Shoreline sits between Seattle and Snohomish County and publishes more about its own review performance than almost any city in the band. In a state with no statutory review deadline, a city that commits to a number and explains how the number is counted is genuinely unusual.
Planning and Community Development issues building, tree, clearing and grading and land use permits, with applications submitted through the city’s electronic permitting portal. The city reports annually to the state on permit review timelines for a subset of permit types.
This guide covers work inside the Shoreline city limits. Unincorporated King County is permitted by the county, and Seattle to the south runs its own department and its own codes.
Sixty-five, one hundred, one hundred and seventy — and the clock pauses. Shoreline publishes review times of sixty-five calendar days for administrative decisions including building permits and tree removals, one hundred for administrative decisions requiring public notice, and one hundred and seventy for decisions requiring a public hearing. The clock starts only after the application is determined complete, and pauses whenever additional information or corrections are requested, resuming when you provide them. Your response time is your own delay.
What requires a building permit in Shoreline?
Washington has a mandatory statewide building code. The codes enumerated in chapter 19.27 RCW, the State Building Code Act, are adopted and amended by the State Building Code Council within the Department of Enterprise Services, and they are required in all cities and counties — local government administers and enforces them rather than deciding whether to have them. A city or county may amend the state code, but it amends upward from a floor it cannot opt out of. So the question in Shoreline is not whether a code applies, but which edition is in force and what Shoreline Planning and Community Development has added to it.
Permit required
- New buildings, additions, alterations and change of occupancy or use
- Structural alterations, load-bearing changes, foundations, decks and retaining walls
- Plumbing work under the Uniform Plumbing Code as adopted by the state
- Mechanical and HVAC change-outs, fuel gas work and ventilation
- Work affecting the Washington State Energy Code envelope or systems
- Re-roofing above the exempt scope, demolition, and work in critical areas
Often exempt
- Ordinary repairs and maintenance replacing materials in kind
- Small accessory structures below the code threshold, where zoning allows
- Painting, flooring, cabinetry and other finish work
- Like-for-like fixture swaps with no alteration to piping
Local amendments, fee schedules and exempt thresholds differ from one jurisdiction to the next, so an exempt list from a neighbouring city is not reliable. An exemption from a building permit is never an exemption from zoning, critical areas review, the energy code or a trade permit. Confirm scope with Shoreline Planning and Community Development before work starts.
Your electrical permit almost certainly does not come from the city. For most of Washington, electrical permits are issued and electrical inspections are carried out by the Electrical Program at the Department of Labour and Industries under chapter 296-46B WAC — not by the local building department. A minority of cities run their own electrical programme instead. Establish which applies to the parcel before you assume a single counter handles everything, because the electrical track runs on its own timetable and its own inspector.
The statewide features that catch projects everywhere
Four things shape a Washington filing more than the model code does. First, the edition is set by the state on a three-year cycle and adopted in two groups over a two-year timeline, so the building, residential, mechanical and plumbing parts do not all arrive on the same day. Second, plumbing runs on the Uniform Plumbing Code as adopted by the state, not the International Plumbing Code that most of the country uses. Third, the Washington State Energy Code is its own code under chapter 19.27A RCW rather than the international energy code, and it is among the most demanding in the country. Fourth, growth management and critical areas regulation reach ordinary residential work near wetlands, steep slopes, streams and shorelines far more often than owners expect. Cascadia subduction zone seismic detailing applies statewide. Trees carry a per-tree charge as well as a permit: the city notes a per tree fee for removing significant trees of twenty-four inches diameter at breast height and greater, referring applicants to the fee schedule for current rates — so on a wooded lot the tree cost scales with the count rather than sitting as a single line
Who handles permitting in Shoreline?
Planning and Community Development issues building, tree removal, clearing and grading and land use permits, publishes annual review timeline performance, and staffs a counter with reduced hours midweek.
| Detail | Information |
|---|---|
| Department | City of Shoreline Planning and Community Development |
| Address | 17500 Midvale Avenue North, Shoreline, WA 98133 |
| Phone | (206) 801-2500 |
| pcd@shorelinewa.gov | |
| Counter hours | Monday, Tuesday and Friday 8:00 a.m. to 5:00 p.m.; Wednesday and Thursday 1:00 p.m. to 5:00 p.m. |
| Portal | Electronic permitting portal; applications must be submitted electronically |
| Tree permit triggers | Over twenty-four inches diameter, in the right of way, or near a stream, wetland or steep slope |
| Clock behaviour | Starts on completeness, pauses on corrections |
Tree permits are triggered three ways rather than one. A permit is required for removal of trees greater than twenty-four inches diameter at breast height; for removal of trees in the rights of way, which extend beyond the edge of the paved road; and for trees of any size on or near a stream, wetland or steep slope. Removal of significant trees without a permit can result in penalties and code enforcement action.
The submittal standards are strict about file quality. Applications for tree permits must be submitted electronically, all forms and plans must be in portable document format, plans must be printed or plotted to that format rather than scanned from an image, must be plotted to scale with a graphic scale bar, and must be flattened and unlocked to allow mark-up, with a blank space left for the city’s stamp. Incomplete submittals and documents not meeting those standards will not be accepted for review.
Permit types
Residential permits
Residential work — new homes, interior remodels, additions and demolitions — runs through the same portal as tree work. Some projects qualify for a permit exemption and can begin without a permit, but the city is explicit that exemptions do not apply to properties with environmentally sensitive or critical areas including steep slopes, wetlands, streams, beaches and lakes.
How Washington contractor credentials work
Washington registers contractors rather than licensing them. Under chapter 18.27 RCW every contractor must register with the Department of Labour and Industries, file a continuous surety bond — thirty thousand dollars for a general contractor, fifteen thousand for a specialty contractor — and keep liability insurance on file. Registration runs for two years and carries no continuing education requirement at the base level. Crucially, registration is not a competence test and it does not authorise trade work: electrical work requires certification under chapter 19.28 RCW and plumbing under chapter 18.106 RCW, each with its own examination and its own programme office.
A general registration does not let anyone touch the wiring or the pipes. A registered general contractor must subcontract electrical and plumbing work to appropriately certified trades, and an electrical contractor licence additionally requires at least one certified electrician on staff. Verify the registration is active and the bond and insurance current with Shoreline Planning and Community Development and with the department, because registration lapses are common and an expired registration invalidates the credential the permit relies on.
Commercial permits
Clearing and grading permits cover work meeting the municipal code thresholds, such as grading in or near critical areas, changing the existing grade by four feet or more, or replacing impervious surfaces above a defined size. Where trees are being removed without any grading, the tree removal permit is the correct application unless six or more trees are involved.
Registrations, trade certifications and design professionals
Three credential layers appear on Washington projects: the state contractor registration under chapter 18.27 RCW, which nearly everyone doing the work needs; separate state trade certification for electricians and plumbers, each examined and administered by its own programme; and, on commercial and larger residential work, drawings stamped by a Washington-licensed architect or professional engineer. Confirm what Shoreline Planning and Community Development requires for the specific building before filing.
Shoreline permit costs and fees
Shoreline fees follow the published schedule, with a per tree fee for removing significant trees of twenty-four inches diameter and greater charged in addition to the permit fee itself.
| Fee component | How it works |
|---|---|
| Building permit | Set by the local jurisdiction, usually on project valuation; the state sets the code, not the fee |
| Plan review | A percentage of the permit fee or a flat charge, set locally |
| Plumbing and mechanical | Separate local permits under the adopted plumbing and mechanical codes |
| Electrical | Usually a state permit fee through the Labour and Industries Electrical Program, not a city fee |
| Energy code | Compliance documentation for the Washington State Energy Code, and review time for it |
| Critical areas and land use | Separate review and fees where wetlands, slopes, streams or shorelines are involved |
Washington sets the code statewide but leaves the fee schedule local, so two jurisdictions on the same edition can price the same project very differently. The electrical fee is the one that most often surprises people, because on most projects it is paid to the state rather than to the city. Ask Shoreline Planning and Community Development for the schedule in force on your filing date, and confirm the electrical route separately.
Need a real number for a specific Shoreline project? Send us the scope, address and valuation and we will identify the edition in force, the local amendments, the electrical route and the fee categories that will apply.
Trade permits and who may pull them
Trade permits are separate from the building permit and, in Washington, are not all issued by the same body. Plumbing and mechanical permits come from the local jurisdiction under the codes the state has adopted. Electrical permits come from the Electrical Program at the Department of Labour and Industries, unless this jurisdiction runs its own. That split is the single most common source of confusion on a Washington project.
Your electrical permit almost certainly does not come from the city. For most of Washington, electrical permits are issued and electrical inspections are carried out by the Electrical Program at the Department of Labour and Industries under chapter 296-46B WAC — not by the local building department. A minority of cities run their own electrical programme instead. Establish which applies to the parcel before you assume a single counter handles everything, because the electrical track runs on its own timetable and its own inspector.
- Electrical work follows chapter 19.28 RCW and the state electrical rules at chapter 296-46B WAC, performed by a certified electrician working for a licensed electrical contractor.
- Plumbing work follows the Uniform Plumbing Code as adopted by the state, performed by a plumber certified under chapter 18.106 RCW.
- Mechanical and fuel gas work follows the state mechanical and fuel gas provisions, permitted locally.
Permit required
- Service installations, panel upgrades, new circuits, solar PV and EV chargers
- New plumbing, repipes, water heater change-outs, fixtures, backflow and gas piping
- HVAC installation and change-out, ductwork, venting and commercial kitchen exhaust
- Sprinkler, standpipe and fire alarm work on commercial and multi-family structures
Typically exempt
- Replacing a fixture, switch, receptacle or light with no alteration to wiring or piping
- Clearing a stoppage without replacing or rearranging concealed piping
- Filter, thermostat and routine component service
- Like-for-like appliance repair that does not alter the connection
How to apply for a Shoreline building permit
The review clock does not start until the application is determined complete, so completeness is the first milestone rather than submission.
The clock pauses when additional information or corrections are requested and resumes when you provide them.
Over twenty-four inches diameter, in the right of way, or any size on or near a stream, wetland or steep slope.
Tree removal without grading uses the tree permit unless six or more trees are involved; grading work uses clearing and grading.
Plotted to format rather than scanned, to scale with a scale bar, flattened and unlocked, with blank space for the stamp.
Exemptions do not apply to properties with environmentally sensitive or critical areas.
Review, corrections and what actually causes delay
In Washington the first cause of delay is the energy code, because the state code is its own instrument and more demanding than the international one most designers default to. After that comes critical areas review, which reaches ordinary residential work near wetlands, streams, steep slopes and shorelines and adds its own study and mitigation timeline. Then the electrical split, where a project waits on a city inspection that was never going to happen because the electrical permit sits with the state. Then edition confusion, because the state adopts in two groups and the parts do not all move together. Build review time into the schedule and confirm the checklist with Shoreline Planning and Community Development before filing.
Approvals do not stay live indefinitely. Permit validity periods are set locally on top of the state code, so they differ between neighbouring jurisdictions and cannot be assumed from a previous job. On phased or financed work, confirm the expiry window and keep the permit alive with progress inspections.
Inspections in Shoreline
Where a permit is required, standard checkpoints include footing and foundation, framing, rough-in plumbing and mechanical, insulation and energy code compliance, fire systems on commercial work, and final, with a certificate of occupancy before the building is used. Incomplete submittals and documents not meeting the published file standards will not be accepted for review at all, so a formatting failure costs the whole intake rather than a correction cycle.
The point to plan around is that the electrical inspections may be booked with a different body entirely. Where the state Electrical Program holds the electrical permit, its inspector attends on the state’s schedule and the local inspector will not sign off electrical work. Sequencing a cover-up around two independent inspection queues is the practical skill on a Washington job.
Do not cover work before the required inspection has been approved. Keep the issued permits — plural — the approved plans and the energy code documentation available on site.
Shoreline permit search and official resources
Permit records in Washington are split the same way the permits are. Where Shoreline Planning and Community Development is the authority for the City of Shoreline, it holds the building, plumbing and mechanical records — but the electrical record for most projects sits with the state Electrical Program instead. If you are buying, refinancing or renovating, check both, because a clean local record does not mean the electrical work was ever permitted.
Confirm the edition, the local amendments and the electrical route. Washington sets a mandatory statewide minimum under chapter 19.27 RCW, but the edition moves in two groups on a three-year cycle and every jurisdiction may amend upward. All three questions have to be answered for the parcel and the filing date.
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- City of Shoreline get a permit
- Shoreline trees
- Shoreline clearing and grading permit
- Shoreline permit frequently asked questions
- Chapter 19.27 RCW, the State Building Code Act
Frequently asked questions
How long will my permit take?
The city publishes sixty-five calendar days for administrative decisions including building permits and tree removals, one hundred for administrative decisions requiring public notice, and one hundred and seventy for decisions requiring a public hearing. The clock starts after the application is determined complete and includes only those days the city is reviewing.
What stops the clock?
You do, in effect. The clock pauses when additional information or corrections to plans are requested, and resumes once the requested information is provided to the city. Turning corrections around quickly is the single biggest thing within your control.
When do I need a tree permit?
Three triggers. Removal of trees greater than twenty-four inches diameter at breast height; removal of trees in the rights of way, which extend beyond the edge of the paved road; and trees of any size on or near a stream, wetland or steep slope.
Is there a charge per tree?
Yes. The city notes a per tree fee for removing significant trees of twenty-four inches diameter at breast height and greater, with rates in the published fee schedule.
Does my exemption still apply near a stream?
No. The city states that exemptions do not apply to properties with environmentally sensitive or critical areas, which include steep slopes, wetlands, streams, beaches and lakes. Contractor credentials are unaffected either way, and they are a state matter. Washington registers contractors rather than licensing them. Under chapter 18.27 RCW a contractor registers with the Department of Labour and Industries, files a continuous surety bond of thirty thousand dollars as a general contractor or fifteen thousand as a specialty contractor, and keeps liability insurance on file, renewing every two years. Registration is not a competence test and does not authorise trade work: electrical certification comes under chapter 19.28 RCW and plumbing under chapter 18.106 RCW. The electrical permit itself usually comes from the state rather than the city, because the Electrical Program at Labour and Industries issues electrical permits and carries out electrical inspections for most of Washington under chapter 296-46B WAC.
Which code edition applies?
The state edition as amended by the city. Washington has a mandatory statewide building code. The codes enumerated in chapter 19.27 RCW, the State Building Code Act, are adopted and amended by the State Building Code Council within the Department of Enterprise Services and are required in all cities and counties, so local government administers and enforces them rather than choosing whether to have them. The two thousand twenty-one editions took effect on the fifteenth of March, two thousand twenty-four after two delays, and the two thousand twenty-four editions are dated to take effect on the third of May, two thousand twenty-seven. Adoption runs in two groups over a two-year timeline, so the building, residential, mechanical and plumbing parts do not all move on the same day. A city or county may amend upward from the state minimum but cannot opt out of it.
Simplify Shoreline permitting with Alliance Permitting
A published clock that pauses on corrections rewards fast, complete responses more than anything else. That is the part we control.
Trusted by leading builders, developers, and national contractors — 22 years of filing in the jurisdictions we write about.
Contractors and builders choose Alliance for Shoreline because the work is done by people who have stood at the counter:
- Twenty-two years of filing, so the edition and the electrical route are settled before submission
- We confirm which state code group governs each part of the work on your filing date
- State contractor registration, bond and insurance verified as active before filing
- Energy code and critical areas documentation prepared rather than discovered in review
- Two inspection queues sequenced so a cover-up never waits on the wrong inspector
Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Shoreline sooner?
Let Alliance prepare, file, and track your Shoreline permits while your crew stays on the job.
More Washington permitting guides
This guide is provided by Alliance Permitting for general information about Shoreline permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.