The City of Battle Ground’s Building Division, part of the Community Development Department, issues permits for residential and commercial construction and alterations, covering building, plumbing, mechanical and fire systems, and applications go in through the City’s Customer Self-Service (CSS) portal. Electrical permits are bought from the state Department of Labor and Industries (L&I), whose Clark County office is at 312 SE Stonemill Drive in Vancouver. Under the 2026 fee schedule, plan review is 65% of the building permit fee and is due when you submit.
The permit counter is at Battle Ground City Hall, 109 SW 1st Street, Suite 127, open Monday, Wednesday and Friday from 9 a.m. to 5 p.m. and Tuesday and Thursday from 8 a.m. to 1 p.m.; Community Development staff answer 360-342-5040. Battle Ground had 23,513 residents in the Census estimate for 2025. Clark County permits the unincorporated land around the city.
What requires a building permit in Battle Ground?
Battle Ground Municipal Code (BGMC) 15.104.010 adopts the current state building codes and, as amended through Ordinance 26-10 of May 18, 2026, adds its own list of exempt work for one- and two-family homes, unless a land use approval is needed under BGMC Titles 16 and 17.
Permit required
- New houses, duplexes and accessory dwelling units, additions, alterations and remodels
- Garages, carports, covered patios, and decks more than 30 inches above grade
- Accessory buildings over 200 sq ft
- Converting a basement, attic or garage into living space, or any change to a building’s footprint
- Water heaters, toilets and sinks; furnaces, air conditioners and ductwork
- Retaining walls over 4 feet, and grading of more than 50 cubic yards
- Fences 42 inches or higher, walls 48 inches or higher, and retaining walls holding back a surcharge (a planning fence permit)
No building permit
- A first or second layer of roof covering on a one- or two-family home, with no structural repair and no new roof sheathing (BGMC 15.104.010)
- Replacement windows and doors that fit existing framed openings and need no fire rating
- Replacement siding with no structural or wall sheathing repair and no fire-resistive requirement
- Sidewalks, decks, platforms and driveways up to 30 inches above grade, not over a basement or story and not part of an accessible route
- Accessory buildings of 200 sq ft or less (the City’s handout adds height, setback and location limits)
The City’s accessory building handout says no permit is needed for a building of 200 sq ft or less that is at most 12 feet tall, sits at least 3 feet from side and rear lines and other buildings, and stands behind the front of the house. The 2026 fee schedule lists a $123 permit for re-roofing or residing a house; under the code that permit is needed only when the work falls outside the exemption, for example where structural repair or new sheathing is involved.
Short on time to read all of this?
Get a free quote →What the city decides and what the state holds
BGMC 15.104.010 adopts the building, residential, fire, mechanical, fuel gas, existing building, property maintenance and swimming pool codes and the state energy code in their current state-adopted editions, with the radon, patio cover and existing building appendices of the residential code. The City’s own changes are the roof, window and siding exemption, the deck and platform wording, a rule that bathroom exhaust fans may not connect to a whole-house ventilation system, a rule letting a tenant improvement use the shell building’s code if applied for within one code cycle, and its own certificate of occupancy procedure. The plumbing code’s chapters 12 and 15 and its building sewer provisions are not adopted.
Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington
Battle Ground building department: who handles permitting
Community Development combines the Planning Division, which administers zoning and land use, and the Building Division, which handles permit processing, plan review and inspections. Plan reviews are done by ICC-certified code professionals, and the City has a Fire Marshal’s Office for fire code matters.
| Detail | Information |
|---|---|
| Office | Community Development, Battle Ground City Hall, 109 SW 1st Street, Suite 127, Battle Ground, WA 98604 |
| Counter hours | Monday, Wednesday and Friday 9 a.m. to 5 p.m.; Tuesday and Thursday 8 a.m. to 1 p.m. |
| Phone and email | 360-342-5040; comdev.info@cityofbg.org (portal access and permit questions) |
| Online services | Customer Self-Service (CSS) portal: applications, uploads, fees, inspections |
| Electrical permits | Washington Department of Labor and Industries |
| Septic systems | Clark County Public Health |
Permit types
Residential permits
The City posts separate applications and submittal checklists for residential building, mechanical and plumbing permits, manufactured home placement, adult family homes, pools and demolition, and a system development charge worksheet for new homes. Applicants upload one digital copy of the plans to the portal and, where required, drop off or mail one paper copy. Setbacks are checked on a plot plan before the permit is issued.
Under the residential code, engineering is required when a design falls outside the prescriptive rules. The City’s examples include insulated concrete form and structural insulated panel walls, dormers and second-floor additions, moving or removing walls, beams or headers, decks more than 9 feet from grade to the underside of the beam, decks that carry a hot tub or cantilever, second-story decks and retaining walls over 4 feet, and a geotechnical report may be needed depending on the soils.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial, multifamily and change of use projects share one application with its own checklist, and commercial mechanical and plumbing work have separate applications. A commercial re-roof is priced on its valuation. The City can send plan review and inspections to its building services consultant at the consultant’s cost plus 10% when the applicant and City agree, and structural or specialized review by a consultant is billed at the consultant’s invoiced cost.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
Planning reviews come first where they apply: residential plot plan review ($70), site plan review ($619 for a Type I review), fence permits ($49), and approvals under the Shoreline Master Program and critical areas rules. Fences forward of the front face of the house may be no taller than 42 inches and those behind it no taller than 72 inches; in critical area buffers they must be open materials such as split rail. Work in a street needs a right-of-way permit. A new home on City water and sewer pays system development charges of $4,150 for a 5/8-inch water meter and $15,701 per sewer equivalent residential unit inside the city, and a lot on septic needs a permit from Clark County Public Health.
Battle Ground permit costs and fees
The City’s 2026 Fee Schedule, Resolution 25-12, was approved 7-0 by the City Council on November 17, 2025, after a public hearing on November 3, and took effect on January 1, 2026. Building permits are priced on valuation, and the schedule lists the state fee as “State Building Fee - Residential $6.50” and “State Building Fee - Commercial $25.00”. Note that the schedule lists $75 for $1 to $500 of value but starts the next band at $73 for the first $500.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee or rule |
|---|---|
| $1 to $500 of value | $75 |
| $501 to $2,000 | $73 for the first $500, plus $4.88 per added $100 or part |
| $2,001 to $25,000 | $134 for the first $2,000, plus $19.98 per added $1,000 or part |
| $25,001 to $50,000 | $548 for the first $25,000, plus $15.22 per added $1,000 or part |
| $50,001 to $100,000 | $879 for the first $50,000, plus $11.57 per added $1,000 or part |
| $100,001 to $500,000 | $1,325 for the first $100,000, plus $9.09 per added $1,000 or part |
| $500,001 to $1,000,000 | $4,221 for the first $500,000, plus $7.94 per added $1,000 or part |
| Over $1,000,000 | $7,287 for the first $1,000,000, plus $4.88 per added $1,000 or part |
| Building plan review | 65% of the building permit fee, due at submittal |
| New single-family home trade permits | Mechanical $0.12 and plumbing $0.16 per finished sq ft |
| Mechanical or plumbing permit issuance | $76 each, plus unit fees |
| Re-roofing or residing a house | $123 |
| Re-inspection; added plan review | $75 an hour, one-hour minimum |
| Temporary certificate of occupancy | $250; extension $500 |
Worked example. A new house valued at $300,000 falls in the $100,001 to $500,000 band: $1,325 plus 200 × $9.09 ($1,818) gives a building permit fee of $3,143. Plan review at 65%, paid when the plans are submitted, is $2,042.95, and the residential state fee adds $6.50. A 2,000 sq ft finished house would add $240 for its mechanical permit and $320 for its plumbing permit at the per-square-foot rates.
Impact fees for a single-family home in 2026 are a traffic fee of $3,943.44, a park fee of $4,538.31, a fire fee of $1,018.78 and a school fee of $10,760 in the Battle Ground School District or $7,790 in the Hockinson School District. The City offers a deferral program for system development charges and impact fees.
Rather not deal with the building department?
Get a free quote →Trade permits and who may pull them
Mechanical and plumbing permits are City permits. On a new single-family home they are priced by finished square footage; other jobs pay a $76 issuance fee plus unit fees, and mechanical plan check is one hour ($75) or 65% of the fee. Battle Ground is not on L&I’s list of cities with their own electrical program, so electrical permits and inspections are L&I’s, and the City asks that final inspections not be scheduled until L&I has signed off the electrical work. Contractor registration and electrician or plumber certificates follow state rules, gathered in our Washington licensing notes.
Who issues what
- Building, plumbing, mechanical and fire systems: City of Battle Ground Building Division
- Fences, plot plans and land use: Planning Division
- Electrical permits and inspections: L&I
- Septic systems: Clark County Public Health
Applying for someone else
- The accessory building handout asks for the owner’s signature on the application
- Anyone applying for a fence on a homeowner’s behalf files an owner authorization form
- Anyone scheduling inspections needs a portal account and must be added to the permit
How to apply for a Battle Ground building permit
Confirm setbacks and any critical areas or shoreline rules for the lot with the Planning Division.
Use the City’s application and submittal checklist for your project type, with a plot plan and engineering where required.
Upload one digital copy of the plans to the Customer Self-Service portal; the City’s CSS user guide explains each screen.
When the application is counter complete it is created in the permit system, the plan review fee is paid, and the status changes to “In Review”.
Respond to each comment letter with complete corrections; the reviewer waits until you do.
When all reviews are approved the permit moves to pre-issue status; pay the remaining fees and collect the permit and inspection card.
Review, corrections and what causes delay
Plans may be reviewed for planning and zoning, structural and building, fire and engineering. After a comment letter goes out, the reviewer takes no further action until you respond, so complete and timely answers shorten the process; another letter follows if the response is incomplete. Revisions to approved plans are billed at $75 an hour.
Want this handled start to finish?
Get a free quote →Inspections in Battle Ground
Inspections are scheduled only through the CSS portal, 24 hours a day; the City no longer takes inspection requests by phone. Requests made by midnight are scheduled for the next day, and inspections run Monday to Friday, except holidays, between 8 a.m. and 4 p.m.; morning or afternoon requests cannot be accommodated. To schedule, you need a portal account and must email the City to be added to the permit. To cancel, call 360-342-5040.
When you collect the permit you get an inspection card listing every required inspection. No building may be occupied until the building official issues a certificate of occupancy. A temporary certificate ($250) can be granted once accessibility, fire and life safety items are complete; it lasts 60 days and can be extended once for 60 days ($500). Work started without a permit can draw an investigation fee as large as the permit and plan review fees, and re-inspections cost at least one hour at $75.
Battle Ground permit search and official resources
Permit status is visible in the Customer Self-Service portal, and older records come through the City’s public records process. FEMA lists Battle Ground as participating community 530025 in the National Flood Insurance Program, with a current flood map dated September 5, 2012.
- Battle Ground Customer Self-Service (CSS) portal
- Building Division
- Permit applications and submittal checklists
- Residential building information
- Inspection requests
- 2026 Fee Schedule, Resolution 25-12 (PDF)
- Residential fences handout (PDF)
- Residential accessory buildings handout (PDF)
- BGMC chapter 15.104, building code
- Shoreline Master Program
- Clark County Public Health septic system forms
- L&I list of cities with their own electrical permits
Inspections are where schedules slip.
Get a free quote →Battle Ground building permit FAQ
Who issues building permits in Battle Ground?
The Building Division of Community Development at City Hall, 109 SW 1st Street, Suite 127 (360-342-5040), through the CSS portal. Electrical permits come from L&I.
Do I need a permit to re-roof my house?
Not for a first or second layer of roofing with no structural repair or new sheathing, under BGMC 15.104.010. Work beyond that needs a permit, listed at $123 in 2026.
Do I need a permit for a fence?
Yes for a fence 42 inches or higher ($49). Fences in front of the house are limited to 42 inches and those behind it to 72 inches.
Do I need a permit for a shed?
Not for one of 200 sq ft or less; the City’s handout adds a 12-foot height limit, 3-foot setbacks and a location behind the front of the house.
How much is a building permit for a new house?
For a $300,000 house, $3,143 plus $2,042.95 plan review and the $6.50 state fee, before trade permits and impact fees.
What impact fees does a new house pay?
In 2026: traffic $3,943.44, park $4,538.31, fire $1,018.78 and a school fee of $10,760 (Battle Ground School District) or $7,790 (Hockinson School District), with a deferral program available.
Can I schedule an inspection by phone?
No. Inspections are requested only in the CSS portal, by midnight for the next day.
Simplify Battle Ground permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Battle Ground sooner?
Let Alliance prepare, file, and track your Battle Ground permits while your crew stays on the job.
More Washington permitting guides
Clark County
Read guide →Camas
Read guide →Ridgefield
Read guide →Bellevue Building Permit Guide
Read guide →Bellingham Building Permit Guide
Read guide →Benton County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Battle Ground permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.