Inside the City of Monterey, building, electrical, plumbing and mechanical permits come from the Building and Safety Division of the Community Development Department, 580 Pacific Street, Room 4 (831-646-3891), where Rob Allen is Chief of Inspection Services and Building Official. Since January 7, 2026 building permits can be filed in the city’s online portal. The city has no spare water credits, so any project that adds plumbing fixtures depends on the water credits already tied to its site.
What requires a building permit in Monterey?
The division’s FAQ states that no regulated building or structure may be erected, enlarged, altered, repaired, moved, improved, converted or demolished without a separate permit for each building. It names re-roofs and skylights, new electrical services or wiring, water heaters and new gas or water piping, heating and cooling systems, patio covers, and tents or awnings over 120 square feet.
No building permit (city FAQ)
- One-story detached structures under 120 square feet
- Fences 6 feet high or less
- Retaining walls under 3 feet from grade, unless supporting a surcharge
- Platforms and walks not over 30 inches
- Prefabricated pools of 5,000 gallons or less
- Movable cases and partitions up to 5 feet 9 inches
May need a permit (ask first)
- Windows and siding
- Platforms and retaining walls
- Fences
- Awnings and tents of any size
- Accessory structures under 120 square feet
Exempt work must still meet the City Code and may need another approval, so check with the division first. Work done without a permit is treated as a new project: the owner starts at the Planning Division with an application and plans, pays every application and permit fee, and may be charged illegal construction fees.
What Monterey decides and what the state holds
Monterey sets its own fees in a master fee schedule, its zoning and architectural review, its historic zoning (H-1 and H-2) and its ADU rules in City Code section 38-112.6. It runs a residential property inspection program for home sales and a mandatory sanitary sewer lateral inspection program under City Code 30-1.2. Water for new fixtures is controlled by the Monterey Peninsula Water Management District, and the state licenses contractors.
Monterey building department: who handles permitting
The Building and Safety Division of the Community Development Department reviews plans and inspects construction inside the city. The Planning Office, at 570 Pacific Street, handles zoning, architectural review, single-family review, use permits, variances and historic preservation. Unincorporated land outside the city limits is permitted by Monterey County.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building office | Building and Safety Office, 580 Pacific Street, Room 4, Monterey, CA 93940 |
| Phone | 831-646-3891 (main); 831-646-3890 (questions and inspection scheduling) |
| Office hours | Monday to Friday, 8 a.m. to 4 p.m.; closed noon to 1 p.m. and Wednesdays 1 to 2:15 p.m. |
| Permit counter hours | Monday to Friday 8 to 11:30 a.m.; afternoons 1 to 3:30 p.m. (Wednesdays 2:15 to 3:30 p.m.) |
| Building Official | Rob Allen, Chief of Inspection Services |
| Planning Office | 570 Pacific Street, 831-646-3885 |
| Other city offices | Fire 831-646-3900; Public Works 831-646-3462; Finance (business licenses) 831-646-3944 |
Monterey permit types
The online portal at mymontereyportal.org (also in the My Monterey Gov app) covers building permits only: re-roofs, electrical, plumbing and mechanical permits, solar, and residential and commercial projects of every size. It asks about scope, use and valuation so that the required reviews and fees are identified at filing. The project checklist (ADU, remodel, deck, EV charger, solar, general intake and others) still has to be uploaded. Encroachment permits, residential property inspections and sewer lateral inspection forms are not in the portal yet.
Residential permits
- Over the counter: Class A re-roofs, water heater replacements and similar plumbing, and minor electrical or mechanical work.
- ADUs follow City Code section 38-112.6 (Ordinance 3641, adopted November 2, 2021): a new attached or detached ADU at a house may be up to 850 square feet for a studio or one bedroom and 1,000 square feet for two or more bedrooms, 16 feet tall, at least 4 feet from side and rear lines, with its own entrance and materials matching the house. A second-story ADU over a garage, allowed only in the R-3 zone, may reach 25 feet with an architectural review permit. Proof of enough on-site water credits from the water district goes in with the building permit application.
- Junior ADUs stay within the house, up to 500 square feet with an efficiency kitchen; the owner records a covenant before the permit issues and must live in the house or the JADU. ADUs and JADUs cannot be rented for under 30 days.
- Legalizing older units: under AB 2533, owners of ADUs and JADUs built before January 1, 2020 can apply to legalize them; a building permit is still required, but corrections are limited to substandard health and safety conditions.
- Fire-damaged homes: a legal nonconforming building destroyed by fire or other calamity may be rebuilt to its earlier size and footprint if restoration starts within 18 months.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Plans must be stamped and signed by a California architect or engineer for structural alterations, changes of occupancy, assembly, school, factory, hazardous, institutional, R-1, R-2, R-6 and storage occupancies, large interior alterations over 3,000 square feet in B, S or M occupancies, storage racks over 8 feet and equipment anchorage. Fire protection plan checks and sprinkler fees are added where they apply, and work at Fisherman’s Wharf also needs Army Corps of Engineers and Coastal Commission approval and a pre-construction meeting.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning approvals. Architectural Review Committee approval (at least preliminary) or homeowners association approval, single-family review by Planning, and any use permit or variance come first. Remodels with exterior changes should start with a planner.
- Water. Projects needing more water must hold a valid Monterey Peninsula Water Management District water permit before the building permit issues, and the district needs a city water allocation first; the city signs the residential water release form for the applicant to send to the district.
- Sewer. A Monterey One Water sewer permit or waiver, plus a city sewer connection engineering fee when a sewer permit is issued.
- Asbestos. Applicants declare they have contacted the Monterey Bay Air Resources District (831-647-9411) about asbestos rules for renovation or demolition.
Monterey permit costs and fees
Building fees are set in the City of Monterey Master Fee Schedule for fiscal year 2026/2027, effective July 1, 2026, linked as the “Schedule of Fees and Fines” on the Permit Center page. Its Building Permits & Inspection Fees section prices minor trade permits at flat amounts and other work by project valuation; unlisted fees come from valuation or hourly estimates. Under Council Resolution 23-139 card payments carry a 2.9% merchant service fee; cash or check paid in person carries none.
| Item | Fee |
|---|---|
| Minor plumbing (water heater, sewer lateral), minor electrical (service panel) or minor mechanical (furnace) permit | $290.50 each |
| Generator: electric only or plumbing only / both together (Class B license required) | $536 / $962 |
| Residential solar PV under 10 kW (fee set by the state) | $450 |
| Residential swimming pool demolition or abandonment | $1,130 |
| Sewer lateral review | $241 |
| Residential property inspection report, single-family home | $458 |
| Missed inspection or work not ready; revision (minimum) | $242 |
| Hourly inspection or plan check / Building Official services | $185 / $299 |
| General plan fee | 15% of the building permit fee |
| Work done without a permit | Investigative fee equal to the cost of the permit |
| Driveway or sidewalk encroachment; street opening | $1,009 each |
Rather talk it over?
Call 1-855-478-4290 →Valuation tables. Plan check and the building permit each use a table of valuation bands: a base amount plus a set sum for each $1,000 above the band’s lower limit. From $100,000.01 to $500,000 the building permit is $3,813 plus $20.50 per $1,000 and plan check is $2,464 plus $14.50 per $1,000. The bands do not meet exactly at their limits, so ask the division to confirm a fee near a limit. Valuation may have to come from a licensed contractor’s estimate approved by the Building Official, and residential roofing is valued at no more than $25,000.
Worked example. A $200,000 addition: building permit $3,813 + (100 × $20.50) = $5,863; plan check $2,464 + (100 × $14.50) = $3,914; general plan fee 15% of $5,863 = $879.45; together $10,656.45 before outside charges. Planning fees in the same schedule include administrative minor architectural review at $701.50 and minor Architectural Review Committee review at $2,938.50.
| Item | What applies |
|---|---|
| School developer fees | Monterey Peninsula Unified School District, when added habitable area exceeds 500 square feet |
| TAMC regional impact fee | New houses, commercial buildings and changes of use; due at issuance |
| Sewer | Monterey One Water permit or waiver; city sewer connection engineering fee from a capacity calculation, due at issuance |
| Fire | Fire protection plan check and sprinkler fees |
| Stormwater | Stormwater review and inspection fee, or developer design review |
| Water | Water district permit where the project adds water use |
Because the city has no water credits to allocate, a project that adds bathrooms or kitchens depends on the credits already on the site; the district can explain retrofit credits and its Ordinance 98 second-bath rule (831-658-5601).
Trade permits and who may pull them
Electrical, plumbing and mechanical permits are building permits in the portal, and minor trade work can be issued over the counter using the over-the-counter electrical checklist where it applies. Only a building owner or a licensed contractor may take out a permit, and the division cautions owners to understand the risks of acting as owner-builder.
- Contractors need a state contractor’s license, a workers’ compensation certificate and a current City of Monterey business license before the permit issues.
- Business license: businesses with a fixed place of business in the city apply to Finance online or on the fillable form; the tax is based on estimated gross receipts and renews each July (831-646-3944).
- Sewer laterals: the sanitary sewer lateral inspection form must be completed by a licensed plumbing contractor, and since January 1, 2019 it is the only report the city accepts on the condition of a lateral, backwater valve and relief vent.
Rather not deal with the building department?
Get a free quote →How to apply for a Monterey building permit
Ask the water district how many credits run with the property, and consult Planning about exterior changes.
Complete architectural review, single-family review, a use permit or variance, or HOA approval where required.
Combine the drawings into one file of up to 100 MB, flattened, at least 300 dpi, landscape, bookmarked, with a 3 by 2 inch city stamp space on every sheet.
Answer the scope, use and valuation questions and upload the checklist for the project type.
Resubmit sheets in the same order and numbering as before.
Submit the water permit, sewer permit or waiver, school fee receipt and air district approval.
Contractors show their license, workers’ compensation and city business license.
Review, corrections and what causes delay
The division takes at least 15 business days to review smaller projects and 20 business days for larger ones, and plans typically come back in about 20 working days. Incomplete portal answers lead to missed reviews or wrong fees, so call the division before submitting if unsure. The most common outside hold-ups are the water district permit, which cannot be issued until the city approves a water allocation, and Monterey One Water’s sewer permit or waiver.
Inspections in Monterey
Call 831-646-3890 with the permit number, job address, inspection type, requested date and a contact name and phone. Requests received before 2 p.m. are scheduled for the next business day, and those after 4 p.m. may go to the day after; the division does not call to confirm. A missed inspection or work not ready costs $242.
- Someone must be on site, with the plans and job card left out for the inspector.
- A permit expires one year after issue or after the last inspection.
- A new connection to a city sewer main is coordinated with the Streets Division, which hydro-jets the line, and the connection must be inspected before backfilling.
Before close of escrow or any transfer of a single-family home or apartment building, the owner must obtain a residential property inspection: an exterior inspection and report by Building Permit and Inspection Services ($458 for a single-family home). Condominiums are exempt. RPI appointments are booked by 4 p.m. the business day before, by emailing the application or calling 831-646-3890.
Want this handled start to finish?
Get a free quote →California building code in Monterey
Monterey’s adopted codes are set in its City Code, published at monterey.municipal.codes; the division’s adopted-codes list (last updated for the 2022 cycle) also includes the California Historic Building Code and the International Property Maintenance Code except section 111. The downtown is a National Historic Landmark District, and the city’s most important historic buildings carry H-1 or H-2 zoning under Chapter 38, Article 15. FEMA’s Community Status Book lists Monterey (community 060200) as participating in the National Flood Insurance Program, with a current flood map dated June 21, 2017.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Monterey building permit FAQs
Who issues building permits in Monterey?
The city’s Building and Safety Division at 580 Pacific Street, Room 4, for property inside the City of Monterey; unincorporated areas go to Monterey County.
How do I apply?
Online at mymontereyportal.org or in the My Monterey Gov app, or by emailing a complete application; the division is paperless and accepts PDF plans only.
Can I add a bathroom?
Only with enough water credits: a water district permit is needed before the building permit, though the district’s Ordinance 98 lets a single-family house on its own parcel get the credits for a second full bath (two full baths at most, including the master bath) without a city allocation.
How big can an ADU be?
Up to 850 square feet for a studio or one bedroom and 1,000 square feet for two or more bedrooms, 16 feet tall, with a 4-foot side and rear setback.
How much is a water heater or panel permit?
The FY 2026/2027 schedule charges $290.50 for a minor plumbing permit such as a water heater or sewer lateral and the same for a minor electrical permit such as a service panel replacement.
Do I need an inspection to sell my house?
Yes. A residential property inspection report is required before close of escrow on single-family homes and apartment buildings; condominiums are exempt.
Monterey permit search and official resources
Permits filed through the portal since January 7, 2026 can be tracked there. Other city records are requested from the City Clerk through the public records request listed on the city’s Permit Center page.
Inspections are where schedules slip.
Get a free quote →- Monterey Building and Safety Services
- My Monterey online permit portal
- Plan submittal requirements and outside agency fees
- Building permit frequent questions
- ADUs and JADUs
- Residential property and construction inspections
- Planning Office
- How to apply for a planning permit
- Water availability
- Historic preservation
- Permit Center
- Starting your business and business licenses
- California Building Standards Code (Title 24)
- FEMA Community Status Book, California
Simplify Monterey permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Monterey sooner?
Let Alliance prepare, file, and track your Monterey permits while your crew stays on the job.
More California permitting guides
Monterey County
Read guide →Pacific Grove
Read guide →Salinas
Read guide →Monterey Park Building Permit Guide
Read guide →Moorpark Building Permit Guide
Read guide →Moraga Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Monterey permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.