Barrington, Illinois Building Permit Guide

To get a building permit in Barrington, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Barrington’s Development Services Department at 200 South Hough Street takes building permits and contractor registrations online for land inside the village, in both its Cook and Lake County parts.

Authority: Barrington Development ServicesFiling: SmartGov online portalPhone: (847) 304-3460
Authority
Development Services200 S. Hough St., Barrington
Filing
Online portalSubmit, pay and print permits online
New house fee
$0.95 per sq ftPlus plan review; schedule of July 1, 2018
Inspections
24 hours’ noticeCall (847) 304-3460

The Village of Barrington issues its own building permits through the Development Services Department at 200 South Hough Street ((847) 304-3460), led by Director of Development Services Jennifer Tennant. Applications, plan review comments, payment and the permit itself all move through the village’s online permit and contractor registration portal, and every contractor on the job must be registered before a permit is issued. Under the fee schedule in effect since July 1, 2018, new living space in a detached house is charged $0.95 per square foot plus plan review.

What requires a building permit in Barrington?

Barrington publishes a submittal list for each kind of project it permits, and the list itself shows how wide the net is. Some items are full construction permits; a few are reviewed for zoning only.

Construction permit

  • New houses and garages, additions, interior alterations such as kitchen and bath remodels
  • Decks, gazebos, driveways, patios, walkways and parking lot repair or restriping
  • Fences, generators, air conditioning units, water heaters and solar panels
  • Roofs, gutters, siding, trim, windows and doors
  • Permanent pools, lawn irrigation, signs and awnings
  • Demolition, fire alarms, fire suppression and sanitary or water service repairs

No-fee reviews

  • Playsets: zoning review only, no fee, with a plat showing setbacks
  • Temporary or seasonal pools: a no-fee permit for zoning and code review, with a letter promising removal at season’s end

Seasonal pools may not go in a front or corner side yard, and a pool under 48 inches tall needs a compliant fence or barrier, which an existing fence with a self-latching gate can satisfy. Irrigation heads must stay on private property, out of the right-of-way. Work may run from 7 a.m. to 7 p.m. on weekdays and 8 a.m. to 6 p.m. on weekends.

What Barrington decides and what the state holds

Barrington adopts its own codes and local amendments, its fee schedule, contractor registration and zoning rules; its Village Code is published in the Municode library. One local amendment makes any new building or addition dug deeper than the existing structure supply a soil boring with seasonally adjusted water-table data, and a foundation that would sit in the water table must be raised or waterproofed. Plumbing still follows the Illinois State Plumbing Code with a state-licensed plumber, energy work follows the Illinois Energy Conservation Code, and roofers need the state roofing license.

Barrington building department: who handles permitting

Development Services handles permits, plan review, contractor registration and inspections for everything inside the village, and its Planning & Zoning Division staffs the Plan Commission, Zoning Board of Appeals and Architectural Review Commission. About 5,740 residents live in the Cook County part of the village and 4,846 in the Lake County part, according to Census estimates for 2025; both answer to the same village office.

Short on time to read all of this?

Get a free quote →
Barrington permit contacts
DetailInformation
OfficeDevelopment Services, Village Hall, 200 South Hough Street, Barrington, IL 60010
Front desk(847) 304-3460; fax (847) 381-1056; Village Hall main line (847) 304-3400
Department headJennifer Tennant, Director of Development Services, (847) 304-3462
FilingOnline permit and contractor registration portal (SmartGov)
Inspections(847) 304-3460, at least 24 hours ahead
ZoningPlanning & Zoning Division; Village Planner (847) 304-3463

Plenty of homes outside the village carry a Barrington mailing address. The village says that in most cases a five-digit street number means the property is outside its limits, and it holds no building or zoning records for those unincorporated parcels; they belong to the county they sit in, which in Cook means the county Department of Building and Zoning.

Barrington permit types

Every application starts with the Village of Barrington Construction Permit Application, filed through the portal with the documents on the project’s submittal list. The form asks for the total square footage of the building and of the space added or remodeled, the estimated cost, whether a fire alarm or sprinkler system exists, and the name of each contractor by trade. The owner also acknowledges that a village permit does not waive any homeowners’ association covenants or private restrictions on the lot.

Residential permits

  • New houses and garages need two paper sets in addition to the online filing, a plat of survey, stamped engineering and grading plans with impervious-surface figures, stamped architectural plans labeling floor area, lot coverage, setbacks, daylight plane and building height, a soil boring and a water service review form.
  • Additions follow the same list, with a paper copy only if the reviewer asks for one, plus a watershed development permit.
  • Decks, driveways, patios and walkways need a plat and scaled site plan; driveways show the width at the property line and at the street.
  • Water heaters and service repairs need a letter of intent from the plumber.
  • Roofs and windows need product specifications, and in the Historic District, photos of the existing materials.

Commercial permits

Commercial, non-residential and multi-family work uses the same application and portal, priced on its own square-foot rate. Fire suppression systems need drawings and the technical submission the village cites under 225 ILCS 325, and parking lot work shows stall and aisle sizes, accessible stalls and routes. Demolition has its own submittal guidelines and checklist, and a site restoration and grading plan is required when no new building will follow right away; when a project includes demolition or fire alarm or sprinkler work, those parts need their own separate permits. New commercial and multi-family buildings also go to the Architectural Review Commission for their exterior appearance, and a business opening or moving in the village must complete a Business Registration and Zoning Certificate application before it occupies the space.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Historic Overlay District. Any exterior change needs a Certificate of Appropriateness from the Architectural Review Commission in addition to the permit. There is no fee, the review generally takes 60 to 90 days, and replacement roofs or windows may be approved by staff if no original material is removed.
  • Zoning relief. Variations and special uses go to the Zoning Board of Appeals, which recommends to the Village Board; the process averages 10 to 12 weeks, and the village asks applicants to meet a zoning coordinator first.
  • Planned developments, subdivisions, annexation and rezoning go to the Plan Commission.
  • Stormwater. MWRD lists Barrington as a multi-county village that applies the Lake County Watershed Development Ordinance in its Cook County part, so a district permit is needed only for the activities listed in Section 201.2 of MWRD’s Watershed Management Ordinance.

Barrington permit costs and fees

The village’s Construction Permit Fee Schedule took effect on July 1, 2018. Most projects pay a permit fee and a plan review fee; size-based work is measured on gross floor area including the outside walls.

Rather talk it over?

Call 1-855-478-4290 →
Barrington construction permit fees (effective July 1, 2018)
WorkFee
Habitable space, detached single-family$0.95 per sq ft (non-habitable or converted space $0.60)
Habitable space, attached single-family$1.00 per sq ft
Habitable space, commercial, non-residential and multi-family$1.05 per sq ft
Plan review by size$100 to 1,000 sq ft; $300 to 3,000; $500 to 5,000; $800 above, plus $100 an hour past two hours
Electrical, plumbing or HVAC for new work and alterations$0.12 per sq ft each, $55 minimum
Deck, fence, patio, roof, siding, shed, windows or water heater$55 plus $50 review ($105)
In-ground pool, hot tub or spa$300 plus review
Certificate of occupancy$50 per single-family unit; $100 per commercial or multi-family unit; temporary $50
Permit extension / reinspection$100 / $75
Right-of-way bond$1,000 cash deposit
Road or performance bond$0.50 per sq ft; none if the amount is under $250
Temporary use permit$100 per 90 days with a valid building permit; $25 per 15 days without one
Moving a structure / parking area$310 in total / $225 plus review
Starting work without a permit50% of total permit fees or $750, whichever is less
Stormwater review and inspection, under 5 acres$320 + $320 ($400 + $640 in floodplain or wetlands)

For example, a 2,000-square-foot habitable addition to a detached house has a base permit fee of 2,000 × $0.95, or $1,900, and a $300 plan review fee, for $2,200 before the electrical, plumbing and mechanical charges; the schedule warns that the final total also depends on the number of inspections. Two figures differ between documents: the schedule lists contractor registration at $75 ($50 after July 1), while the registration form itself charges $100, and the permits page mentions a $50 charge for a failed corner-stake inspection against the schedule’s $75 reinspection fee.

Trade permits and who may pull them

Barrington will not issue a permit until every contractor and subcontractor on it, from the general contractor and excavator down to the paver and sider, has registered with the village. Registration is valid for one year from payment and is filed through the same portal.

  • Electricians attach a copy of a municipal electrical license. The village’s Electrical Commission, chaired by the chief electrical inspector, recommends electrical rules and hears appeals of electrical inspection decisions.
  • Plumbers attach the state plumbing license and register free of charge.
  • Alarm contractors also register at no fee.
  • Roofers attach the state roofing license.
  • General contractors provide a certificate of insurance.

Electrical, plumbing and HVAC work on new construction and alterations is priced per square foot, and a new or upgraded electrical service is $100 per panel.

Rather not deal with the building department?

Get a free quote →

How to apply for a Barrington building permit

1. Check the address

Make sure the lot is inside the village; a five-digit address usually means it is not.

2. Clear historic or zoning review

Get a Certificate of Appropriateness in the Historic Overlay District, or zoning relief, before filing.

3. Register every contractor

Each trade on the job registers through the portal with its license or insurance papers.

4. File online

Upload the construction permit application and the project’s submittal list; new houses also need two paper sets.

5. Answer review comments

Log in to upload revisions or extra information when the reviewer asks.

6. Pay and print

Pay in the portal after the approval email, then print the approved plans and placard for the site.

Review, corrections and what causes delay

Applications that need engineering plans are not accepted or reviewed until those plans are attached, and plans must label every zoning figure the ordinance calculates, from daylight plane to top of foundation. An unregistered subcontractor holds up issuance, and work started before the permit costs half the permit fees or $750, whichever is less. A construction permit extension application and a $100 fee keep a slow job alive.

Inspections in Barrington

Call (847) 304-3460 at least 24 hours ahead with the permit number, site address and inspection type. If no one answers, leave those details; the inspection is booked only when staff call back to confirm a date and time. The printed approved plans and placard must be on site, or no inspection takes place.

For permanent structures and site improvements, from additions and garages to fences, patios, pools and freestanding signs, the owner must find and stake the property corner pins before the pre-pour inspection, hiring a licensed surveyor if needed, because the village has no surveyor of its own. A missed staking means no inspection, and work may not start until the pre-pour inspection passes. Occupancy certificates cost $50 per single-family unit and $100 per commercial unit.

Illinois building code in Barrington

Barrington lists the 2018 International Codes, effective for submissions received on or after September 1, 2018, with the 2017 National Electrical Code, the Illinois Energy Conservation Code (2021 IECC), the Illinois State Plumbing Code, the Illinois Accessibility Code and local amendments. FEMA’s Community Status Book lists the Village of Barrington (community 170057) as participating in the National Flood Insurance Program, with flood maps effective January 23, 2026.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Barrington permit search and official resources

Open applications are handled in the online portal, where applicants upload revisions and pay. For older permits and plans, use the village’s online FOIA portal; non-commercial requests are answered within five business days and commercial ones within 21. Emailed responses are free, the first 50 black-and-white pages cost nothing, extra pages are 15 cents and certified copies $1, and architects’ plans can be withheld as copyrighted material.

Inspections are where schedules slip.

Get a free quote →

Barrington building permit FAQs

How do I apply for a permit in Barrington?

Online, through the village’s permit and contractor registration portal, after every contractor on the job has registered.

What does a new house permit cost?

Living space in a detached house is $0.95 per square foot, plus plan review of $100 to $800 by size, trade fees and occupancy fees, under the 2018 schedule.

Do I need a permit for a playset or a summer pool?

Playsets get a zoning review with no fee, and temporary pools a no-fee permit; both still need a plat showing setbacks.

My house is in the Historic District. What extra approval do I need?

A Certificate of Appropriateness from the Architectural Review Commission before the building permit; it is free and usually takes 60 to 90 days.

How do I schedule an inspection?

Call (847) 304-3460 at least 24 hours ahead; the time is confirmed only when staff call you back.

Is my Barrington address inside the village?

Usually not if the street number has five digits; Development Services can confirm, and unincorporated parcels file with their county.

How long do zoning variations take?

About 10 to 12 weeks on average, with a Zoning Board of Appeals hearing and a final Village Board vote.

Simplify Barrington permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Barrington sooner?

Let Alliance prepare, file, and track your Barrington permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Barrington permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.