Building permits in Maywood are issued by the City’s Building Division, part of the Building and Planning Department at City Hall, 4319 East Slauson Avenue (323-562-5744). Permits can be applied for and tracked online in the City’s GoGov portal, plans are submitted for plan check by appointment, and inspections are made on Tuesdays and Thursdays. Maywood also requires a pre-sale property inspection, with a $110 application fee, before any property is sold.
What requires a building permit in Maywood?
The City says permits are required for all new construction and in most cases for building modifications, replacements and remodeling, and that skipping a required permit brings fines and penalties for both the owner and the contractor. The Building Division’s handouts spell out where the line falls for the most common home projects.
Permit needed
- Bathroom remodels that remove, replace or move vanities, toilets, sinks, tubs or showers, change wiring, or replace wallboard
- Kitchen remodels that remove or move cabinets and countertops, the sink or dishwasher, add or alter an island, or change wiring or the exhaust hood
- Re-roofs (a change of roofing material may also need Planning approval)
- Window replacements (egress rules for bedrooms)
- Patio covers, block walls and new construction
- Residential solar systems
No permit, per City handouts
- Replacing towel bars or mirrors
- Paint and floor coverings
- Replacing a kitchen countertop or re-facing existing cabinets
A new business also needs a City occupancy permit before opening, even if the space it is leasing needs no remodeling. Work in the public right of way is outside the Building Division and needs a City encroachment permit.
What Maywood decides and what the state holds
Maywood adopted the 2025 California building codes, along with the 1997 Uniform Housing Code, the Uniform Code for the Abatement of Dangerous Buildings and the 2024 International Property Maintenance Code, by Ordinance No. 25-06, adopted January 21, 2026 and amending Title 8 of the Municipal Code; the local changes in its text deal with permit and plan check fees, the investigation fee and penalties. The City also sets zoning (the 2009 Zoning Ordinance, with ADU rules added by Ordinance No. 24-02), its pre-sale inspection program and its waste hauling rules. Contractors are licensed by the state, and the City verifies their license and workers’ compensation coverage.
Maywood building department: who handles permitting
The City of Maywood issues building permits within its limits through the Building Division, which also performs site inspections. Daisy Guerrero is the Director of Building and Planning. The City’s staff directory shows its permit technician and building inspector positions filled by contract staff, reached through the Building Division’s shared phone and email.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building and Planning, Maywood City Hall, 4319 East Slauson Avenue, Maywood, CA 90270 |
| Building Division | 323-562-5744; building@cityofmaywood.org |
| Permit counter | Tuesdays and Thursdays 8 to 11 a.m., Wednesdays 8 to 10 a.m., by appointment |
| Inspections | Tuesdays and Thursdays, 8 a.m. to 12 p.m. and 1 to 3 p.m., by appointment |
| Planning Division | 323-562-5723; planning@cityofmaywood.org; counter Wednesdays and Fridays by appointment |
| City Hall main line | 323-562-5700 |
| Online | GoGov permit portal and the Building and Planning appointment calendar |
The building inspector takes questions by phone on Tuesdays and Thursdays from 8 a.m. to noon.
Maywood permit types and what comes first
Maywood uses one Building and Planning Permit Application for building work. It asks for the owner and contractor, the contractor’s license number and class, type of construction, occupancy, stories and valuation, and has sections for new buildings, additions, alterations and tenant improvements, block walls, windows and sliding doors, stucco or siding, re-roofs, and electrical, plumbing and mechanical items.
Residential permits
For re-roofs, the City’s handout calls for Class B roofing at minimum, no more than one overlay of asphalt shingles over existing shingles, replacement with the same material approved for the house (asphalt for asphalt, tile for tile), 15/32-inch CDX radiant-barrier plywood where new sheathing goes in, and a structural evaluation by a licensed design professional for roofing heavier than 6 pounds per square foot. The bathroom and kitchen remodel handouts cite California Civil Code 1101.4(a), which requires existing non-compliant plumbing fixtures throughout the house to be upgraded whenever a building permit is issued for remodeling, even fixtures outside the scope of work, and the bathroom handout requires smoke alarms when the permit exceeds $1,000. Replacement bedroom windows must keep a 5.7-square-foot clear opening (5.0 at grade), at least 24 inches high and 20 inches wide, with the sill no more than 44 inches above the floor, and security bars must release from inside.
Owner-occupants of single-family detached homes who meet the income limit (150% of area median income) can apply to the City’s Maywood Cares program for up to $20,000 toward repairs such as roofing, electrical, plumbing, heating and cooling, windows and structural work. The City inspects the home to set the scope, and work may not begin until it issues a Notice to Proceed and all required permits are in hand.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial projects use the same application with the tenant improvement and commercial boxes, and commercial re-roofs note whether energy compliance forms are provided. Every new business must apply for an occupancy permit, and Planning reviews certificates of occupancy, childcare facilities, sign permits and minor development projects as administrative applications.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning. Conditional use permits, variances, temporary use permits, lot mergers and zone changes go through Planning’s Land Use Permit application; fence permits, home occupations and sign permits are administrative.
- ADUs. The Planning Division posts the 2025 ADU Handbook and Ordinance No. 24-02, which added ADU rules (Section 4070.120) to the Zoning Ordinance.
- Right of way. Encroachment permits for any work in the street or sidewalk.
- Excavation near a lot line. Proof of the required neighbor notifications must be filed with the City before excavating at or near a property line.
Maywood permit fees
Maywood’s building fees are set by City Council resolution: Ordinance No. 25-06 amends Section 109.2 of the building code so that permit fees follow “the schedule as established by the City Council”, with the plan-checking fee paid when plans are submitted. The City does not post that building fee schedule on its Building, Building Permits or Documents and Forms pages, so ask the Building Division (323-562-5744) for a quote; the GoGov portal shows the fees on an application once it is entered. These amounts are published:
| Item | Fee |
|---|---|
| Building permit and plan check | By City Council fee resolution; plan check paid at submittal |
| Additional plan check (incomplete or changed plans) | At a rate set by the Building Official |
| Work started before a permit (investigation fee) | Equal to the permit fee, at least $100 |
| Pre-sale property inspection | $110 application, non-refundable; a new $110 application if the 6-month window lapses |
| SolarAPP+ automated review (paid to SolarAPP+) | $25, plus City permit fees |
Rather talk it over?
Call 1-855-478-4290 →The investigation fee does not replace the permit or any penalties: the ordinance says paying it does not excuse full compliance with the code. Gas and electric utilities are released only after final clearance and once all applicable fees have been paid.
Trade permits and who may pull them
Electrical, plumbing and mechanical work is listed on the same application, which counts service panels and sub-panels, branch circuits, outlets, fixtures, appliances and power equipment by size. The City checks that contractors hold a valid state license and workers’ compensation insurance before issuing permits.
Every contractor and subcontractor working in Maywood needs a City business license; the construction rules warn that a missing subcontractor license will delay final inspection, and the SolarAPP+ page repeats that contractors must hold a Maywood license to finish permitting. Renewal payments are mailed by check to the Business Support Center in Fresno named on the City’s business license page.
Rooftop solar installers may use SolarAPP+, the automated plan review: register, complete the IREC training, submit the system and pay SolarAPP+’s $25 processing fee, then upload the approval documents to a Residential Photovoltaic System record in GoGov, pay the City permit fees online and request an inspection. Homeowners installing their own systems cannot use SolarAPP+ unless they are licensed contractors. Systems with battery storage also follow the Los Angeles County Fire Department’s submittal procedures.
How to apply for a building permit in Maywood
Call 323-562-5723 or book a Wednesday or Friday Planning appointment if the project involves a new use, a fence, a sign, an ADU or a discretionary approval.
Complete the Building and Planning Permit Application with the scope, valuation and owner and contractor details.
Start the permit in the GoGov portal; for work that needs plans, use the appointment calendar to submit plans for plan check in person.
The plan check fee is due when plans are submitted; revised or incomplete plans can add plan check charges.
Arrange construction waste with Universal Waste Systems (562-287-7888) or plan to self-haul to a designated recycling site, and get City business licenses for every contractor.
Pay permit fees in the portal; permits are processed at the counter on Tuesday, Wednesday and Thursday mornings by appointment.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The counter and inspections run only on set weekdays, so book appointments early. Plans that come back incomplete or changed pay additional plan check fees, and a permit expires if work does not start within 365 days of issuance or stops for 365 days after the last inspection. Before excavating near a property line, file proof of the legally required notifications with the City.
Inspections in Maywood
Book inspections through the Building and Planning appointment calendar; they are made on Tuesdays and Thursdays from 8 a.m. to noon and 1 to 3 p.m., and questions go to 323-562-5744. A re-roof, for example, is inspected at tear-off with the sheathing exposed, again if new sheathing is installed, and at final, when the smoke and carbon monoxide alarm self-certification is handed to the inspector and an OSHA-approved ladder rated for 250 pounds must be on site.
Job sites must post a 24-by-36-inch weatherproof sign on each street frontage with work hours and the contractor’s emergency number, be secured with a 6-foot chain-link fence covered with windscreen, and keep to construction hours of 7 a.m. to 8 p.m. Monday to Saturday and 9 a.m. to 8 p.m. on Sundays.
Before any property is sold, the seller applies for a pre-sale inspection ($110). The building inspector, with the City Planner when available, inspects on Tuesdays or Thursdays from 1 to 4 p.m. with the seller or agent present, and the report, usually ready in two to three weeks, must be signed by buyer and seller and returned to the City within the application’s six-month life.
Building code in Maywood
Ordinance No. 25-06, adopted January 21, 2026 and in force 30 days later, replaced the building chapters of Title 8 of the Maywood Municipal Code, following an urgency ordinance (No. 25-05) that adopted the same codes in 2025. FEMA lists Maywood as a participating community in the National Flood Insurance Program, with no special flood hazard area mapped in the city.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Frequently asked questions
Want this handled start to finish?
Get a free quote →Who issues building permits in Maywood?
The City’s Building Division in the Building and Planning Department at City Hall, 4319 East Slauson Avenue (323-562-5744).
Can I apply online?
Yes. The GoGov portal takes permit applications and shows status and fees around the clock; plans for plan check are submitted at a booked in-person appointment.
How much does a building permit cost?
Building and plan check fees are set by City Council resolution, and the schedule is not posted online, so ask the Building Division or check the fees shown in GoGov. Starting work without a permit costs an investigation fee equal to the permit fee, at least $100.
Do I need a permit for a bathroom or kitchen remodel?
Yes, if fixtures, cabinets, wiring or wallboard are removed, replaced or moved. Replacing towel bars or mirrors, painting, new floor coverings, replacing a countertop or re-facing cabinets needs no permit.
When are inspections?
Tuesdays and Thursdays from 8 a.m. to noon and 1 to 3 p.m., booked through the City’s appointment calendar.
Do I need an inspection to sell my house?
Yes. Maywood requires a pre-sale property inspection before the sale of any property; the application fee is $110 and stays valid for six months.
Can a homeowner use SolarAPP+ for a rooftop solar permit?
Only a homeowner who is also a licensed contractor; the City’s SolarAPP+ page bars other owners installing their own systems from the automated review. Contractors using it still need a Maywood business license.
Can I hire any dumpster company?
No. Universal Waste Systems is the only authorized hauler for construction and demolition debris, unless the contractor self-hauls to a designated recycling site.
Maywood permit search and official resources
Applicants can follow their own permits, status and fees in the GoGov portal. For older permit records on a property, contact the Building Division.
Inspections are where schedules slip.
Get a free quote →- Building Division
- GoGov online permit portal
- Building and Planning appointments
- Building and Planning Permit Application (PDF)
- Construction regulations handout (PDF)
- Re-roofing requirements (PDF)
- Bathroom remodel handout (PDF)
- Kitchen remodel handout (PDF)
- Ordinance No. 25-06, building codes (PDF)
- Pre-sale inspections
- SolarAPP+ solar permits
- Planning Division
- Maywood Cares home repair program
- Planning documents and ADU rules
- California Building Standards Code (Title 24)
Simplify Maywood permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Maywood sooner?
Let Alliance prepare, file, and track your Maywood permits while your crew stays on the job.
More California permitting guides
Los Angeles County
Read guide →Montebello
Read guide →Monterey Park
Read guide →McFarland Building Permit Guide
Read guide →Mendocino County Building Permit Guide
Read guide →Mendota Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Maywood permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.