporated Effingham County (community 170227) among the communities not in the National Flood Insurance Program, with county flood maps dated January 17, 2025; the city of Effingham is listed separately as participating.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Want this handled start to finish?

Get a free quote →

Effingham County permit FAQs

Do I need a building permit to build a house in rural Effingham County?

Not from the county: it has no zoning, and its letter says building permits and certificates of occupancy are not required in unincorporated areas. You still need septic and well permits from the health department and must respect highway setbacks.

How far back from the road must I build?

Generally 90 feet from the centerline of county and state highways, more near intersections and less along some state aid routes under the setback resolution; on township roads the county recommends at least 40 feet.

Does Effingham or Teutopolis control land outside its limits?

The county says both enforce extraterritorial zoning up to 1.5 miles beyond their limits, so ask the town if your site is that close.

What does a well permit cost?

$100, payable to the Illinois Department of Public Health and filed with the county health department before drilling.

Can I install my own septic system?

Yes, if you own and live in the single-family home it serves; otherwise a licensed installation contractor must do it.

How do I get a culvert for a new driveway?

Tell the Highway Department where you want it. Unless the County Engineer approves more, each parcel gets one culvert; the county sizes it, invoices you and installs it after payment.

Is unincorporated Effingham County in the flood insurance program?

FEMA lists it as not participating, although flood maps dated January 17, 2025 cover the county.

Effingham County permit records and official resources

Because there are no county building permits, there is no county building permit search. Plats, deeds and other real estate records are recorded and kept by the County Clerk & Recorder, who also keeps the county board minutes; septic and well records are held by the health department; and right-of-way permits are on file with the Highway Department. Parcel ownership, size and tax data can be searched on the ECOMS map. Ask the office that holds a record for a copy, or file a written request under the Illinois Freedom of Information Act with that office.

Inspections are where schedules slip.

Get a free quote →

Simplify Effingham County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Effingham County sooner?

Let Alliance prepare, file, and track your Effingham County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Effingham County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.