In the Village of Bellwood, building permits come from the Building Department, the office of the Building Commissioner at Village Hall, 3200 Washington Boulevard ((708) 547-3500, ext. 1609 or 1610). A permit is issued only after the Building, Finance and Police departments approve it, so unpaid water bills, open code violations or parking tickets stop it. Contractors need a Bellwood contractor’s license, which costs $175 a year and requires a $10,000 bond, while a homeowner doing the work files a Homeowners Completion Statement.
What requires a building permit in Bellwood?
Bellwood’s permit page says that anyone making certain repairs, remodeling or building new on their property must apply for a building permit, and that every job must comply with the village building and zoning codes. The Building Department lists the permits it issues:
Issued by the Building Department
- Building permits for new construction and room additions
- General and replacement permits
- Fence permits
- Electrical permits (blue card) and plumbing permits (yellow card)
- Certificates of occupancy for every space, structure or premises before use
Village inspections without a project
- A pre-sale inspection before any house or commercial property is sold
- A rental inspection before a property is leased
- Yearly inspections of multi-unit and commercial buildings
- An area exterior inspection that covers the whole village each year
Any work outside the building needs a plat of survey with the application, and the application form asks whether the property sits in a flood zone and whether it is vacant. Work in a village street or alley, including utility installations, uses a separate right-of-way permit approved by the village engineer and the Building Commissioner.
What Bellwood decides and what the state holds
Bellwood adopted its current set of codes in March 2020 and keeps its own building code as Chapter 150 of the Code of Ordinances. The Village Board’s April 15, 2026 agenda listed an ordinance to permit a variation from Section 117.072 of the village code and the 2017 National Electrical Code for one manufacturer’s CE-marked equipment. The state side covers plumbing, done under the Illinois Plumbing Code by an IDPH-licensed plumber, and roofing, where contractors carry a state license, plus the statewide energy and accessibility codes.
Bellwood building department: who handles permitting
The Building Department, run as the Building Commissioner’s office, issues permits, inspects work and licenses contractors for property inside Bellwood. It also handles the paperwork behind property sales. Zoning requests go to the village’s Zoning Department, and land outside the village in unincorporated Cook County is the county Department of Building and Zoning’s concern.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Office of the Building Commissioner, Village Hall, 3200 Washington Boulevard, Bellwood, IL 60104 |
| Phone | (708) 547-3500, ext. 1609 or 1610; department line (708) 547-3545 |
| Department hours | Monday to Friday, 9 a.m. to 5 p.m. (Village Hall also opens 9 a.m. to noon on Saturdays) |
| Zoning | Zoning Department, (708) 547-3500, ext. 1650 |
| Water meter and sidewalk inspections (property sales) | Water Department 708-547-3520; sidewalk inspections 708-547-3540 |
| Code | Bellwood Code of Ordinances, Chapter 150 (building) and Chapter 156 |
Bellwood permit types
Bellwood uses one Application for Building Permit (revised June 26, 2023) for commercial and residential work. It asks for the owner, the property index number, a description and total cost of the job, and the name of every trade: architect, general contractor, excavator, concrete, steel or precast erector, mason, carpenter, roofer, sheet metal, plumber, HVAC, sprinkler and electrician. Attach the work contract or plans. The office worksheet on the form prices general construction, electrical, HVAC, water meter, roofing, plumbing, plan and processing review and street opening separately, and the office calls when the permit is ready to collect and tells you the cost.
Residential permits
Room additions, new construction, fences and replacement work all use the same application, with a plat of survey for anything outside the house. The permit card goes up where it can be seen from the main street before work starts. When a house is being sold, any repairs flagged in the pre-sale inspection need their own permits before the work begins.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial work uses the same application, and every new tenant space needs a certificate of occupancy first. The village will not issue a business license or other operating license until that certificate exists, and the application has to be picked up in person at the Building Commissioner’s office. Commercial and industrial buildings and apartment buildings of three or more units also need a fire department inspection when they are sold.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning relief. The Zoning Department processes rezonings, conditional uses, special exceptions, variances and administrative appeals. In 2026 the Planning Commission held the hearings on conditional uses and text amendments and the Zoning Board of Appeals heard variances, each recommending an ordinance to the Village Board. The Planning Board has seven members appointed by the mayor for four-year terms, and the village posts a 2019 zoning map for checking a lot’s district before you apply.
- Clean accounts. Pay off any water bill, code violation or parking ticket, because Finance and Police must approve the permit.
- Stormwater. Bellwood is not one of the towns MWRD authorizes to issue watershed permits, so sites that trigger the district’s Watershed Management Ordinance, such as development disturbing more than half an acre, apply to MWRD directly.
- Right-of-way. Utility or other work in a village street or alley needs the separate right-of-way permit. Before it takes effect the applicant posts a cash restoration bond, a construction bond and a cash deposit for the village’s outside consultant review, pays the review and permit fees, and files insurance naming the village and its engineer as additional insured. Restoration must include at least 4 inches of topsoil and sod on disturbed grass, 5-inch concrete for sidewalks and 7-inch concrete for driveways, and no parkway tree may be trimmed without approval. Work is coordinated with Public Works (708-547-3540) and the village engineers, Edwin Hancock Engineering.
Bellwood permit costs and fees
Bellwood says its permit fees vary and are calculated from the work being done, and no building fee schedule is posted on the permit page, so the office states the cost when the permit is ready. The village does publish its license and inspection charges:
| Item | Fee |
|---|---|
| Contractor’s license, May 1 to April 30 | $175; $131.25 from August 1; $87.50 from November 1; $43.75 from February 1 |
| Plumbing contractor license | No fee |
| Pre-sale inspection, single-family house | $125 processing + $50 inspection |
| Pre-sale inspection, two-family house | $150 + $50 |
| Pre-sale inspection, commercial or industrial | $175 + $50 up to 5,000 sq ft; $200 + $50 above |
| Pre-sale inspection, multi-family building | $150 + $50, plus $10 per unit |
| Pre-sale inspection, condominium unit | $150 + $50 on the Building Department page; $75 + $50 on the 2025 selling checklist |
| Additional re-inspection | $125 each |
| Rental inspection | $35 residential; $50 commercial |
| Real estate transfer stamp | $5 per $1,000 of value ($10 per $1,000 if closing comes first) |
Rather talk it over?
Call 1-855-478-4290 →The pre-sale processing and inspection fees cover the first inspection and one compliance check, and no inspection fee is charged if the village does not perform the inspection. Two village documents give different condominium figures, so confirm that one with the office before paying.
Trade permits and who may pull them
Every contractor working in Bellwood must hold a village contractor’s license, renewed each May 1, and the contractor’s card is mailed within seven business days. The license classes are general, electrical, plumbing and sewer, roofing and HVAC; the general class covers asphalt, concrete, masonry, decks and porches, doors, fences, carpentry, gutters, siding, windows and handyman work.
- All licensed trades file a $1,000,000 liability insurance certificate and a $10,000 surety bond, except plumbers.
- Electrical contractors show a license from a community that gives an electrical test; electrical permits carry a blue card.
- Plumbing contractors file the IDPH plumbing contractor certificate and state plumber’s license and pay no license fee; plumbing permits carry a yellow card.
- Roofers add a copy of the state roofing license.
- HVAC contractors license in their own class.
Homeowners may do their own work, but Bellwood asks them to complete and submit the Homeowners Completion Statement with the permit application.
How to apply for a Bellwood building permit
Clear any unpaid water bill, code violation or parking ticket on the property.
Ask the Zoning Department (ext. 1650) whether the project needs a variance or conditional use.
Each contractor needs a current Bellwood license, insurance and bond on file.
Fill in the Application for Building Permit, attach the contract or plans and a plat of survey for outside work, or the Homeowners Completion Statement.
Building, Finance and Police each approve; the office then calls with the cost.
Collect the permit card and post it facing the main street before any work starts.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The application warns that it will not be processed until every required item is filled in, and any change of contractor must be reported to the Building Commissioner’s office. An unlicensed or unbonded contractor, or a balance owed to another village department, also stops the permit. A permit is good for six months from the date it is bought, so plan the start date accordingly.
Inspections in Bellwood
Village building inspectors check permitted work; call the Building Department at (708) 547-3545 or the main line to arrange a visit. The certificate of occupancy for a new or changed space follows an on-site inspection that confirms the use fits village ordinances and codes, or that the needed variances were granted.
Property sales add their own round of checks. The seller files the pre-sale inspection application and pays before the inspection is booked; the report is usually ready in three to five business days and is valid for six months. After that come a final water reading, a Water Department check of the meter and remote reader, and a public sidewalk inspection booked at least 72 hours ahead, all before the transfer stamp is sold. Rental properties are inspected before they are let, and a letter of compliance follows once violations are fixed and re-inspected.
When a pre-sale report lists violations, the seller can either make the repairs under permit and book a re-inspection, which leads to a compliance report, or use the village’s property sales affidavit or an escrow account. A buyer who takes on the repairs signs and notarizes the Purchaser’s Acknowledgement Agreement. The Building Department also wants the front page of the sale contract, the original plat of survey and the signed, notarized original deed, and every fine owed to the Police, Finance or Building departments must be paid before the transfer stamp is issued.
Illinois building code in Bellwood
Bellwood’s March 2020 code list names the 2018 International Building, Residential, Energy Conservation, Fire, Mechanical, Fuel Gas, Swimming Pool and Spa and Property Maintenance codes, the 2017 National Electrical Code, the 2014 Illinois Plumbing Code, the state energy and accessibility codes and the village’s own Chapter 150. FEMA’s Community Status Book lists the Village of Bellwood (community 170061) as participating in the National Flood Insurance Program, with its flood map effective August 19, 2008.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Want this handled start to finish?
Get a free quote →Bellwood permit search and official resources
Old permits, inspection reports and plans are public records requested under the Freedom of Information Act. Send the village’s FOIA request form to the FOIA Officer at 3200 Washington Boulevard, by email to FOIA@vil.bellwood.il.us, by fax to (708) 547-1965 or in person, and keep a copy in case you later need to ask the state Public Access Counselor for a review.
- Applications, licenses and permits
- Building Department
- Application for building permit (2023)
- Contractor’s license application
- Procedures for obtaining a contractor’s license
- Certificate of occupancy application (sample)
- Procedures for selling a home (2025)
- Right-of-way permit application
- Codes adopted March 2020
- Zoning Department
- Village Board agendas and minutes
- FOIA request form
- FEMA Community Status Book, Illinois
Inspections are where schedules slip.
Get a free quote →Bellwood building permit FAQs
Why was my Bellwood permit held up?
Permits need approval from the Building, Finance and Police departments, so an unpaid water bill, open code violation or parking ticket on the property will stop issuance.
Can I do the work myself?
Yes; a homeowner doing the work fills out the Homeowners Completion Statement and submits it with the application.
How much is a contractor’s license?
$175 for a full May-to-April year, prorated down to $43.75 from February, with a $10,000 bond; plumbers pay nothing.
How long is a permit valid?
Six months from the date of purchase, with the card posted where it can be seen from the main street.
Do I need an inspection to sell my house?
Yes. A pre-sale inspection is required for every sale; for a single-family house it costs $125 to process plus $50 for the inspection.
Does a new business need a certificate of occupancy?
Yes. No business license is issued until the space has a certificate of occupancy, which must be applied for in person.
Does a rental property need an inspection?
Yes. Owners pay $35 for a residential or $50 for a commercial rental inspection, and a letter of compliance is issued once any violations are corrected.
Who handles variances?
The Zoning Department processes them, the Zoning Board of Appeals holds the hearing and the Village Board decides by ordinance.
Simplify Bellwood permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Bellwood sooner?
Let Alliance prepare, file, and track your Bellwood permits while your crew stays on the job.
More Illinois permitting guides
Cook County
Read guide →Blue Island
Read guide →Brookfield
Read guide →Belvidere Building Permit Guide
Read guide →Bensenville Building Permit Guide
Read guide →Berwyn Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Bellwood permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.