To get a building permit in Washougal, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Washougal’s Building Division takes permit applications by email or at the Permit Center on 39th Street and issues building, mechanical and plumbing permits; electrical permits come from Labor and Industries.

Authority: Washougal Building DivisionCode: 2021 state codes (WMC 15.04)Phone: 360-835-8501
Authority
Building DivisionPermit Center, 211 39th Street
Counter
Monday to Thursday8 a.m. to 5 p.m.
Plan review
65% of permit feeWMC 3.97.010
Electrical
Labor and IndustriesNot a City permit

The City of Washougal’s Building Division, part of Community Development, receives building permit applications, reviews plans against the Washington State Building Code, routes them to planning, engineering and fire reviewers and inspects the work. Over-the-counter permits can be emailed to the permitting address, and all others are dropped off at the Washougal Permit Center. Electrical circuits and service are permitted by the state Department of Labor and Industries (L&I) through its Vancouver office (360-896-2300). Building fees are set in Washougal Municipal Code (WMC) chapter 3.97, with plan review at 65% of the permit fee.

The Permit Center is at 211 39th Street and takes drop-off applications Monday to Thursday from 8 a.m. to 5 p.m. The City’s main number is 360-835-8501; the building permit technician is at extension 611, and the Building Division’s pages list extension 698. Washougal had 18,028 residents in the Census estimate for 2025, and Clark County permits the unincorporated land outside the city.

What requires a building permit in Washougal?

WMC 15.04.020 adopts the state codes with local amendments. It cuts the building code’s shed exemption from 200 to 120 sq ft and adds freestanding decks less than 30 inches above grade to the residential code’s exempt list. The City’s “Permits Required & Not Required” handout gives the everyday examples.

Permit required

  • Carports, decks, garage conversions, accessory apartments, interior remodels and home-business conversions
  • Replacing or altering exterior doors, windows and skylights, and residential re-roofs
  • Fireplaces, wood stoves and inserts; furnaces, boilers, exhaust fans and other mechanical equipment; gas piping
  • Water heaters, new hose bibs, irrigation systems, spas and saunas
  • Pools and swim spas 2 feet deep, or above-ground prefabricated pools over 5,000 gallons
  • Retaining walls over 4 feet or holding back a surcharge, grading of 50 cubic yards or more, and dock repairs or additions

No permit (City handout)

  • One-story sheds and playhouses of up to 120 sq ft
  • Retaining walls or rockeries up to 4 feet with no surcharge
  • Freestanding decks less than 30 inches above grade (WMC 15.04.020)
  • Sidewalks, driveways and finish work such as painting, tiling, carpet and cabinets
  • Prefabricated pools under 24 inches deep, swings and playground equipment, and window awnings up to 54 inches

Two handout items differ from the adopted code. The 120 sq ft shed limit in WMC 15.04.020 amends the building code; the residential code adopted in the same section is not amended for sheds, so ask the Building Division before building a residential shed between 120 and 200 sq ft. And the handout and the City’s fence regulations exempt fences up to 6 feet, while the adopted codes exempt fences up to 7 feet; under the City’s fence rules, fences may be no taller than 6 feet in side and rear yards and 4 feet in the front setback, which on a corner lot includes both street sides.

Short on time to read all of this?

Get a free quote →

What the city decides and what the state holds

The City’s codes page says that permits vested after March 15, 2024 fall under the 2021 Washington State Building Code with Washougal’s amendments. WMC 15.04.020 adds the flood-resistant construction, sign and grading appendices of the building code, the pool, patio cover, grading and radon appendices of the residential code, emergency lighting for accessible restrooms and dressing rooms, local design values (25 psf roof snow load, 105 mph wind, seismic category D-1, 12-inch frost depth) and fees set in WMC 3.97. The building official is designated by the director of community development.

Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington

Washougal building department: who handles permitting

The Building Division confirms that contractors are properly licensed, keeps construction records, receives applications and reviews plans, and routes them to Planning, Engineering or the Fire Department when the project calls for it; the City tells applicants about those other reviews and permits when they apply.

Washougal permitting contacts
DetailInformation
OfficeWashougal Permit Center, 211 39th Street, Washougal, WA 98671
Drop-off hoursMonday to Thursday, 8 a.m. to 5 p.m.
Phone360-835-8501; building permit technician ext. 611; ext. 698 listed on the Building Division pages
Email applicationspermitting@cityofwashougal.us (over-the-counter permits and completed applications)
Inspection requestsBy phone or by email to BuildingInspectionLine@cityofwashougal.us
Electrical permitsWashington Department of Labor and Industries
Septic systemsClark County Public Health

Permit types

Residential permits

The City’s forms page carries the 2023 residential building permit application and separate forms for plumbing and mechanical work, demolition, irrigation, swimming pools, signs, occupancy, permit transfers and contractor changes, plus a heating requirement affidavit, energy code compliance certificates and a request form to withdraw, extend or reactivate an application that has not been issued. Mechanical and plumbing application lists explain what each trade permit needs, and the Building Division posts a single-family inspection requirements page and a list of ten ways to make the permit process go faster.

Submittals go in as two sets of documents or as pre-approved electronic plan sets, drawn to scale and clear enough to show the location, nature and extent of the work; plans must include structural observation programs and other data where required. Once approved, plans may not be changed without the Building Division’s authorization.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial and multifamily projects use their own application and a combined commercial plumbing and mechanical application, and businesses moving into an existing space file an occupancy request. WMC 15.04.100 requires a Washington-licensed design professional for any building with five or more dwelling units and for any building over 4,000 sq ft. The City’s tips page points out that a space that already has a certificate of occupancy for the same use is often quicker to permit, and that backflow assemblies and kitchen exhaust hoods are “big ticket” items to show on the plans from the start.

What comes before the building permit

Zoning, home occupation, parking, business licensing and right-of-way requirements are checked by Planning and Public Works and are best settled before design. Shoreline areas fall under the City’s Shoreline Master Program, and mapped flood areas bring the building code’s flood-resistant construction rules. Grading of 50 cubic yards or more needs a permit, and new construction connecting to City water and sewer pays connection charges. Stormwater general permits from the state Department of Ecology can apply to construction sites, and the City posts the notice of intent forms. A septic system is permitted by Clark County Public Health.

Washougal permit costs and fees

Building fees are codified in WMC chapter 3.97 (Ordinance 1604, 2008), which the City’s building page links as its permit fee schedule. Residential valuations come from the current Building Safety Journal tables, and other occupancies use the applicant’s valuation, with the final figure set by the building official.

Rather talk it over?

Call 1-855-478-4290 →
Washougal building fees (WMC chapter 3.97)
ItemFee or rule
$1 to $500 of value$23.50
$501 to $2,000$23.50 for the first $500, plus $3.05 per added $100 or part
$2,001 to $25,000$69.25 for the first $2,000, plus $14 per added $1,000 or part
$25,001 to $50,000$391.25 for the first $25,000, plus $10.10 per added $1,000 or part
$50,001 to $100,000$643.75 for the first $50,000, plus $7 per added $1,000 or part
$100,001 to $500,000$993.75 for the first $100,000, plus $5.60 per added $1,000 or part
$500,001 to $1,000,000$3,233.75 for the first $500,000, plus $4.75 per added $1,000 or part
Over $1,000,000$5,608.75 for the first $1,000,000, plus $3.15 per added $1,000 or part
Building plan review65% of the building permit fee; mechanical plan review 25%
Residential re-roof$40 standard 3-tab or architectural, $60 dimensional shingle, $100 shake, $125 tile or concrete
Plumbing permit$25.40 to issue, plus $8.89 per fixture or water heater; building sewer $19.05; private sewage disposal system $50.80
Mechanical permit$23.50 to issue; furnace up to 100,000 Btu/h $14.80
Demolition$25 residential; $50 per commercial structure
Same-as plan review; occupancy inspection$200; $50
Extra inspections, re-inspections, added plan review$47 an hour; additional trip fee $50

WMC 3.97.050 still lists the “State Building Code Fee – per single-family residence – in accordance with RCW 19.27.085” at $4.50, plus $2.00 for each multifamily unit after the first. RCW 19.27.085 now sets the fee at $6.50 for each residential building permit and $25 for each commercial building permit, so expect the statutory amount.

Worked example. A house valued at $350,000 falls in the $100,001 to $500,000 band: $993.75 plus 250 × $5.60 ($1,400) gives a building permit fee of $2,393.75, and plan review at 65% adds $1,555.94, before the state fee, plumbing and mechanical permits and the L&I electrical permit.

A new single-family home also pays impact and connection charges. The City’s sheet updated January 2, 2025 lists a park impact fee of $6,847.85, a transportation impact fee of $8,274.54 (9.43 trips at $877.47), a fire impact fee of $0.68 per sq ft, a school fee of $6,650 in the Camas School District and $0 in the Washougal School District (plus a 1% administration fee), and water, sewer and stormwater charges of $4,418, $7,145 and $478 for a 3/4-inch meter. An accessory dwelling unit pays 35% of the single-family rate. The fees rest on WMC chapters 15.45 (school), 15.62 (park), 15.64 (transportation) and 15.65 (fire).

Rather not deal with the building department?

Get a free quote →

Grading permits under WMC 3.97.040 cost $15 for 50 cubic yards or less, $22.50 for 51 to 100 cubic yards and $22.50 plus $10.50 per added 100 cubic yards up to 1,000; grading plan review is free up to 50 cubic yards and $23.50 for 51 to 100. Plumbing plan review, where plans are required, is 65% of the plumbing permit fee.

Trade permits and who may pull them

Plumbing and mechanical permits are City permits; the City’s required list puts water heaters, new hose bibs, irrigation systems, gas piping, furnaces, boilers, exhaust fans and wood stoves under permit. Electrical circuits and service are not: Washougal is not on L&I’s list of cities with their own electrical program, and its handout sends electrical work to L&I. Registration and trade-certificate rules for anyone you hire are statewide; see our Washington licensing section.

Who issues what

  • Building, plumbing, mechanical, pools and demolition: Washougal Building Division
  • Fire code matters: the Fire Department, through routing
  • Electrical permits and inspections: L&I
  • Septic systems: Clark County Public Health

Permits and owners

  • Under WMC 15.04.100 a City permit belongs to the property owner, and an applicant who is not the owner acts as the owner’s agent
  • The Building Division is responsible for making sure contractors are properly licensed

How to apply for a Washougal building permit

1. Ask about your space

Describe what you want to do; size and use decide exits, bathrooms and sprinklers, and other departments may need to look first.

2. Pick the right form

Download the residential or commercial application and any trade, demolition or pool form from the forms page.

3. Draw the plans to scale

Show all dimensions and room uses, and every water-using fixture and backflow assembly on commercial jobs.

4. Submit

Email over-the-counter permits to the permitting address; drop off all others at the Permit Center, Monday to Thursday.

5. Answer review and pay

Respond to any other department reviews, then pay the permit fee; plan review is paid when plans are submitted.

6. Get the L&I electrical permit

Buy the electrical permit from L&I before wiring begins.

Review, corrections and what causes delay

An application expires if no permit is issued within 180 days of application, and the Building Division may extend it once, for up to 180 days, on a written request showing circumstances beyond the applicant’s control; after that the plans must be resubmitted with a new plan review fee. Incomplete or changed plans are billed for extra review at $47 an hour.

Want this handled start to finish?

Get a free quote →

Inspections in Washougal

Inspection requests must be called in or received by 5 p.m. on the working day before the inspection; anything later is scheduled for the following workday. Requests can be phoned to the recorded line, where the caller must leave complete information, or emailed to the building inspection request address. The City no longer takes morning or afternoon requests, except for concrete pours, and a pour that is not ready at the requested time can be charged the $50 trip fee.

A permit becomes void if work does not start within 180 days, or stops for 180 days or more, even if the work is finished. Work stopped for less than a year can be restarted with a new permit at half the fee if the plans have not changed. A refund of up to 80% of the permit fee is possible when no work has been done, on a written request within 180 days of payment.

Washougal permit search and official resources

The Building Division keeps the City’s construction records; permit histories are requested through the City. Washougal joined the National Flood Insurance Program as community 530028; its current FEMA map is dated January 19, 2018, and in mapped flood areas the building code’s flood-resistant construction appendix applies.

Inspections are where schedules slip.

Get a free quote →

Washougal building permit FAQ

Who issues building permits in Washougal?

The Building Division of Community Development, through the Permit Center at 211 39th Street (360-835-8501). Electrical permits come from L&I.

Can I apply by email?

Yes for over-the-counter permits, sent to the permitting address; other permits are dropped off at the Permit Center, Monday to Thursday, 8 a.m. to 5 p.m.

Do I need a permit to re-roof my house?

Yes. A residential re-roof costs $40 to $125 depending on the roofing, under WMC 3.97.050.

Do I need a permit for a shed or fence?

The City’s handout exempts sheds up to 120 sq ft and fences up to 6 feet; larger sheds and taller fences need a permit.

What impact fees does a new house pay?

Under the January 2025 sheet: park $6,847.85, transportation $8,274.54, fire $0.68 per sq ft, and a Camas School District fee of $6,650 where it applies.

How do I request an inspection?

Call or email the request by 5 p.m. the day before; morning or afternoon slots cannot be requested except for concrete pours.

Simplify Washougal permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Washougal sooner?

Let Alliance prepare, file, and track your Washougal permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Washougal permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.