Outside city limits, Skagit County Planning and Development Services (PDS) issues building, plumbing, mechanical, flood and fire permits from 1800 Continental Place in Mount Vernon. The department is paperless: applications, plans, payments and inspection requests all run through the PDS Permit Portal. Under the fee schedule the commissioners approved on December 23, 2025, plan review costs 65 percent of the valuation-based permit fee and is due at application.
What requires a building permit in Skagit County?
The county’s permit pages sort work into residential and commercial “work classes”, and almost anything structural lands in one of them: new houses and accessory dwelling units, additions, garages, barns and pole buildings, alterations that move or cut load-bearing walls, new or larger exterior openings, and foundation repairs. The accessory structure class also takes in shipping containers, bulkheads, fences over 7 feet, ground-mounted solar arrays, pools and bridges.
Permit needed
- Houses, ADUs, additions and residential or agricultural accessory buildings
- Structural alterations, including new beams, columns or heavy rooftop units
- Demolition, after the Northwest Clean Air Agency asbestos steps
- Manufactured and modular homes
- Stand-alone furnace or heat pump replacement (residential mechanical)
- Water heater replacement, issued when you pay
- Any work at all inside a mapped flood hazard area, floodway or critical area
No building permit
- A one-story shed up to 200 sq ft with no plumbing and no sleeping use
- A deck no more than 30 inches above grade and up to 200 sq ft, covered or not, if it stays independent of the house
- Fences up to 7 feet; retaining walls up to 4 feet without a surcharge
- New roof covering (or one added layer), siding and house windows with no framing changes
- Above-grade prefabricated pools up to 5,000 gallons at a home
- Rooftop solar panels on an existing single-family roof
That list is Essential Handout #03, revised in January 2026. Its first line matters most in the Skagit delta: inside a special flood hazard area, a designated floodway or a critical area, no size exemption applies, and even a reroof in the floodplain needs a flood permit. Exempt sheds and fences still have to meet the setbacks in SCC 14.16.810.
What the county decides and what the state holds
The technical rules are the state’s 2021 codes. Skagit County’s adoption chapter, SCC 15.04, picks the appendices it uses and adds the 2021 Wildland-Urban Interface Code and NFPA 855 for energy storage. Local design values come from the county’s iMap: roof snow loads of 25, 30, 40 or 50 psf depending on the map zone, seismic category D1, 110 mph three-second-gust wind, 1,500 psf soil bearing and a 12-inch frost depth. Electrical work is outside the county’s remit altogether and goes to the state Department of Labor and Industries.
Skagit County building department: who handles permitting
PDS is one department with five teams: permit technicians, planning, fire, building and code compliance. It works with the county’s Public Health and Public Works departments on septic, water and road access. Randy Johnson serves as building official and floodplain manager.
Short on time to read all of this?
Get a free quote →| Office | Details |
|---|---|
| Building, land use, fire and flood permits | Planning and Development Services, 1800 Continental Place, Mount Vernon, WA 98273; 360-416-1320; pds@co.skagit.wa.us |
| Permit counter | Appointments preferred; walk-ins Monday, Tuesday, Wednesday and Friday 8 a.m. to noon and 1 to 3:30 p.m., Thursday 9 a.m. to noon and 1 to 3:30 p.m.; reception 8 a.m. to 4:30 p.m. weekdays |
| Online | PDS Permit Portal (Tyler Civic Access); written questions through the Ask a Permit Technician form |
| Septic | Skagit County Public Health, 301 Valley Mall Way, Suite 110, Mount Vernon; 360-416-1500 (press 1, then 2) |
| Electrical | Washington L&I, 525 E College Way, Suite H, Mount Vernon; 360-416-3000 |
Swinomish Reservation
A 1998 memorandum of understanding with the Swinomish Indian Tribal Community (county contract 3913) splits the work on the reservation. Where a fee-simple parcel belongs to a tribal member, the Tribe alone handles land use and the county issues no permits. On other non-trust parcels the applicant picks the lead agency and the other agency charges an administrative review fee.
The cities and towns
None of Skagit County’s eight incorporated places sends its building permits to the county; each runs its own.
| City or town | Building permits |
|---|---|
| Mount Vernon | City of Mount Vernon (online permitting on SmartGov) |
| Anacortes | City of Anacortes (Permit & Build pages) |
| Sedro-Woolley | City of Sedro-Woolley Building Department (iWorQ permit portal) |
| Burlington | City of Burlington Community Development, building division |
| La Conner | Town of La Conner (building permit application packet; permit fees revised January 2024) |
| Concrete | Town of Concrete Building Department, Town Hall, 45672 Main St.; 360-853-8401 |
| Lyman | Town of Lyman (its own building permit application; inspections booked on 360-826-3033) |
| Hamilton | Town of Hamilton, Town Hall, 584 Maple Street; 360-826-3027 (building fees set by Resolution 23-03) |
Permit types and what comes first
Residential permits
In the portal you pick a permit type and then a work class: Residential with Single Family Residence, Accessory Dwelling Unit, Addition, Alteration, Accessory Building or Accessory Structures; Manufactured/Modular Structures for a manufactured home; Mechanical (Residential) for a stand-alone equipment change; and Plumbing (Residential) for a water heater. Every building and land disturbance submittal needs the county’s Stormwater Worksheet and Model Construction SWPPP. Houses also need the state energy code worksheets, and an owner who is not applying in person signs the Agent Authorization form. Drawings must follow the county’s Electronic Document Standards.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial work classes cover new buildings, additions, alterations and tenant improvements, commercial accessory and agricultural buildings and pools. Most commercial projects must first hold a pre-development meeting with county staff, booked through the portal at no charge; a full pre-application meeting is a separate $625 service. Commercial packages include the Energy Code Compliance Tool for envelope, lighting and mechanical systems and a Special Inspection Summary, and an alteration application has to include its plumbing and mechanical work.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning: setbacks, height and lot coverage come from SCC 14.16 for the parcel’s zone; a zoning review costs $155.
- Critical areas: a Critical Area Evaluation ($625) under SCC 14.24 decides whether wetlands, streams, slopes or habitat buffers affect the site. Wetland buffers run from 25 to 50 feet for Category IV up to 150 to 300 feet for Category I and II.
- Shorelines: the county still administers a Shoreline Master Program first adopted in 1976 and last amended in 1995 while an update is under way; a shoreline letter of exemption is $625 and a substantial development permit $6,125.
- Floodplain: a flood area development permit is $500. SCC 14.34 requires the lowest floor of a home, including the basement and utilities, to sit 1 foot above base flood elevation, and improvements costing 50 percent or more of the building’s market value, counted over 10 years, require elevation.
- Septic and water: Skagit County Public Health permits septic systems; see the fees section for its design review charges.
- Driveway: a Public Works access permit is $374 for a house in 2026.
- Data centers: an emergency moratorium adopted on June 1, 2026 stops the county accepting permit applications for data centers for six months; the July 14, 2026 hearing minutes put its expiry in December 2026.
Skagit County building permit fees
The fees below are from the PDS fee schedule the Board of County Commissioners approved on December 23, 2025 (Resolution R20250314), which raised most charges 2.7 percent with the consumer price index. Each permit has two valuation-based parts: a plan review fee of 65 percent, charged when you apply, and the permit fee, charged at issuance.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Valuation $1 to $500 | $33.00 |
| $501 to $2,000 | $33.00 plus $3.85 for each additional $100 or fraction |
| $2,001 to $25,000 | $90.75 plus $15.15 for each additional $1,000 or fraction |
| $25,001 to $50,000 | $439.20 plus $11.00 for each additional $1,000 or fraction |
| $50,001 to $100,000 | $714.20 plus $9.25 for each additional $1,000 or fraction |
| $100,001 to $500,000 | $1,176.70 plus $6.68 for each additional $1,000 or fraction |
| $500,001 to $1,000,000 | $3,848.70 plus $5.53 for each additional $1,000 or fraction |
| $1,000,001 to $5,000,000 | $6,613.70 plus $4.04 for each additional $1,000 or fraction |
| Plan review | 65% of the building permit fee |
| Minimum for valuation-based permits not listed elsewhere | $310.00 |
| Residential plumbing or mechanical permit | $310.00 plus $15 per fixture |
| Prefabricated metal carport or storage | $465.00 flat |
| Shipping containers | $465.00 flat for up to 3 containers |
| Manufactured or modular home | $625.00 (foundation work extra) |
| Inspections; plan review of revisions | $155 per hour (inspections 1-hour minimum) |
| Temporary certificate of occupancy | $315.00 |
| Renewal, once, of an unexpired permit or within 6 months of expiry (up to 3 years) | 30% of the original permit fee |
| Working without a permit | Double permit fee |
| State Building Code Council surcharge | Residential $6.50 + $2 for each additional residential unit; commercial $25.00 |
| Technology fee | 7.5% of total amount, on all applications |
Worked example: a project valued at $300,000 falls in the $100,001 to $500,000 band, so the permit fee is $1,176.70 plus 200 × $6.68, or $2,512.70. Plan review adds 65 percent of that figure at submittal, and the 7.5 percent technology fee, the state surcharge and any trade or septic fees come on top.
A change of use is $315, and a one-time extension of up to six months on an unexpired permit is free. The county levies no impact fee of its own but collects other districts’ impact fees inside their boundaries. Septic design review by Public Health costs $620 for a new system and $570 for a repair in 2026.
Trade permits and who may pull them
Plumbing and mechanical permits are county permits in unincorporated Skagit County: a house’s plumbing or a furnace change-out is its own residential permit at $310 plus $15 a fixture, while commercial plumbing and mechanical work is priced on valuation. Fire sprinkler, alarm, kitchen hood and fuel-tank permits come from the PDS fire team on its own fee table.
Rather not deal with the Skagit County building department?
Get a free quote →- Electrical: Labor and Industries sells every electrical permit and does the inspections; none of the county’s cities runs its own electrical program, so this holds in town as well. The nearest L&I office is on East College Way in Mount Vernon.
- Who may pull them: a contractor needs an active L&I registration, electricians and plumbers need L&I licenses or certificates, and an owner can do some of the work on their own home under the state limits (see Washington contractor licensing).
- Septic installers: only installers certified by Skagit County may install a system; gravity-only systems may be eligible for homeowner installation, at $495 in 2026.
How to apply for a Skagit County building permit
Look it up on Skagit iMap; city parcels show gray with no zoning.
The online Ask a Permit Technician form answers questions on setbacks, heights and which permits apply; commercial projects book a pre-development meeting.
A designer files the septic application with Public Health in Civic Access; Public Works handles the driveway permit.
Choose the permit type and work class, then upload the plans, stormwater worksheet, SWPPP and energy forms as separate files.
A permit technician moves the record to Intake, and the status changes to Fees Due when an invoice is ready.
Upload revisions with the Building Permit Revision Form; the permit fee is billed at issuance.
Review, corrections and what causes delay
An application sits as Submitted Online until a permit technician picks it up, and any request for more material sets it to Pending Resubmittal, so a missing worksheet costs time before review even starts. Septic design review is often the long pole: Public Health issues a decision within 30 days of a complete, paid application, reported an average of about 60 days from application to design permit in 2025, and a wet-season review between roughly November and April can take up to 12 months. Revisions to approved plans are billed at $155 an hour.
Inspections
Building inspections are requested in the PDS Permit Portal, which needs an account; anyone can view the day’s inspection list there without one. Inspection fees and re-inspections are billed at $155 an hour with a one-hour minimum, and after-hours inspections at the same rate with a two-hour minimum.
Under Essential Handout #02, concrete poured before its inspection has to be removed unless a Washington-licensed engineer documents the reinforcement, dimensions and mix for the building official. The L&I electrical inspector and the county’s Public Health septic inspector work on their own schedules; the septic installer must give Public Health two full working days’ notice before backfill. A temporary certificate of occupancy costs $315.
Want this handled start to finish?
Get a free quote →Washington building code and flood maps
Skagit County enforces the 2021 Washington codes, in force statewide since March 15, 2024, through SCC 15.04. FEMA’s Community Status Book lists Skagit County in the National Flood Insurance Program with a Community Rating System class of 5, and all eight of its cities and towns as participating communities.
Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington
Skagit County building permit FAQ
Can I drop off paper plans at the Mount Vernon office?
No. PDS is paperless and takes all application material electronically through its permit portal; counter staff can help you use it.
How much is a building permit on a $300,000 house?
The permit fee is $2,512.70 on the schedule approved in December 2025, plus plan review at 65 percent of that, the 7.5 percent technology fee and the $6.50 state surcharge.
Do I need a permit for a shed?
Not for a one-story shed of 200 sq ft or less with no plumbing and no sleeping use, unless it sits in a flood hazard area, floodway or critical area. Setbacks still apply.
Does a new roof need a permit?
Replacing the covering, or adding one layer, needs no building permit if the framing is untouched, but in the floodplain the same reroof needs a flood permit.
Who issues electrical permits in Skagit County?
Washington L&I, for unincorporated land and for every city and town in the county.
How long does a septic permit take?
Public Health aims for a decision within 30 days of a complete, paid application; it reported about 60 days on average in 2025, and wet-season reviews can take up to 12 months.
Permit search and official resources
Past and current permits for unincorporated parcels can be searched in the PDS Permit Portal without an account, or through Property One-Stop by address. For documents not online, file a public records request with the county.
Inspections are where schedules slip.
Get a free quote →- Skagit County Planning and Development Services
- PDS Permit Portal (Civic Access)
- How to use the PDS Permit Portal
- Residential building permit types
- Commercial building permit types
- Adopted codes and design criteria
- Essential Handout #03: construction exempt from a building permit
- PDS forms and checklists
- Skagit County permit fee schedule
- Commissioners’ minutes, December 23, 2025 (fee schedule, Resolution R20250314)
- Essential Handout #18: flood hazard areas
- Critical areas (SCC 14.24)
- Shoreline Master Program
- Public Health septic permitting
- L&I list of cities with their own electrical inspections
- L&I contractor registration
- FEMA Community Status Book, Washington
Simplify Skagit County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Skagit County sooner?
Let Alliance prepare, file, and track your Skagit County permits while your crew stays on the job.
More Washington permitting guides
Anacortes
Read guide →Mount Vernon
Read guide →Sedro-Woolley
Read guide →Skamania County Building Permit Guide
Read guide →Snohomish Building Permit Guide
Read guide →Snohomish County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Skagit County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.