Bensenville, Illinois Building Permit Guide

To get a building permit in Bensenville, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Bensenville’s Community & Economic Development Department at Village Hall, 12 S. Center Street, issues building permits and books inspections inside the village; every permit carries a refundable escrow.

Authority: Community & Economic DevelopmentFiling: Village Hall or permits@bensenville.il.usPhone: 630-350-3413
Authority
Community & Economic Development12 S. Center Street
Same-day permits
Roofing, siding, guttersAlso fascia and emergencies
House addition
$200 + $330 reviewUnder 500 sq ft; $140 escrow
Inspections
24 hours’ notice630-350-3413

Inside Bensenville, building permits come from the Community & Economic Development Department (CED), led by Director Walter Magdziarz, at Village Hall, 12 S. Center Street (630-350-3413; Monday to Friday, 8 a.m. to 5 p.m.). The Village Plan Reviewer checks each application against the village’s 2021 codes and zoning. Roofing, siding, gutters and fascia can be permitted the same day, larger projects take about 10 to 12 days, and every permit pays an application fee, a plan review fee where required, inspection fees and a refundable escrow.

What requires a building permit in Bensenville?

The village publishes separate lists for homes and for other buildings. Window replacement is the one listed item that needs no permit, but the owner must give CED the energy efficiency rating of the new windows so the village can confirm they meet the Illinois energy code.

Residential

  • New construction, additions and remodels
  • Driveways, patios and decks
  • Water heater, furnace and air conditioner replacement
  • Sheds and detached garages
  • Roofs, gutters and siding
  • Sanitary sewer replacement
  • Demolition and chicken coops

Non-residential

  • New construction, additions and remodels
  • Parking lot and curb replacement
  • All plumbing, mechanical and electrical work
  • Accessory structures and demolition
  • Fire sprinkler installation or changes
  • Signs and warehouse racking

Pre-assembled offices and office furniture, low-voltage and voice and data wiring, burglar alarms and electric vehicle chargers also have their own submittal lists or applications.

What Bensenville decides and what the state holds

The village reviews plans against its own adopted codes: the 2021 International Building, Residential, Existing Building, Fuel Gas, Mechanical, Swimming Pool and Spa, Property Maintenance and Fire codes, 2021 NFPA standards and the 2023 National Electrical Code, with local amendments and the fee rules in the Village Code. The state’s 2014 Illinois Plumbing Code and the current Illinois Energy Conservation Code also apply, and every plan set must state the code year it was drawn to or it is denied.

Bensenville building department: who handles permitting

CED handles building permits and inspections, zoning and subdivision questions, sign permits, real estate transfer inspections, rental registration and annual inspections of rental and non-residential property. The Village Plan Reviewer checks applications, and CED inspectors inspect the work. Bensenville lies in both DuPage and Cook counties; land outside the village is permitted by the county: DuPage County Building and Zoning (630-407-6700) or the Cook County Department of Building and Zoning (312-603-0500), each for unincorporated areas only.

Short on time to read all of this?

Get a free quote →
Bensenville permit contacts
DetailInformation
OfficeCommunity & Economic Development, Village Hall, 12 S. Center Street, Bensenville, IL 60106
Phone and fax630-350-3413; fax 630-350-3449
HoursMonday to Friday, 8 a.m. to 5 p.m.
Electronic submissionspermits@bensenville.il.us
Department headWalter Magdziarz, Director of Community & Economic Development
Village Hall main line630-766-8200

Bensenville permit types

All work uses one Permit Application, marked residential, multi-residential or non-residential, with the estimated cost, the contractor and the signatures of both the applicant and the property owner. Additional licensed contractors attach their license certificates and bonds on page two. Every application also needs a signed proposal between owner and contractor, a current plat of survey and the escrow payment. Applications can be emailed to permits@bensenville.il.us or brought to Village Hall.

Residential permits

  • Fences, decks, sheds, porches, patios and driveways: two copies of a current plat of survey showing the work, with drawings, dimensions and materials. Sheds need a concrete foundation of at least 3.5 inches of concrete on 4 inches of stone, vinyl fences need the maker’s installation instructions, and brick paver walks or drives need a notarized village covenant.
  • Garages: plans with foundation, framing, roofing and electrical details and the driveway.
  • Additions and new homes: electronic copies of signed and sealed architectural plans with mechanical, electrical and plumbing drawings, a civil engineering grading and utility plan and an energy code checklist (REScheck); after approval, two hard copies (three for a new house) before pickup.
  • Demolition: a $100 application fee, a $2,000 refundable right-of-way bond, utility disconnection letters, proof of insurance and, except on single- and two-unit lots, a tree survey; all accessory structures must also come down and the site be graded and seeded.

Commercial permits

Multi-family and non-residential alterations, additions and new buildings need signed and sealed architectural drawings with mechanical, electrical and plumbing sheets and a COMcheck or REScheck, and some projects are flagged for a pre-construction meeting. The general submission sheet lists what an interior alteration set includes: a cover sheet and index, floor plans with keynotes and legends, elevations and details, a reflected ceiling plan, HVAC layouts and schedules, electrical plans with a riser diagram and lighting layout, and plumbing plans with water and sanitary risers. Warehouse racking needs a floor plan with rack heights and aisle widths, the manufacturer’s instructions, safety data sheets and the commodity stored; signs need dimensioned drawings, a site plan and a licensed, bonded electrician.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning relief. Zoning changes, special use permits and land use plans go to the Community Development Commission, an advisory body to the Village Board that meets in the board room at 12 S. Center Street; the CDC public hearing packet is on the forms page. A zoning verification letter can be requested on the village form.
  • Property lookup. The Bensenville Community Portal shows a parcel’s zoning, village services and school district.
  • Overhead sewers. The village’s Overhead Sewer Program reimburses homeowners in incorporated Bensenville 75% of the cost of an overhead sewer, up to $7,500, or of a backflow prevention device, up to $750. The work needs village permits and inspections, and the village must approve it before work starts (questions: 630-350-3411).
  • Solar. Bensenville holds a SolSmart Silver designation; it streamlined solar permitting and plan review, updated its Solar Energy Code and posts Solar Permitting Guidelines and a checklist.
  • Engineering. Site development is reviewed and inspected under the village’s current engineering contract, with a $1,250 escrow and $400 per lot application fee.

Bensenville permit costs and fees

The Permit Fee Schedule, marked “Approved – Ordinance #17”, sets four charges for each permit: a refundable escrow, an application fee, a plan review fee and a fee for each inspection. The plan review fee covers all plan submittals with no extra charge for resubmittals.

Bensenville single-family permit fees (Permit Fee Schedule)
PermitEscrow (refundable)ApplicationPlan reviewEach inspection
Over the counter$70$30None$35
Accessory or alteration$105$50$27$35
Addition$140$200$330 under 500 sq ft; $420 over$35
New construction$350$500$525$35

Rather talk it over?

Call 1-855-478-4290 →

Multi-family permits pay $45 per inspection with application fees of $30 to $750; non-residential permits pay $45 per inspection, $30 to $1,000 to apply and escrows of $90 to $900. Commercial and multi-family plan review follows Table 1 by floor area, from $455 for a base building review of up to 2,500 square feet ($550 with two added disciplines, $755 with three) to $980 above 10,000 square feet plus $20 for each further 1,000 square feet; an alteration review is $400. Stop work orders cost $100 to $750, and permit fees double for work started without a permit. Re-inspections and each failed inspection are charged against the escrow, and a second escrow is needed if it runs out. The office fee box on the application form prints inspection fees as $45 or $80, so confirm the count and rate when you pay.

Worked example from the schedule: a 400-square-foot addition to a house pays a $200 application fee and a $330 plan review fee, $530 in all, plus $35 for each required inspection and a $140 escrow that is refunded after the final inspection, less any failed-inspection charges.

Trade permits and who may pull them

Electrical, plumbing and mechanical work is permitted through the same application and fee schedule. Electricians must hold a license from an Illinois municipality and post an original $10,000 surety bond for the village; the same applies to electricians on burglar alarm, voice and data and low-voltage jobs. Plumbers send a copy of their plumbing license and a letter of intent, and roofers must be licensed by the State of Illinois. A homeowner may do the electrical work on a single-family house that is their primary residence without the electrician license and bond. Contractors and their license certificates and bonds are listed on page two of the application.

How to apply for a Bensenville building permit

1. Confirm the village has the parcel

Check the address on the Community Portal; unincorporated land goes to DuPage or Cook County.

2. Gather the checklist items

Use the Permit Checklist for your project type and draw plans to the code year the village enforces.

3. Line up contractors

Collect electricians’ municipal licenses and $10,000 bonds, the plumber’s license and letter of intent and the roofer’s state license.

4. Submit

Email the application and plans to permits@bensenville.il.us or file at Village Hall, with the owner’s signature, proposal, plat of survey and escrow.

5. Plan review

The Village Plan Reviewer checks codes and zoning; simple jobs can be approved in days.

6. Pay and pick up

Pay the fees, drop off the hard plan sets if required and display the permit placard in a front window.

Rather not deal with the building department?

Get a free quote →

Review, corrections and what causes delay

The building permits page says significant projects are reviewed in 12 days or less, while the general submission sheet gives 10 days as the general review time. Plans that do not state the code year are denied, and missing owner signatures, proposals, surveys, contractor bonds or escrow hold up an application. Work authorized by a permit must be finished within the time the FAQ sets (it reads “one (6) months”), and the Director may extend a permit case by case.

Inspections and certificates in Bensenville

The required inspections are listed on the permit information given when the permit is issued. Book each one at least 24 hours ahead by calling CED at 630-350-3413 with the address, the permit application number and a phone number and email; a confirmation email gives the date and time. Keep the placard in a window visible from the street until the final inspection is approved. When the final is approved, the escrow refund is processed and usually reaches the payee in four to six weeks; refunds go only to the person who paid, at the address on file. No one may occupy or use new space until CED approves it in writing.

The village’s list of common inspection items gives a sense of what inspectors flag: BX cable is not allowed and must be replaced with hard pipe, as must Romex entering a panel; GFCI receptacles are needed within 6 feet of water, outdoors and in garages; new receptacles must be tamper resistant; stairs with four or more risers need handrails 34 to 38 inches high; gas appliances need an accessible sediment trap; water meters need a jumper wire and water heaters bonding; and electrical panels need 36 inches of clearance. Parking is allowed only on asphalt, concrete or pavers, and crumbling driveways and parking lots must be repaired under a permit.

CED inspectors also inspect every rental property, single-family and multi-family, each year: owners register in October, schedule within 30 days and finish inspections by October 1. Non-residential properties are inspected annually, usually door to door by area, and buyers or sellers can request a real estate transfer inspection on the village form.

Illinois building code in Bensenville

Bensenville enforces the 2021 International codes and the 2023 National Electrical Code with local amendments in the Village Code. FEMA’s Community Status Book lists the Village of Bensenville (community 170200, in DuPage and Cook counties) as participating in the National Flood Insurance Program, with flood maps effective August 1, 2019.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Want this handled start to finish?

Get a free quote →

Bensenville building permit FAQs

Do I need a permit to replace windows in Bensenville?

No, but you must give CED the efficiency rating of the new windows so it can confirm energy code compliance.

Can I get a roofing permit the same day?

Yes. Roofing, siding, gutter, fascia and emergency permits are same-day permits.

What is the escrow for?

It encourages finishing on time and getting inspections; failed-inspection fees come out of it, and the rest is refunded after the final.

How much is a permit for a house addition?

Under 500 square feet, a $200 application fee and $330 plan review, plus $35 per inspection and a $140 refundable escrow.

Can a homeowner do their own electrical work?

Yes, on a single-family house that is their primary residence; otherwise the electrician needs a municipal license and a $10,000 bond.

How do I schedule an inspection?

Call 630-350-3413 at least 24 hours ahead with the address and permit number.

Is there help paying for an overhead sewer?

Yes. The village reimburses 75% of the cost, up to $7,500, for an overhead sewer and up to $750 for a backflow device, with permits and approval before work starts.

What happens if I start without a permit?

The village can issue a stop work order, and permit fees are doubled.

Bensenville permit search and official resources

Call CED at 630-350-3413 about a permit or inspection. For copies of permit records, file a Freedom of Information Act request with the Village Clerk’s Office in person or by mail at 12 S. Center Street, or email it to FOIArequest@bensenville.il.us; the village generally responds within five working days, with up to five more allowed in some cases. Completed FOIA requests are listed by month on the village’s FOIA page.

Inspections are where schedules slip.

Get a free quote →

Simplify Bensenville permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Bensenville sooner?

Let Alliance prepare, file, and track your Bensenville permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Bensenville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.