Inside Edwardsville, building permits come from the City’s Public Works Department, whose Building Inspection Division works from 200 East Park Street (618-692-7535, weekdays 8 a.m. to 4:30 p.m.). Building fees are charged by floor area, $30 for the first 500 square feet, and a single-family plan review typically takes 7 to 14 working days. Land outside the city limits is handled by Madison County Building & Zoning.
What requires a building permit in Edwardsville?
The city asks for a building permit for any new building and for remodeling of existing homes or commercial buildings, and singles out additions, moving walls, installing plumbing fixtures and upgrading electrical wiring or lighting. Its fee schedule shows how far the rule reaches into small jobs. Every shed needs a permit, even one under 100 square feet (no fee is charged below that size), every retaining wall needs a permit (also free), and siding has needed a permit since May 1, 2023, with windows and exterior doors folded into the building permit fee.
Permit needed
- New homes, commercial buildings and additions
- Remodels that move walls or add plumbing fixtures
- Electrical service, wiring and lighting upgrades
- Sheds of any size, detached garages, pergolas and covered patios
- Siding, windows and exterior doors
- Roofs, fences, pools and retaining walls
- Demolition, signs, irrigation and driveway curb cuts
No fee charged
- Sheds under 100 square feet (permit still required)
- Retaining walls (permit still required)
- Window, door and siding work already covered by a building permit fee
No work may start before the permit is issued and paid, including clearing, grading, bringing in dirt or digging footings; only erosion control and staking may go ahead. Building without a permit can bring a fine of up to $750 for each day the violation continues.
What Edwardsville decides and what the state holds
The City Council chose its own codes: on July 7, 2022 it approved the 2021 International Building, Residential, Mechanical, Property Maintenance and Fire Codes, in force from January 1, 2023, and the 2020 National Electrical Code with local amendments, effective July 7, 2022. Plumbing follows the Illinois State Plumbing Code and must be done by a plumber holding an Illinois license unless the owner-occupant exception the city cites applies. On energy, the building page cites the 2021 Illinois energy code for permits submitted after June 1, 2024, while the newer residential packet (February 26, 2026) asks for REScheck under the 2024 edition.
Edwardsville building department: who handles permitting
The Public Works Department runs permitting as a single counter: its Building Inspection Division takes the application, routes the plans to every city department with a stake in public safety, tracks their approvals and issues the permit card once all departments sign off and the fees are paid. The Department is led by Public Works Director Ryan Zwijack, P.E. Its Planning and Zoning Division handles the Zoning Ordinance, the Land Development Code, the Plan Commission and the Zoning Board of Appeals.
Short on time to read all of this?
Get a free quote →The Fire Department reviews plans and inspects the occupancy groups the city lists: assembly, business, educational, factory and industrial, hazardous, institutional, mercantile, storage, utility and miscellaneous buildings, and residential groups R-1, R-2 and R-3; its office is at 618-692-7540. Exterior work on a landmark or in the city historic districts (Leclaire, St. Louis Street and Downtown) also goes to the Historic Preservation Commission.
| Detail | Information |
|---|---|
| Office | Public Works Department, Building Inspection Division, 200 East Park Street, Edwardsville, IL 62025 |
| Phone | 618-692-7535; inspections also 618-692-7537 |
| publicworks@cityofedwardsville.com | |
| Hours | Monday to Friday, 8 a.m. to 4:30 p.m. |
| Fire plan review | Edwardsville Fire Department, 618-692-7540 |
| Historic review | Historic Preservation Commission, HPC@cityofedwardsville.com |
| Outside city limits | Madison County Building & Zoning (see the Madison County guide) |
Edwardsville permit types
Besides the packets handed out at 200 East Park Street, the city posts applications for residential and commercial building permits, demolition (with a historic-district version), fences and pools, retaining walls, parking lots, right-of-way excavation and signs, plus an online roof permit form.
Residential permits
- New homes and additions. The residential packet lists the plan review comment form, the application, the signed page 3 of the residential permit policy, a full site, drainage and erosion control plan of the whole lot, the truss package and specification sheet, a cross connection survey, window elevations, a REScheck report, Manual J, S and D load calculations where they apply, and four sets of plans at a quarter inch to the foot or digital plans.
- Design values. Plans must use a 40-inch frost depth, 1,500 psf soil bearing, seismic zone C, a 110 mph wind speed and a 20 psf ground snow load; panels need two spare breaker spaces and smoke and carbon monoxide alarms must be interconnected.
- Accessory buildings. A site plan is required; buildings sit at least 5 feet from side and rear lot lines and 10 feet from the house, cover no more than 30% of the required rear yard, stay under 15 feet tall and stay out of easements.
- Retaining walls. Walls 4 feet or taller from the bottom of the footing need plans sealed by an Illinois structural engineer or architect, not a professional engineer.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial projects use the commercial application and the same multi-department review, with the Fire Department charging its own review fees; a priority review costs a $250 application fee plus 150% of the calculated review fee.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning and subdivision. Variances, special uses and rezoning go through the Planning and Zoning Division to the Zoning Board of Appeals or Plan Commission ($700 each); plats, PUD plans and lot consolidations have their own checklists.
- Historic review. A Certificate of Appropriateness may be needed in the Leclaire, St. Louis Street and Downtown districts, sometimes even for basic maintenance.
- Site and erosion control. After applying for a new home, the applicant meets the building inspector on site to go over erosion control, easements, drainage, grading and the rock driveway; the pre-permit erosion control must be in place and approved before the permit is issued.
- Flood areas. Homes in potential flood hazard areas need an elevation certificate before construction and again after completion.
- Utilities and annexation. Water and sewer tap-on fees are paid with the permit, and in certain new subdivisions a $2,000 per-lot annexation fee is due when the building permit is paid.
Edwardsville permit costs and fees
Fees come from the city’s fee schedule; its building and trade pages are marked revised April 8, 2026, and its land development, tap-on and fire pages revised August 12, 2025. The schedule does not cite its own ordinance number. The building fee is set by square footage for both homes and commercial buildings, not by construction value.
| Item | Fee |
|---|---|
| Building permit, first 500 sq ft | $30 |
| Building permit, 500 to 4,000 sq ft | $0.07 for each additional sq ft |
| Building permit, 4,001 sq ft and up | $0.03 for each additional sq ft |
| Shed 10 x 10 or larger | $30 (under 100 sq ft: permit, no fee) |
| Electrical, house: service upgrade or replacement | $20 |
| Electrical, new house service 100 / 200 / 400 amp | $25 / $35 / $45 |
| Plumbing: upgrade, renovation or relocation / new house | $20 / $40 |
| Electrical, plumbing or mechanical, commercial | 1.25% of estimated cost |
| Fence / roof | $30 / $25 |
| Swimming pool | $100 plus $20 electrical |
| Demolition, principal / accessory building | $25 / $10 |
| Driveway curb cut or street excavation | $10 plus a $1,000 insurance bond ($10,000 for sewer work) |
| Extra re-inspection | $25 (first inspection and one re-inspection included) |
| Fire and life-safety plan review | $75 for the first $10,000 of cost plus $1 per $1,000 above |
| Expedited review | $250 plus 150% of the calculated review fee |
| Water / sewer tap-on, house in city (May 1, 2026 to April 30, 2027) | $3,900 (1 inch or less) / $4,340 |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the schedule: a 2,000-square-foot house addition pays $30 for the first 500 square feet plus 1,500 square feet at 7 cents, or $105, for a building fee of $135, before any trade permits. Outside the city, tap-on fees are $4,900 for water and $5,040 for a single-family sewer connection, and residential tap-on fees rise every May 1, by $100 for water and $210 for sewer.
Trade permits and who may pull them
Electrical, plumbing and mechanical work each carry their own fee and inspection but are filed with Public Works along with the building permit.
- Plumbing: the city requires an Illinois-licensed plumber unless the work is done by an owner who will live in the home for at least 6 months after the work is finished, as the city’s policy words the state exception. Plumbing inspections are booked by calling before 2 p.m. and have been carried out in the evenings.
- Electrical: work follows the 2020 National Electrical Code with the city’s amendments; house service fees run from $20 for an upgrade to $45 for a new 400-amp service, and larger services pay 1.25% of cost.
- Mechanical: commercial mechanical permits are charged at 1.25% of the estimated cost; the schedule lists no separate residential mechanical fee.
- Roofing: roof permits cost $25 and can be requested through the city’s online roof permit form.
- Fire systems: sprinkler, alarm, hood and clean-agent systems are reviewed by the Fire Department at $50 plus a per-$1,000 charge.
The city’s permit pages do not describe a separate local contractor license or registration; the residential application asks for the general contractor or project manager on the job. Illinois plumbing licensing is handled by the Illinois Department of Public Health.
Rather not deal with the building department?
Get a free quote →How to apply for an Edwardsville building permit
Make sure the lot is inside the city; parcels outside go to Madison County Building & Zoning.
Ask Planning and Zoning about setbacks and easements, and the Historic Preservation Commission if the property is a landmark or in a historic district.
Use the residential or commercial packet: application, site and erosion plan, truss and specification sheets, cross connection survey, energy report and four plan sets.
Bring the packet to 200 East Park Street; the division logs it once it is complete and sends the plans to each department.
For a new home, walk the lot with the building inspector and install the pre-permit erosion control.
Pay the fees, collect the approved plans and permit card, and post the card where it is visible from the street.
Review, corrections and what causes delay
A single-family plan review typically takes 7 to 14 working days, and the clock stops whenever the city asks for missing information until it is logged in at Public Works. Each department sends its corrections by email as it finishes, or by letter if no email was given, and the applicant must resubmit or answer them. A permit expires one year from issue; the 2026 packet says work must begin within 180 days, while the 2024 policy still says 90 days, and both void a permit when work is abandoned for 180 days. A new-home permit is not issued until the pre-permit erosion control has been approved and every reviewing department has signed off.
Inspections and certificates in Edwardsville
Call 618-692-7535 or 618-692-7537 before 9:30 a.m., Monday to Friday, for a same-day inspection, subject to availability; plumbing inspections are booked by calling before 2 p.m. The approved plans and the posted permit card must be on site, or the inspection fails and a $25 re-inspection fee is charged. The permit covers the first inspection and one re-inspection of each stage; further trips cost $25 each and must be paid at Public Works before the next visit, and Fire Department re-inspections beyond the first cost $50.
After the pre-permit site visit, a new house moves through footing (with property lines staked and easements marked), foundation steel before the pour, foundation final before backfill (drainage, waterproofing and rock cover), sill plate and anchor bolts, the 10-mil vapor barrier before the basement slab, rough-ins, and framing after the rough-ins pass. A certificate of occupancy is issued only after every required city inspection passes, nobody may move in without it, and proof of the occupancy permit is needed to move a new home’s water service from the builder’s name to the new occupant.
Want this handled start to finish?
Get a free quote →Illinois building code in Edwardsville
Edwardsville enforces the codes listed on its building page: the 2021 International Building, Residential, Fire, Mechanical and Property Maintenance Codes with local amendments, the International Existing Building and Fuel Gas Codes, the 2020 National Electrical Code, the NFPA 101 Life Safety Code, the Illinois Plumbing Code, the Illinois energy code and the Illinois Accessibility Code (the 2026 packet names the 2018 edition). FEMA’s Community Status Book lists the City of Edwardsville (community 170441) as participating in the National Flood Insurance Program, with a current flood map dated January 18, 1984, and no Community Rating System class.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Edwardsville building permit FAQs
How much is a building permit in Edwardsville?
$30 for the first 500 square feet, 7 cents for each additional square foot up to 4,000, and 3 cents a square foot beyond that, plus any electrical, plumbing and tap-on fees.
Do I need a permit for a shed?
Yes, for every shed. Sheds of 10 by 10 feet or larger pay $30; smaller ones still need a permit but pay nothing, and all must meet the 5-foot and 10-foot setbacks.
Do I need a permit for a fence or new siding?
Yes. A fence permit costs $30 and fences cannot go in an easement; siding has needed a permit since May 1, 2023, with the fee covered by the building permit.
How long does plan review take for a new house?
Typically 7 to 14 working days, longer if the city has to ask for missing documents, because the review clock stops until they arrive.
Can I get a same-day inspection?
Usually, if you call 618-692-7535 or 618-692-7537 before 9:30 a.m. on a weekday; plumbing inspections are booked by 2 p.m.
Can a homeowner do their own plumbing?
Only an owner who will live in the home for at least 6 months after the work, as the city words the state exception; otherwise an Illinois-licensed plumber is required.
Does Edwardsville handle permits outside the city limits?
No. Unincorporated land around Edwardsville is permitted by Madison County Building & Zoning.
Edwardsville permit records and official resources
Permit files, approved plans and occupancy records for city addresses are kept by Public Works at 200 East Park Street; call 618-692-7535 to ask whether a permit was issued or closed. Copies of permit records can be requested from the city under the Illinois Freedom of Information Act.
Inspections are where schedules slip.
Get a free quote →- Edwardsville building permit applications and adopted codes
- Edwardsville fee schedule (revised April 8, 2026)
- Residential building permit application packet (2026)
- Single-family residential building permit policy
- Building permit application process
- Accessory building permit information
- Public Works Department
- Historic Preservation Commission
- Fire and life-safety inspections
- FEMA Community Status Book, Illinois
- Illinois Department of Public Health plumbing
Simplify Edwardsville permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Edwardsville sooner?
Let Alliance prepare, file, and track your Edwardsville permits while your crew stays on the job.
More Illinois permitting guides
Madison County
Read guide →Glen Carbon
Read guide →Godfrey
Read guide →Effingham Building Permit Guide
Read guide →Effingham County Building Permit Guide
Read guide →Elgin Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Edwardsville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.