Skip to main content
Municipal GuideCaliforniaMontebello · Los Angeles County

Montebello, California Building Permit Guide

To get a building permit in Montebello, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Montebello’s Building and Safety Division, in the Planning and Community Development Department at City Hall, issues building, electrical, plumbing, mechanical and grading permits and takes complete applications by email.

Authority: Montebello Building and Safety DivisionFiling: Email to buildingsafety@montebelloca.govPhone: 323-887-1497
Authority
City Building and SafetyPlanning & Community Development
Open
Mon–ThuClosed Fridays; walk-ins all day
Fee schedule
Res. 25-77Effective Nov 1, 2025; CPI each July
Inspections
323-887-1458Mon–Thu 7:30–5:30

In Montebello, permits are issued by the City’s Building and Safety Division, part of the Planning and Community Development Department in the West Wing of City Hall. Complete applications go by email to buildingsafety@montebelloca.gov, permit technicians answer at 323-887-1497, and the counter is open Monday to Thursday with walk-ins all day. Fees come from Resolution No. 25-77, adopted August 27, 2025 and effective November 1, 2025, which charges a $36 issuance fee and valuation-based permit and plan check fees and adjusts them by CPI every July 1 from 2026.

What requires a building permit in Montebello?

Montebello’s Building and Safety Division reviews plans for and inspects new construction, renovated structures, additions and remodels, including heating, ventilation and air-conditioning units and electrical, plumbing and structural systems, and it issues building, electrical, plumbing, mechanical and grading permits. The division asks owners to contact it before starting any project to find out whether City approvals, permits and inspections are required.

Work the City permits

  • New buildings, additions and remodels
  • Accessory dwelling units and junior ADUs
  • HVAC units, electrical services and plumbing fixtures
  • Pools and spas
  • Grading, from 1 cubic yard up
  • Demolition of a building or structure
  • Changes of use or occupancy
  • Fire sprinkler and fire alarm systems (Fire Department)

Planning steps that may apply

  • Site plan review for new development
  • Hillside plan review on hillside lots
  • Walls and fences (Planning handout)
  • Signs, temporary uses and sidewalk dining
  • Conditional use permits and variances
  • Over-the-counter Planning review for small residential and commercial jobs

The City’s pages do not publish a list of work exempt from permits, so ask a permit technician before skipping a permit. Work done without one is charged an investigation fee equal to the permit fee and at least $365.

What Montebello decides and what the state holds

The City sets zoning and ADU standards, the hillside and site plan review process, construction hours (7 a.m. to 8 p.m. on weekdays and 9 a.m. to 6 p.m. on weekends and holidays under Municipal Code Section 9.08.050.I), its fee schedules and its business license tax. Its own Fire Department sets fire separation rules for new ADUs. Building standards come from Title 24, and contractors are licensed by the state.

Montebello building department: who handles permitting

The City of Montebello issues its own building permits through the Building and Safety Division. Joseph Palombi, Director of Planning and Community Development, oversees Building and Safety along with Planning, Code and Parking Enforcement, Economic Development and Housing. Public Works Engineering handles encroachment and driveway permits, and the Montebello Fire Department charges for fire sprinkler and alarm review and inspection.

Short on time to read all of this?

Get a free quote →
Montebello permit contacts
DetailInformation
OfficePlanning and Community Development, West Wing of Montebello City Hall, 1600 W. Beverly Blvd., Montebello, CA 90640
ApplicationsEmail complete application requests to buildingsafety@montebelloca.gov
Permit technicians323-887-1497
Building inspector323-887-1458; inspection requests by the City’s online Building Inspection Form
HoursMonday to Thursday, 7:30 a.m. to 5:30 p.m.; closed Fridays; walk-ins all day
Planning323-887-1478; walk-ins 7:30 to 11:30 a.m., appointments 1:30 to 5 p.m., Monday to Thursday
Public Works / Engineering; Fire Department323-887-1460; 323-887-4510

Montebello permit types and what comes first

Building and Safety issues building, electrical, plumbing, mechanical and grading permits, each with its own fee table, and every permit carries the $36 issuance fee. Applications go to the division by email, and the City notes that incomplete applications may delay processing.

Residential permits

A single-family lot may have one ADU, attached or detached, and one junior ADU. The Planning Division’s ADU fact sheet, revised October 28, 2026, asks for a site plan, roof plan, existing and proposed floor plans, elevations and the City’s ADU/SFR questionnaire. A new detached ADU may be up to 1,200 square feet and 16 feet tall (18 feet within half a mile of a major transit stop), with 4-foot side and rear setbacks, and the Fire Department requires 5 feet of separation from any other dwelling or accessory structure. An ADU over a detached garage is allowed only above an existing garage. ADU review costs $330 in Planning.

Walls and fences go to Planning by email with a site plan, an elevation of the fence or wall and, where it applies, a common property line wall agreement. The City’s handout limits a view-obscuring fence or wall in a residential front yard to 36 inches and an open (non-view-obscuring) one to 6 feet, and solid fences, walls or hedges in side and rear yards to 6 feet; the height includes any decorative top. On corner lots nothing over 36 inches may stand in a 15-foot sight triangle at the corner. Fencing seen from the street must be metal, vinyl, wood or masonry, and barbed wire, chain link, woven wire and plywood sheeting are not allowed.

Commercial permits

Commercial projects may need Planning entitlements first: site plan review ($3,662 in FY 2026-27), a conditional use permit ($8,790) where the use requires one, and sign plan check. A change of occupancy outside Groups R and U is inspected for $1,165 up to 5,000 square feet. New businesses also need a City business license, which Planning reviews for zoning, and the Fire Department charges $112 for a new-business license inspection.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Planning review. Over-the-counter review ($85) for small jobs, administrative and minor permits, site plan review, and hillside plan review (deposit $6,875) for hillside lots; a pre-application review costs $1,396.
  • Grading and drainage. Grading permits and plan check from 1 cubic yard, hydrology report review ($6,470) where one is required, and low-impact-development (LID) plan review starting at $219 for a single-family home.
  • Geotechnical review. Soils and geology reports are reviewed for 0.5% of valuation, from $2,200 to $14,190.
  • Public right of way. Driveway approaches ($430) and encroachment permits ($1,184) from Public Works, and a daily permit ($154) for a dumpster in the street.
  • Fire. Fire sprinkler plans and inspections through the Montebello Fire Department.

Montebello permit fees

The Building and Safety Master Fee Schedule was adopted by Resolution No. 25-77 on August 27, 2025 and took effect on November 1, 2025. It provides that every fee is adjusted each July 1, starting July 1, 2026, by the April-to-April change in the Los Angeles-area consumer price index, so the printed amounts below may have risen; the City’s fee page still posts the November 2025 schedule. Planning, Public Works and Fire fees are in a companion schedule, Resolution No. 25-76, which prints separate amounts for fiscal years 2025-26, 2026-27 and 2027-28.

Building permit fees, Table 1A (Resolution No. 25-77)
ValuationPermit fee
Up to $2,000$271, plus $6 per $100 over $500
$2,001 to $25,000$362, plus $43 per $1,000 over $1,000
$25,001 to $50,000$1,399, plus $36 per $1,000 over $25,000
$50,001 to $100,000$2,304, plus $33 per $1,000 over $50,000
$100,001 to $500,000$3,937, plus $11 per $1,000

Rather talk it over?

Call 1-855-478-4290 →
Other Building and Safety fees (Resolution No. 25-77)
ItemFee
Permit issuance$36 per permit
Building plan checkSeparate valuation table ($1,190 at $25,001 plus $31 per $1,000 to $50,000)
Energy / disabled access / CALGreen workTable 1A fee increased 10% / 5% / 5%
Expedited plan check125% of the plan check fee
Electrical / mechanical / plumbing plan check70% / 50% / 50% of the trade permit fee (minimum $437 / $437 / $475)
Grading permit, 1–50 cubic yards / 51–1,000$350 / $520 plus $176 per 100 cubic yards
Certificate of occupancy / temporary$220 / $328
Demolition inspection$256
Change of use, Group R or U$473
Additional review, per hour$219
Work without a permitEqual to the permit fee, at least $365
Building Board of Appeals hearing$930

Reading the table. For a job valued at $40,000, the Table 1A permit fee is $1,399 plus 15 × $36, or $1,939, before the energy, access and CALGreen increases, plan check, the $36 issuance fee, state fees and any CPI adjustment made since July 1, 2026. The Planning and Code schedule adds a technology enhancement fee of 6% (minimum $34) and a General Plan maintenance fee of 10% of application fees on Planning permits.

Trade permits and who may pull them

Electrical, mechanical and plumbing permits are issued by the same division from per-item tables: wiring for a new single- or two-family house is $0.45 per square foot, a new private in-ground pool $237, each plumbing fixture $36, and each water heater or roof drain $91, each with the $36 issuance fee. Plan check applies when plans are needed, at 70% of the electrical fee and 50% of the mechanical or plumbing fee, with minimums of $437 to $475.

Contractors need the state license for their trade, and owners may act as owner-builders under state law. A contractor doing business in Montebello also needs a City business license, handled for the City by the HdL Business Support Center (Montebello.hdlgov.com, 323-248-8614). New business license tax amounts took effect on February 1, 2026 after the City Council updated the Municipal Code on November 12, 2025; the application processing fee is $80 and the renewal processing fee $31.

Fire sprinkler systems are a Fire Department permit: in FY 2026-27 a residential riser is $499 with a $404 inspection, and a commercial riser $523 with a $740 inspection.

Rather not deal with the building department?

Get a free quote →

How to apply for a building permit in Montebello

1. Ask Planning first

Call 323-887-1478 or visit during walk-in hours to learn which Planning review applies: over-the-counter, ADU, site plan or hillside review.

2. File the Planning application

Use the Master Land Use or Minor and Administrative Permit application, the property owner authorization form and the plans the handout lists.

3. Assemble the building package

Prepare complete plans, calculations and any geotechnical, hydrology or LID documents for the work.

4. Email the application

Send the complete application to buildingsafety@montebelloca.gov and call a permit technician at 323-887-1497 with questions.

5. Answer plan check comments

Revise and resubmit; reviews beyond the second check are billed at $219 an hour.

6. Clear other departments and pay

Obtain Public Works, Fire and Planning sign-offs, then pay the permit, issuance and any surcharges to have the permit issued.

Review, corrections and what causes delay

The division warns that incomplete applications may delay processing. Expedited plan check is available at 125% of the normal plan check fee, and a preliminary plan review for code questions before filing has no base charge but carries a two staff-hour minimum, with time beyond that at $219 an hour. The division is closed on Fridays.

Inspections in Montebello

Inspections are requested by filling out the City’s online Building Inspection Form; questions go to the building inspector at 323-887-1458. Inspections are made only during City hours, Monday to Thursday from 7:30 a.m. to 5:30 p.m. Inspections the schedule does not price separately are billed at $182 an hour.

At the end of a project Building and Safety issues a certificate of occupancy ($220), or a temporary certificate ($328, with $220 for each extension). Demolition of a building, including termination of its sewer connection, is inspected for $256, and a change of use or occupancy of a house or garage-type building is inspected for $473.

Building code in Montebello

Montebello’s fee resolution charges building, electrical, mechanical and plumbing fees “per the relevant sections” of the codes the City adopts in its Municipal Code. FEMA lists Montebello as a participating community in the National Flood Insurance Program, with no special flood hazard area mapped in the city.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Want this handled start to finish?

Get a free quote →

Frequently asked questions

Who issues building permits in Montebello?

The City’s Building and Safety Division, part of the Planning and Community Development Department at City Hall. It issues building, electrical, plumbing, mechanical and grading permits.

How do I apply?

Email a complete application to buildingsafety@montebelloca.gov. Permit technicians can be reached at 323-887-1497, and walk-ins are taken Monday to Thursday.

Is the Building counter open on Fridays?

No. Building and Safety is open Monday to Thursday and closed on Fridays.

How much does a permit cost?

Under Resolution No. 25-77 a permit carries a $36 issuance fee plus a valuation-based permit fee, for example $1,399 plus $36 per $1,000 above $25,000 for a job of $25,001 to $50,000, and a separate plan check fee. Amounts are adjusted by CPI each July 1 from 2026.

Can I build an ADU?

Yes. Single-family lots may have one ADU and one junior ADU; a new detached ADU may be up to 1,200 square feet and 16 feet tall with 4-foot side and rear setbacks.

How do I book an inspection?

Submit the City’s online Building Inspection Form. Inspections take place Monday to Thursday between 7:30 a.m. and 5:30 p.m.

What are construction hours?

From 7 a.m. to 8 p.m. on weekdays and 9 a.m. to 6 p.m. on weekends and holidays.

Do contractors need a Montebello business license?

Yes, businesses operating in the city need a City business license, applied for through the HdL Business Support Center; new tax amounts took effect February 1, 2026.

Montebello permit search and official resources

For permit history on a property, contact Building and Safety at 323-887-1497; Planning charges $355 for public records research in FY 2026-27 under the Planning and Code schedule.

Inspections are where schedules slip.

Get a free quote →

Simplify Montebello permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Montebello sooner?

Let Alliance prepare, file, and track your Montebello permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Montebello permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.