In the Village of Beach Park, permits come from the Community Development Department at Village Hall, 11270 W. Wadsworth Road (847-746-1770), led by Community Development Director Nimrod Warda. Homeowners and contractors apply and book inspections in the village’s BS&A online portal, or use the printable application, and each review can take 5 to 10 business days. One-story sheds and playhouses up to 100 square feet need no permit, though the village offers a free review so they still meet anchoring and zoning rules.
What requires a building permit in Beach Park?
The Community Development Department handles building permits for new buildings, additions and alterations, with the printable application listing roofing, plumbing, HVAC, electrical and solar contractors as well as the general contractor. The village publishes separate guidance for fences, swimming pools and hot tubs, mailbox placement and watershed development. Some projects go through more than one review.
Permit needed
- New buildings, additions and alterations
- Roofing, plumbing, HVAC, electrical and solar work listed on the application
- Fences other than decorative or temporary ones
- Pools, spas and hot tubs that hold 24 inches of water or more
- A separate permit for a deck built with a pool
- Development covered by the Watershed Development Ordinance
No permit
- One-story detached sheds, playhouses and similar structures up to 100 square feet
- Decorative fences up to 30 inches tall and 16 feet long (not chain link, mesh or reed)
- Temporary fencing such as construction or silt fence
An exempt shed still has to follow the village’s anchoring and zoning rules on how many structures a lot may have and where they go. The village recommends a 4-inch concrete slab on 4 inches of compacted gravel, or concrete piers at least 10 inches wide and 42 inches deep; gravel or deck-block bases still need ground anchors at least 24 inches deep.
What Beach Park decides and what the state holds
Beach Park adopts its own ordinances in its Village Code, published on American Legal and updated within about 48 hours of each Village Board meeting, with newer ordinances listed as pending codification. Its zoning ordinance is amended through October 17, 2022, and the Village Board adopted its Watershed Development Ordinance on March 25, 2021. The village’s pool guide applies the 2017 National Electrical Code to pool wiring. On a lot with a septic field, any change to the property needs a Property Alteration from the Lake County Health Department.
Short on time to read all of this?
Get a free quote →Beach Park building department: who handles permitting
The Community Development Department covers building permits, planning and zoning, and code enforcement, with code enforcement officers who follow up complaints, issue warning tickets and tickets and track cases to compliance. Stormwater management is shared by the Department of Public Works and the village engineer, HMG Engineers, Inc., under the programs of the Lake County Stormwater Management Commission and the Illinois Environmental Protection Agency. Land outside the village limits is permitted by Lake County, not Beach Park.
| Detail | Information |
|---|---|
| Office | Community Development Department, Village Hall, 11270 W. Wadsworth Road, Beach Park, IL 60099-3358 |
| Phone and fax | 847-746-1770; fax 847-746-1797 |
| Hours | Monday to Friday, 8:00 a.m. to 4:30 p.m. |
| Department head | Nimrod Warda, Community Development Director |
| Portal | BS&A Online (applications and inspection requests) |
| Public Works | 40185 Glendale Avenue; illicit discharge reports 847-246-6062 |
Beach Park permit types
Homeowners and business owners can apply online through BS&A; if you are doing the work yourself, enter “self” as the contractor. Contractors set up a contractor login, and one profile can be used for several permits. The printable application asks for the site address, the cost of construction, a description of the work (with the PIN for a new building), the owner or permittee, the occupant if different, and each contractor. Call the village before filing to confirm the materials your project needs.
Residential permits
- Pools, spas and hot tubs. A plat of survey showing the pool and barriers, the pool’s dimensions and construction drawings, barrier details and electrical details. Pools go in the rear yard at least 6 feet from every property line, or 30 feet from the abutting sides of a corner lot, and the plat shows total lot coverage and every overhead and buried utility. The pump’s locking receptacle sits 5 to 10 feet from the pool wall on a GFCI, a general-purpose GFCI outlet sits 10 to 20 feet away, metal parts are bonded with solid No. 8 copper, and no overhead line may be within 10 feet. A barrier of at least 48 inches with self-closing, self-latching gates is required, and a ladder that is the only way in must be removable or lockable.
- Fences. Open fences up to 4 feet in a front yard, open or solid fences up to 6 feet along side lot lines behind the front yard, and up to 6 feet in a street side yard only with a 10-foot setback. Materials are wood, wrought iron or look-alike aluminum, chain link or coated chain link, or brick and stone (not concrete block); privacy slats in chain link are not allowed, the finished side faces out, and a new fence may not run within 42 inches of a neighbor’s parallel fence. A fence may stand on a village or utility easement if the owner acknowledges in writing that it can be removed for work there and replaced at the owner’s cost. Fences, walls and plantings over 4 feet are banned in vision triangles (30 feet at street intersections and at commercial or multi-family driveways, 10 feet at a house driveway), driveway gates sit at least 20 feet from the right-of-way line, and the zoning administrator can allow up to 8 feet along a railroad or beside a business or industrial district.
- Sheds over 100 square feet and other accessory buildings go through the regular permit.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial work uses the same BS&A application or printable form, listing every trade contractor. In the CS and LI districts, barbed wire is allowed on fences only 7 feet or more above the ground and subject to site plan approval; elsewhere it takes a variation from the Zoning Board of Appeals after a public hearing. The village also runs a rental housing inspection and certification program and a vacant property and foreclosure registration, both listed with its permit forms.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning relief. Variations, conditional uses, map and text amendments, subdivisions and appeals of a Zoning Administrator decision go to the combined Plan Commission / Zoning Board of Appeals, which meets on the first Thursday of the month. File at least 30 calendar days before the hearing with the owner’s authorization, a narrative, a site plan, a plat of survey and the application fee; village staff mail notices to owners within 250 feet, publish the hearing and post a sign, and the board’s findings go to the Village Board.
- Watershed development. Projects under the Watershed Development Ordinance file the village’s Watershed Development Permit Application.
- Septic lots. A Property Alteration from the Lake County Health Department before changing a lot with a septic field.
Beach Park permit costs and fees
Beach Park’s permit pages and handouts do not print building permit fee amounts, so the department confirms the charge for each permit. The fee rules the village does publish are these:
Rather talk it over?
Call 1-855-478-4290 →- Free shed review. Sheds, playhouses and similar one-story structures up to 100 square feet need no permit, and the village reviews them for anchoring and zoning at no charge if you ask.
- Zoning applications. Variation and other zoning applications are charged “per the Village fee schedule”.
- Professional fees. Under Section 3.12.010 of the Village Code, an applicant signs a Professional Fee Agreement and pays the engineering, planning, legal and other professional costs the village incurs on the application. The village may ask for an escrow deposit, top it up when the balance runs low, and refund what is left at the end of the project.
- Records. Copies made under a FOIA request that must be sent out for reproduction are charged at cost.
Because no rate table is posted, ask the Community Development Department at 847-746-1770 for the fee on your project before you file, and budget separately for any professional review costs on zoning or subdivision cases.
Trade permits and who may pull them
The village requires detailed information on every contractor working under a building permit, and it warns that some trades must show licenses and proof of insurance before they start. The application has lines for the general, roofing, plumbing, HVAC, electrical and solar contractors.
- Doing it yourself: owners may apply with “self” as the contractor, but if the scope of work requires a licensed contractor, the permit is not issued until one is named.
- Plumbers and roofers: plumbers hold state licenses from the Department of Public Health and roofing contractors state licenses from the Department of Financial and Professional Regulation, so name them on the application.
- Contractors online: contractors create a BS&A contractor profile to apply and schedule inspections.
Before signing a home repair contract over $1,000, the contractor must give you the Illinois Attorney General’s consumer rights pamphlet, which the village links from its permit page along with its own tips on choosing a contractor.
How to apply for a Beach Park building permit
Make sure the property is inside Beach Park; unincorporated land goes to Lake County.
Use the current zoning map and the fence and pool rules; file any variation at least 30 days before a PC/ZBA meeting.
Phone 847-746-1770 to confirm the drawings and documents your project needs.
Submit online with your contractors (or “self”), or file the printable application at Village Hall.
Each review can take 5 to 10 business days, and some projects need several.
Once the permit is issued, request inspections through the BS&A portal.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
Because the 5-to-10-day clock applies to each review, every round of corrections adds time, so plan for it. A permit that needs a licensed contractor stalls until one is named, pool applications need the barrier and electrical details on the plat, and a lot with a septic field waits on the county health department’s property alteration approval.
Inspections and certificates in Beach Park
Inspections are requested online through the village’s BS&A portal, from the homeowner page or the contractor login. Pool work is checked against the guide’s electrical rules: no underground wiring under the pool or within 5 feet of it, circuits buried at least 6 inches in metal raceway or 18 inches in non-metallic raceway, no switches within 5 feet, and listed underwater lighting. Where the house forms part of the pool barrier, the door needs a self-closing gate, a safety cover on the pool or an alarm. Pool decks take their own permit and must be slip resistant, with rounded or tapered edges.
Code enforcement officers also visit properties after complaints about blight, hazardous conditions, housing code and building code violations; officers may issue a warning ticket or a ticket with a fine, and a warning letter can set an exact deadline to comply.
Illinois building code in Beach Park
Beach Park enforces the building codes adopted in its Village Code. FEMA’s Community Status Book lists the Village of Beach Park (community 171022) as participating in the National Flood Insurance Program, with a current flood map dated October 5, 2023; the village is not in the Community Rating System.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Beach Park building permit FAQs
Do I need a permit for a shed in Beach Park?
Not for a one-story shed or playhouse of 100 square feet or less, but it must still meet anchoring and zoning rules, and the village will review it free.
Want this handled start to finish?
Get a free quote →How long does a permit take?
5 to 10 business days for each review; projects that need more than one review take longer.
Can I pull a permit for my own work?
Yes. Enter “self” as the contractor in the online application; if the work requires a licensed contractor, the permit waits until one is named.
How tall can my fence be?
Up to 4 feet (open style) in a front yard and up to 6 feet along side lot lines behind the front yard.
Where can a pool go?
In the rear yard, at least 6 feet from every lot line (30 feet on the abutting sides of a corner parcel), behind a barrier at least 48 inches high.
Does a small garden fence need a permit?
Not if it is decorative: no more than 30 inches tall and 16 feet long, not chain link, mesh or reed, and not enclosing an area.
When does the zoning board meet?
The Plan Commission / Zoning Board of Appeals meets on the first Thursday of the month; file at least 30 days ahead.
Beach Park permit search and official resources
Permit holders follow their applications and inspections in BS&A Online. For other records, send a Freedom of Information Act request to the village’s FOIA Officer in the Administration Department: in person, by mail, by fax to 847-746-1797, or by e-mail with the full request written in the body of the message, since the village need not open attachments or links. The village’s suggested FOIA request form is on the same page.
Inspections are where schedules slip.
Get a free quote →- Building permits and inspections
- Printable building permit application
- Building Department helpful hints
- Construction forms, guides and handouts
- Fence regulations
- Swimming pool and hot tub permit guide
- Planning, zoning and subdivision applications
- Variation application and PC/ZBA procedure
- Professional fee agreement
- Codes and ordinances
- Community Development Department
- Stormwater management
- Contact the village
- Make a FOIA request
- FEMA Community Status Book, Illinois
Simplify Beach Park permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Beach Park sooner?
Let Alliance prepare, file, and track your Beach Park permits while your crew stays on the job.
More Illinois permitting guides
Lake County
Read guide →Buffalo Grove
Read guide →Deerfield
Read guide →Bellwood Building Permit Guide
Read guide →Belvidere Building Permit Guide
Read guide →Bensenville Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Beach Park permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.