Puyallup’s Building Services division, part of Development and Permitting Services, reviews plans and issues building, mechanical, plumbing and fire construction permits, and applicants file through the CityView permit portal. The City states plainly that the Department of Labor and Industries issues all electrical permits. Plan review is charged at 65% of the building permit fee when you submit, and the building permit itself follows a valuation table the City has used since 2008.
The Permit Center is on the second floor of City Hall at 333 South Meridian, open Monday to Friday from 9 a.m. to 3 p.m.; staff answer 253-864-4165 from 8 a.m. to 5 p.m. (option 1 for the Permit Center, option 6 for Building Services). Ray Cockerham is the Building Code Official and Permit Center supervisor. Puyallup had 42,682 residents in the Census estimate for 2025; its permits cover the city limits, and Pierce County handles unincorporated land outside them.
What requires a building permit in Puyallup?
Chapter 17.04 of the Puyallup Municipal Code (PMC) adopts the current state building, residential, mechanical, fuel gas, plumbing and energy codes, which are the 2021 editions until the 2024 codes take over for applications from May 3, 2027. Puyallup changed one residential exemption: PMC 17.04.050 lets you build a deck without a permit if it is no more than 30 inches above grade at any point and not over a basement or story, with no size limit attached. The City’s building page lists the common jobs that do need one.
Permit required
- New houses and additions, including covered porches and patios
- Detached accessory buildings over 200 sq ft
- Interior remodels of a house
- Re-roofs that need sheathing, on any house or garage roof over 200 sq ft (issued over the counter)
- Decks more than 30 inches above grade at any point, or over a basement or story (PMC 17.04.050)
- Windows or doors that enlarge the opening
- Retaining walls over 4 feet from the bottom of the footing, or holding a surcharge
- Furnaces, water heaters, heat pumps, gas logs and gas piping; dishwashers, toilets, sinks, showers, hose bibs and irrigation
No building permit
- Sheds and outbuildings under 200 sq ft
- Decks no more than 30 inches above grade and not over a basement or story (PMC 17.04.050)
- Other work on the state residential code’s exempt list, such as finish work and fences up to 7 feet
The City’s building page goes further than the code on decks: it lists decks among additions and asks for a permit for any deck serving the required exit door, while PMC 17.04.050 exempts every deck no more than 30 inches high that is not over a basement. On roofs, the City’s list asks for a permit only when a re-roof needs new sheathing.
Short on time to read all of this?
Get a free quote →What the city decides and what the state holds
The building codes are the state’s, but PMC 17.04 sets the local rules around them: the deck exemption, no certificate of occupancy for a house (Group R-3), the flood hazard map adopted through PMC chapter 21.07, a two-year outside limit on every permit, and the requirement that every contractor carry a City business license. Fees are set by the City Manager under PMC 17.04.080 and published in the municipal fee schedule.
Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington
Puyallup building department: who handles permitting
Development and Permitting Services splits the work three ways: Building Services and Fire Prevention for the codes, plan review and inspections; Planning Services for zoning, environmental and subdivision rules; and Engineering Services for utility and road permits. All three review through the same CityView record, and fire prevention staff review sprinkler and alarm work.
| Detail | Information |
|---|---|
| Permit Center | City Hall, 333 South Meridian, 2nd floor, Puyallup, WA 98371 |
| Counter hours | Monday to Friday, 9 a.m. to 3 p.m., except holidays |
| Phone | 253-864-4165 (option 1 Permit Center, option 6 Building Services), 8 a.m. to 5 p.m. |
| PermitCenter@PuyallupWA.gov; Building@puyallupwa.gov; planning@puyallupwa.gov for pre-applications | |
| Building Code Official | Ray Cockerham |
| Applications and inspections | CityView portal, permits.puyallupwa.gov/Portal |
| Electrical permits | Washington Department of Labor and Industries |
A free virtual counter visit can be booked online for basic zoning, building and permitting questions. The City has also posted a scam alert about fraudulent emails that impersonate its staff.
Permit types
Residential permits
For a new house, the City asks for a signed application, three copies of a scaled site plan with setbacks, easements and septic or utility lines, two sets of construction drawings (floor, framing, foundation and elevations), WSU energy forms with HVAC sizing and a glazing schedule, truss layouts and calculations, engineering where needed, and a current City business license. The application form itself asks whether the lot is on sewer or septic, which water purveyor serves it, and whether it lies in the flood plain. Additions, interior remodels and new accessory buildings over 200 sq ft use shorter versions of the same list.
Not sure this scope needs a permit?
Get a free quote →Garages and sheds over 200 sq ft have their own checklist with a fast lane: a project qualifies for expedited review only if it is not in a critical area or floodplain, has no mechanical or plumbing work, adds less than 2,000 sq ft of hard surface, and is a single story that is not attached to another structure. Demolishing a house, or a detached building over 120 sq ft, needs a demolition permit with the Puget Sound Clean Air Agency asbestos notification receipt, and the site must be cleared of foundations and slabs.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Tenant improvements need a submittal checklist, full drawings with exit travel distances, any change of occupancy, and plumbing and mechanical plans. Racking systems have their own requirements. Fire sprinkler systems cost $3.77 per sq ft, and commercial, industrial and multifamily building permits carry a $265 fire plan review fee.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
Planning Services handles zoning, critical areas and shoreline review; a critical area review costs $160 and clearing or grading plan review runs from $70 to $1,240, plus a $190 grading permit fee. A pre-application review costs $300 for written notes (Tier 1) or $500 for a virtual meeting (Tier 2); the fee schedule credits the full pre-application fee to the permit if you apply within six months (the City’s page calls it a refund). New construction must run a new sanitary sewer line to the main, and an old septic system must be decommissioned under Tacoma-Pierce County Health Department rules, with the certificate copied to the City. Projects that disturb an acre or more also need the Department of Ecology’s construction stormwater general permit. On June 2, 2026 the City Council adopted a one-year emergency moratorium on new commercial and utility-scale battery energy storage facilities (home battery backup systems and rooftop solar are not affected), and held the required public hearing on July 21, 2026.
Puyallup permit costs and fees
Building fees are in the City of Puyallup Municipal Fee Schedule, effective January 1, 2026 and approved by Resolution 2535. Its building table points to “Exhibit A” for plan review and valuation, and the Exhibit A the City posts is dated 2008: it sets plan review at 65% of the permit fee, due at submittal, and values projects by a square-foot table. No line in Puyallup’s 2026 document covers the state building code fee under RCW 19.27.085.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee or rule |
|---|---|
| $1 to $500 of valuation | $25 |
| $501 to $2,000 | $25 for the first $500, plus $3.05 per added $100 or part |
| $2,001 to $25,000 | $69.25 for the first $2,000, plus $14 per added $1,000 or part |
| $25,001 to $50,000 | $391.25 for the first $25,000, plus $10.10 per added $1,000 or part |
| $50,001 to $100,000 | $643.75 for the first $50,000, plus $7 per added $1,000 or part |
| $100,001 to $500,000 | $993.75 for the first $100,000, plus $5.60 per added $1,000 or part |
| Plan review (Exhibit A) | 65% of the building permit fee, paid at submittal |
| Expedited review, qualifying permits | Twice the plan review fee |
| Re-inspection, after-hours and extra plan review | $55 an hour, or the City’s total hourly cost if greater |
| Mechanical permit | $40 issuance, plus items such as $19.55 per standalone AC unit |
| Plumbing, new house | $40 issuance plus $160 (1 bathroom), $200 (2) or $240 (3); $13 per fixture on alterations |
| Development services hourly rate | $180, billed by the half hour |
Worked example. Exhibit A values wood decks at $22.93 per sq ft, so a 300 sq ft deck that needs a permit is valued at $6,879. That falls in the $2,001 to $25,000 band: $69.25 plus 5 × $14 (each started $1,000 above $2,000 counts) gives a permit fee of $139.25. Plan review at 65% adds $90.51, for $229.76 before any other charge.
Puyallup collects school, park and traffic impact fees on some projects, but the City calculates them case by case rather than publishing a flat rate on its permit pages. The valuation bands in the table do not chain from one to the next, so a project is always priced inside the band its value falls in.
Rather not deal with the building department?
Get a free quote →Trade permits and who may pull them
Mechanical and plumbing permits are City permits filed in CityView, usually as separate permits with their own issuance fee; plumbing plan review is 65% of the plumbing permit fee and a plumbing re-inspection is $63 an hour. Electrical is different: the City’s permit page says L&I issues all electrical permits, and PMC 17.04.030 adopts the National Electrical Code only as L&I adopts it.
Who issues what
- Building, mechanical, plumbing, demolition and fire construction: Puyallup, on CityView
- Electrical: L&I
- Septic decommissioning: Tacoma-Pierce County Health Department
- Construction stormwater for an acre or more: Department of Ecology
Licenses and owners
- The City will not issue a permit for work by a contractor who must register under RCW 18.27 until it has checked the registration
- All contractors also need a City of Puyallup business license
- An owner who leaves the contractor section blank certifies that no contractors will be hired, or only licensed ones
For owner-builder limits and the state licenses electricians and plumbers hold, see the licensing section of our Washington guide.
How to apply for a Puyallup building permit
Use the City’s parcel tools for zoning, lot size, septic records, wetlands, streams and the floodplain, or email the Permit Center.
Choose Tier 1 notes ($300) or a Tier 2 virtual meeting ($500) for larger projects; the fee is credited to the permit if you apply within six months.
Use the submittal requirements for houses, additions, remodels and demolition, or the garage and shed checklist.
Create an account on the CityView portal; the City’s video tutorials cover registering, paying and scheduling inspections.
Upload the site plan as its own document, separate from the plan set, and pay the 65% plan review fee.
Respond to building, planning, engineering and fire comments, pay the permit fee, then buy the L&I electrical permit.
Review, corrections and what causes delay
An application expires if no permit is issued within 180 days after the City finds it complete, unless the applicant has pursued it in good faith; the Building Official can extend it in 90-day steps on written request. Revisions to an issued permit go through the Permit Center. Projects in critical areas or the floodplain, or with plumbing or mechanical work, lose the expedited route and go to standard review.
Want this handled start to finish?
Get a free quote →Inspections in Puyallup
Inspections are requested in the CityView portal. Under the City’s October 2026 final-inspection tip sheet, a request made by 11:59 p.m. is scheduled for the next business day. Before a commercial building final, fire prevention (sprinkler, alarm and emergency radio), engineering, planning, L&I and any health department finals must already be approved, and earlier corrections closed; the City does not write punch lists for the final.
A Puyallup permit becomes void if work does not start within 180 days, stops for 180 days or more, or reaches two years from issue, whether or not the work is finished. The Building Official can grant extensions of up to 180 days each on written request, and an expired permit can be reissued for the unfinished work at half the original fee, an option that lapses two years after expiry.
Puyallup permit search and official resources
CityView shows permit status and inspection results, and the Permit Services page carries a city map of permits. Puyallup is a participating community in the National Flood Insurance Program; FEMA’s status book gives March 7, 2017 as the date of its current flood map, and the building application asks whether the site is in the flood plain.
- Puyallup Permit Services: steps, hours, pre-applications
- CityView permit and inspection portal
- Building permit applications and requirements
- Municipal fee schedule, effective January 1, 2026 (PDF)
- Exhibit A: building permit fees and valuation table (PDF)
- Garage and shed submittal checklist (PDF)
- Submittal requirements for building permits (PDF)
- Commercial final inspection tip sheet (PDF)
- Adopted codes
- Puyallup Municipal Code
Inspections are where schedules slip.
Get a free quote →Puyallup building permit FAQ
Who issues building permits in Puyallup?
Building Services in the Development and Permitting Services Department, at the Permit Center on the second floor of City Hall (253-864-4165, option 1).
Where do I get an electrical permit in Puyallup?
From the Washington Department of Labor and Industries, which issues all electrical permits in the city.
Do I need a permit for a deck in Puyallup?
Not if the deck is no more than 30 inches above grade at any point and not over a basement or story, under PMC 17.04.050. Higher decks need one.
Do I need a permit for a shed?
Not for a shed or outbuilding under 200 sq ft. Larger ones use the garage and shed checklist and may qualify for expedited review.
How much does a building permit cost?
A 300 sq ft deck that needs a permit (more than 30 inches high), valued at the City’s $22.93 a square foot, costs $139.25 for the permit and $90.51 for plan review.
Do I need a permit to re-roof my house?
Only if the job needs new sheathing on a roof over 200 sq ft; that permit is issued over the counter or the same business day. Plain re-roofing without sheathing is not on the City’s permit list.
When will my inspection happen?
The City’s October 2026 tip sheet says requests made in CityView by 11:59 p.m. are scheduled for the next business day.
Simplify Puyallup permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Puyallup sooner?
Let Alliance prepare, file, and track your Puyallup permits while your crew stays on the job.
More Washington permitting guides
Pierce County
Read guide →Bonney Lake
Read guide →DuPont
Read guide →Redmond Building Permit Guide
Read guide →Renton Building Permit Guide
Read guide →Richland Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Puyallup permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.