In the City of Burbank, permits come from the Building Department at City Hall, 6530 W. 79th Street (708-599-5500, option 2), where Joe Hession serves as Building Director, Building Commissioner and Zoning Administrator. The department posts fillable application forms for each kind of work, from roofs and fences to plumbing and new houses, and every contractor must be licensed with the city. Replacing a gas water heater? Burbank asks you to call for a safety inspection, which it performs at no charge.
What requires a building permit in Burbank?
Burbank requires a permit for all new construction. On existing buildings, a permit is needed whenever the work touches structure, light and ventilation, exits, room sizes, fire safety or sanitary facilities, or could change a building’s height, area, capacity, use or occupancy. The Building Department gives these examples:
Building work
- Structural changes, room additions, dormers and bay windows
- Garages, sheds and garage breezeways
- Demolition of any structure
- Roof replacement, including recoating or recovering
- Building, repairing, enclosing or heating porches
- Siding, masonry, chimneys, gutters and window or skylight replacement
- Driveways, fences and swimming pools
- Raising, underpinning or moving a building, and fire escapes
Systems work
- Installing, replacing or extending warm-air furnaces
- Air conditioning for homes, apartments and commercial buildings
- Boilers and mechanical supply or exhaust ventilation
- Any electrical equipment installed or altered
- Any plumbing built or altered
- Any type of remodeling
The city’s permit also confirms the work meets zoning, health and fire-safety standards under the City of Burbank Building Code. If a job is not on the list, the department asks you to call 708-599-5500, option 2, before starting.
What Burbank decides and what the state holds
Burbank chooses its construction codes by City Council ordinance; the 2026 adoptions are listed in the code section below. Its ordinances are published as the Municipal Code in the Municode library, and its permit forms add local construction rules, such as a two-layer limit on shingles and a ban on front-facing furnace vents. Its electrical permits are issued under the city’s Electrical Commission and Bureau of Electrical Inspection. Plumbers carry an Illinois plumbing license or a City of Chicago license, roofers a state roofing license, and the statewide plumbing, energy and accessibility codes still apply.
Burbank building department: who handles permitting
The Building Department issues every building and trade permit inside the city. Its head, the Building Commissioner, reviews and issues permits, enforces the building and property maintenance codes, and, as Zoning Administrator, reviews requests for variances, special uses, subdivisions and rezonings and prepares recommendations to the Planning and Zoning Commission. The city’s Code Enforcement Division handles complaints such as dumping, tall grass and junk vehicles, which can also be reported to the Police Department at 708-924-7300. Unincorporated Cook County land is permitted by the county’s Department of Building and Zoning rather than the city.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Department, City Hall, 6530 W. 79th Street, Burbank, IL 60459 |
| Phone / fax | 708-599-5500, option 2 / 708-599-9981 |
| Inspections | 708-599-5500, ext. 241 (fence and pool forms) |
| Hours | Monday to Friday, 8:30 a.m. to 5 p.m. |
| Building Commissioner | Joe Hession, Building Director, Building Commissioner and Zoning Administrator |
| Code complaints | Online form, or the Police Department at 708-924-7300 |
Burbank permit types
Burbank posts a separate fillable form for each permit: new construction and demolition, miscellaneous building work, driveways, fences, above-ground swimming pools, heating and air conditioning, electrical, plumbing, signs and temporary signs, plus the contractor registration form. Each form carries the city’s own construction rules, so read it before ordering materials.
Residential permits
- Roofing, windows, gutters, siding and flat work use the miscellaneous building permit. No more than two layers of shingles are allowed, staples are banned on roofs and siding, ice and water shield must run 24 inches past the building line, siding needs house wrap, and sidewalks or flat work need a survey.
- Sheds (code section 4-90) need a survey, a concrete base at least 4 inches thick and elevation drawings; they may be no larger than 10 feet wide, 12 feet deep and 11 feet tall, with walls no higher than 8 feet, and may not sit in an easement.
- Fences face the finished side toward the neighbor, keep all posts and concrete on the owner’s land, set posts in 36-inch holes and are not allowed between houses less than 8 feet apart. Call ext. 241 for an inspection before the posts are set, with the survey on site.
- Above-ground pools need a ground-fault circuit interrupter, a plat of survey on site and 10 feet of horizontal clearance from overhead lines.
- Driveways match the garage width at the property line, between 12 and 24 feet (18 feet allowed on corner lots where the garage faces the side street), and require a plat of survey.
- Rentals. Under the Crime Free Rental Housing Program, run since 2024, every residential rental unit, including houses, condominiums and townhomes, needs an annual license, and the landlord attends a training seminar and adds the program’s lease addendum. On September 22, 2026 the mayor said the city’s short-term rental ban stays.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
New commercial buildings, additions and demolitions use the Application for Building Permit, which records the lot, floor area, height, setbacks and parking area along with every contractor from excavator to roofer. Rooftop units and commercial heating and cooling systems need drawings and specifications. A permanent sign needs its own application with two sets of plans showing the fastenings, stress calculations where required, the landowner’s written consent, an electrical permit for lit signs, and a $50,000 bond with a 30-day notice clause or acceptable insurance under section 6-285. Portable temporary signs must stand on the business’s own property, may not exceed 100 square feet and must come down within 15 days, or the city removes them at the owner’s cost. No building may be occupied until it passes a final inspection and receives an occupancy certificate.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. The Zoning Administrator reviews variance, special use, subdivision and rezoning requests and sends recommendations to the Planning and Zoning Commission.
- Survey. Sheds, flat work, fences, pools and driveways all need a plat of survey, and the new-construction form asks for the proposed foundation grade relative to the curb or street crown.
- Sidewalk. The building permit is issued on condition that the owner lays a sidewalk where none exists and relays one in bad repair.
- Stormwater. Burbank is not on MWRD’s list of authorized municipalities, so projects that trigger the Watershed Management Ordinance, such as development disturbing more than half an acre, need a district permit. The city’s own stormwater program adds that a contractor disturbing an acre or more needs Illinois EPA general permit (ILR10) coverage, with the Notice of Intent filed at least 30 days before any earth is moved and a stormwater pollution prevention plan submitted to the city for approval; landscapers who pile black dirt, sand, gravel or mulch on a city street can be warned or ticketed.
- Parkway trees. Only Public Works staff or the homeowner may trim a parkway tree, and the code bans destroying one; Public Works is at 5700 W. 75th Place (708-924-7390).
Burbank permit costs and fees
The Building Department page lists no permit fee amounts, and each city form has a fee line that the department fills in when it approves the application. The forms show what the charges are made of:
Rather talk it over?
Call 1-855-478-4290 →| Permit | Fee items on the form |
|---|---|
| New construction, alteration or demolition | Street cleaning fee, building construction fee, building inspection fee, certificate of occupancy, construction bond fee and construction bond |
| Miscellaneous building permit | Asks for the cost of construction; the permit fee is entered by the department |
| Plumbing | A charge for the first five fixtures plus a charge for each additional fixture |
| Residential driveway | Minimum fee of $15 |
| Permanent sign | Structural fee, electrical fee and reinspection fee; $50,000 bond or insurance |
| Temporary portable sign | $200 cash bond (section 4-360) |
| Gas water heater replacement inspection | No charge |
| Contractor license | Regulatory fee or registration recorded on the form the City Clerk signs |
| Real estate transfer tax (City Clerk) | $5 per $1,000 of the full actual consideration, $100 minimum |
The building permit rates themselves sit in the Municipal Code, not on the forms, and no 2026 council minutes show a change to them; the council did amend the Chapter 8 license fee schedule on June 16, 2026 (Ordinance No. 12-6-26), so ask the City Clerk for current license amounts. Transfer stamps need proof that the scavenger and water and sewer bills are paid.
Because most amounts are not printed on the forms, ask the Building Department for the figure before you file, and budget for the construction bond on new buildings and demolitions. The new-construction form asks for the estimated cost exclusive of land, and copies of the permit go to the township and county assessors.
Trade permits and who may pull them
All contractors must be licensed with the City of Burbank to do any type of work, and most forms ask for the expiry date of the contractor’s Burbank license. The license is applied for on the city’s registration form and approved by the City Clerk and the Building Commissioner.
- Electrical: the electrical permit is issued through the city’s Bureau of Electrical Inspection under its Electrical Commission and must be signed by the supervising electrician.
- Plumbing: the plumber lists an Illinois plumbing license (055 and 058 numbers) or a City of Chicago license; plumbing inspections and tests need 48 hours’ notice.
- Heating and cooling: all gas appliances must be vented, sidewall vents go to the rear only with no vents or flues on the front of the house, compressors sit behind the house, and wood stoves and fireplaces need chimney caps.
- Roofing: the miscellaneous permit records the roofer’s state license number and its expiry.
The miscellaneous permit form is signed by the “homeowner/contractor”; ask the department how it handles an owner doing the work without a licensed contractor.
Rather not deal with the building department?
Get a free quote →How to apply for a Burbank building permit
Phone 708-599-5500, option 2, to confirm what permit the job needs.
Make sure each contractor holds a current Burbank license.
Fill in the fillable PDF for the work type from the Building Department page.
A plat of survey for outside work, elevations for sheds, drawings for commercial HVAC.
Bring the form to the Building Department at 6530 W. 79th Street during office hours.
Before work begins, post the permit card in front of the building where it can be seen from the street.
Review, corrections and what causes delay
The Building Commissioner reviews and approves each application, and zoning questions go through the same office. An expired Burbank contractor license, a missing survey or a design that breaks one of the form’s rules, such as a third layer of shingles or a shed over the size limit, will send the application back. Variances and special uses need a Planning and Zoning Commission recommendation, so allow extra time for them.
Inspections in Burbank
Call the Building Department to book inspections; the fence and pool forms give extension 241, and the driveway form asks for 24 hours’ notice before construction starts. Plumbing inspections and tests need 48 hours’ notice. Fences are inspected before the posts are set, and the survey must be on site for fence and pool inspections.
New buildings and additions may not be occupied until the final inspection is passed and an occupancy certificate is issued, which the new-construction form lists as its own fee item. When you replace a gas water heater, the department asks for a call so an inspector can check the venting, safety valve and connections, a service it provides free of charge.
Illinois building code in Burbank
On April 14, 2026 the City Council passed Ordinance No. 10-4-26, adopting the 2024 International Building, Residential, Mechanical and Fire codes, the Illinois Plumbing Code, the Chicago Electrical Code and the Illinois Energy Conservation Code. Ordinance No. 7-3-26 (March 24, 2026) brought in the 2024 International Property Maintenance Code under section 4-293, and Ordinance 13-6-26 (June 16, 2026) amended section 4-92 on gazebos and pergolas; ask the department for that rule before building one. FEMA’s Community Status Book lists the City of Burbank (community 170069) as participating in the National Flood Insurance Program, with its current flood map showing no special flood hazard area in the city.
Want this handled start to finish?
Get a free quote →Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Burbank permit search and official resources
Past permits and inspection records are public records. Request them on the city’s Freedom of Information Act form, delivered by email, mail, fax (708-599-8088) or in person at City Hall; the first 50 pages are free, then 15 cents per black-and-white page, and certified copies are $1 per record.
- Burbank Building Department
- Application for building permit (new construction or demolition)
- Miscellaneous building permit
- Fence permit application
- Driveway permit and detail
- Above-ground pool permit
- Heating, venting and air conditioning permit
- Plumbing permit application
- Electrical permit application
- Contractor registration form
- Real estate transfer tax declaration
- Crime Free Rental Housing Program
- Stormwater management program (MS4)
- Public Works and parkway trees
- Council minutes, April 14, 2026 (code adoption)
- City Council agendas and minutes
- City Clerk’s Office
- Freedom of Information request form
- FEMA Community Status Book, Illinois
Inspections are where schedules slip.
Get a free quote →Burbank building permit FAQs
Where do I get a building permit in Burbank?
At the Building Department in City Hall, 6530 W. 79th Street; call 708-599-5500, option 2.
Do I need a permit to replace my roof?
Yes, including recoating or recovering; the miscellaneous permit allows no more than two layers of shingles and no staples.
How big can a shed be?
Up to 10 feet wide, 12 feet deep and 11 feet tall with 8-foot walls, on a concrete base at least 4 inches thick and outside any easement.
Can I put up a fence between houses?
Not where the houses are less than 8 feet apart; elsewhere the fence must sit on your property with the finished side facing the neighbor.
Does my contractor need a Burbank license?
Yes. All contractors must be licensed with the city for any type of work.
How wide can my driveway be?
As wide as the garage at the property line, but never under 12 or over 24 feet; the permit fee starts at $15.
Which building codes does Burbank use?
The 2024 International Building, Residential, Mechanical and Fire codes, the Chicago Electrical Code and the Illinois plumbing and energy codes, adopted by Ordinance No. 10-4-26 on April 14, 2026.
Is my Burbank property in a flood zone?
FEMA’s listing for the City of Burbank shows no special flood hazard area on its current map.
Simplify Burbank permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Burbank sooner?
Let Alliance prepare, file, and track your Burbank permits while your crew stays on the job.
More Illinois permitting guides
Cook County
Read guide →Calumet City
Read guide →Chicago
Read guide →Bureau County Building Permit Guide
Read guide →Burr Ridge Building Permit Guide
Read guide →Canton Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Burbank permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.