Redmond is the eastside technology centre and runs one of the most explicitly sequenced permitting processes in Washington. Nothing here is discretionary about the order: land use, then civil, then building, with one narrow exception written into the code.
The zoning code governs building and construction procedures and controls where it conflicts with other administrative sections. A Technical Committee makes administrative decisions and can hear pre-application conferences, which are highly recommended for anything beyond the simplest permit type.
This guide covers work inside the Redmond city limits. Unincorporated King County is permitted by the county, and the neighbouring eastside cities administer the state code themselves.
The rainy season is a permitting season here. A city-approved wet weather plan for erosion and sediment control is required for any work anticipated to occur during the rainy season, defined as the first of October to the thirtieth of April. An erosion control bond may be required as part of that plan where work is near critical areas such as wetlands, streams, steep slopes or their buffers, and review carries its own fees.
What requires a building permit in Redmond?
Washington has a mandatory statewide building code. The codes enumerated in chapter 19.27 RCW, the State Building Code Act, are adopted and amended by the State Building Code Council within the Department of Enterprise Services, and they are required in all cities and counties — local government administers and enforces them rather than deciding whether to have them. A city or county may amend the state code, but it amends upward from a floor it cannot opt out of. So the question in Redmond is not whether a code applies, but which edition is in force and what Redmond Development Services has added to it.
Permit required
- New buildings, additions, alterations and change of occupancy or use
- Structural alterations, load-bearing changes, foundations, decks and retaining walls
- Plumbing work under the Uniform Plumbing Code as adopted by the state
- Mechanical and HVAC change-outs, fuel gas work and ventilation
- Work affecting the Washington State Energy Code envelope or systems
- Re-roofing above the exempt scope, demolition, and work in critical areas
Often exempt
- Ordinary repairs and maintenance replacing materials in kind
- Small accessory structures below the code threshold, where zoning allows
- Painting, flooring, cabinetry and other finish work
- Like-for-like fixture swaps with no alteration to piping
Local amendments, fee schedules and exempt thresholds differ from one jurisdiction to the next, so an exempt list from a neighbouring city is not reliable. An exemption from a building permit is never an exemption from zoning, critical areas review, the energy code or a trade permit. Confirm scope with Redmond Development Services before work starts.
Your electrical permit almost certainly does not come from the city. For most of Washington, electrical permits are issued and electrical inspections are carried out by the Electrical Program at the Department of Labour and Industries under chapter 296-46B WAC — not by the local building department. A minority of cities run their own electrical programme instead. Establish which applies to the parcel before you assume a single counter handles everything, because the electrical track runs on its own timetable and its own inspector.
The statewide features that catch projects everywhere
Four things shape a Washington filing more than the model code does. First, the edition is set by the state on a three-year cycle and adopted in two groups over a two-year timeline, so the building, residential, mechanical and plumbing parts do not all arrive on the same day. Second, plumbing runs on the Uniform Plumbing Code as adopted by the state, not the International Plumbing Code that most of the country uses. Third, the Washington State Energy Code is its own code under chapter 19.27A RCW rather than the international energy code, and it is among the most demanding in the country. Fourth, growth management and critical areas regulation reach ordinary residential work near wetlands, steep slopes, streams and shorelines far more often than owners expect. Cascadia subduction zone seismic detailing applies statewide. The sequence is fixed by code. All land use permits required by the zoning code must be obtained before any building or construction permit may be issued, and civil construction drawings must be reviewed and approved before a building permit or clearing and grading permit issues. The single exception is narrow: the administrator may allow building permits for residential structures in the neighbourhood residential district ahead of civil approval where the applicant has executed an agreement with the city
Who handles permitting in Redmond?
Development Services runs land use, civil and building review for the city, with a Technical Committee taking administrative decisions and making recommendations to the hearing examiner or council on the more complex review types.
| Detail | Information |
|---|---|
| Department | City of Redmond Development Services |
| Address | 15670 NE 85th Street, Redmond, WA 98052 |
| Phone | (425) 556-2473 |
| Pre-construction meetings | (425) 556-2746, scheduled within five business days of request |
| Wet weather plan | Required for work between the first of October and the thirtieth of April |
| Technical Committee | Makes administrative decisions and hosts pre-application conferences |
| Coordinated Civil Review | Construction and landscape drawings, performance bonds, engineering fees |
| Vesting | Building, electrical, mechanical, plumbing and fire permits vest on accepted complete application |
The Coordinated Civil Review is a substantial process in its own right. It covers review and approval of construction and landscape drawings, collection of performance bonds and development engineering review and inspection fees. Construction drawings must be submitted to the civil drawing checklist and to the conditions of approval in the notice of decision, and reviewed and approved by every applicable division. A kick-off meeting is recommended before submitting.
Submittal standards are precise on the technical side. Clear and grade submittals call for a composite drawing file with no external references, geo-referenced to the state plane coordinate system, with horizontal coordinates shown on at least two exterior boundary corners and electronic files tied to the city’s coordinate system.
Permit types
Residential permits
Residential work follows the same sequence, with the one exception allowing building permits in the neighbourhood residential district ahead of civil approval under an executed agreement. Approved mylars must be submitted at least twenty-four hours before requesting the pre-construction meeting, which is then scheduled within five business days of the request.
How Washington contractor credentials work
Washington registers contractors rather than licensing them. Under chapter 18.27 RCW every contractor must register with the Department of Labour and Industries, file a continuous surety bond — thirty thousand dollars for a general contractor, fifteen thousand for a specialty contractor — and keep liability insurance on file. Registration runs for two years and carries no continuing education requirement at the base level. Crucially, registration is not a competence test and it does not authorise trade work: electrical work requires certification under chapter 19.28 RCW and plumbing under chapter 18.106 RCW, each with its own examination and its own programme office.
A general registration does not let anyone touch the wiring or the pipes. A registered general contractor must subcontract electrical and plumbing work to appropriately certified trades, and an electrical contractor licence additionally requires at least one certified electrician on staff. Verify the registration is active and the bond and insurance current with Redmond Development Services and with the department, because registration lapses are common and an expired registration invalidates the credential the permit relies on.
Commercial permits
Commercial work typically moves through a site plan entitlement decision by the Technical Committee, then Coordinated Civil Review, then building permit review. Pre-application conferences with the Technical Committee are highly recommended for the more involved review types and optional only for the simplest.
Registrations, trade certifications and design professionals
Three credential layers appear on Washington projects: the state contractor registration under chapter 18.27 RCW, which nearly everyone doing the work needs; separate state trade certification for electricians and plumbers, each examined and administered by its own programme; and, on commercial and larger residential work, drawings stamped by a Washington-licensed architect or professional engineer. Confirm what Redmond Development Services requires for the specific building before filing.
Redmond permit costs and fees
Redmond fees cover land use review, coordinated civil review including development engineering review and inspection charges, and the building permit itself, with performance bonds collected through the civil process and wet weather plan review carrying its own fees.
| Fee component | How it works |
|---|---|
| Building permit | Set by the local jurisdiction, usually on project valuation; the state sets the code, not the fee |
| Plan review | A percentage of the permit fee or a flat charge, set locally |
| Plumbing and mechanical | Separate local permits under the adopted plumbing and mechanical codes |
| Electrical | Usually a state permit fee through the Labour and Industries Electrical Program, not a city fee |
| Energy code | Compliance documentation for the Washington State Energy Code, and review time for it |
| Critical areas and land use | Separate review and fees where wetlands, slopes, streams or shorelines are involved |
Washington sets the code statewide but leaves the fee schedule local, so two jurisdictions on the same edition can price the same project very differently. The electrical fee is the one that most often surprises people, because on most projects it is paid to the state rather than to the city. Ask Redmond Development Services for the schedule in force on your filing date, and confirm the electrical route separately.
Need a real number for a specific Redmond project? Send us the scope, address and valuation and we will identify the edition in force, the local amendments, the electrical route and the fee categories that will apply.
Trade permits and who may pull them
Trade permits are separate from the building permit and, in Washington, are not all issued by the same body. Plumbing and mechanical permits come from the local jurisdiction under the codes the state has adopted. Electrical permits come from the Electrical Program at the Department of Labour and Industries, unless this jurisdiction runs its own. That split is the single most common source of confusion on a Washington project.
Your electrical permit almost certainly does not come from the city. For most of Washington, electrical permits are issued and electrical inspections are carried out by the Electrical Program at the Department of Labour and Industries under chapter 296-46B WAC — not by the local building department. A minority of cities run their own electrical programme instead. Establish which applies to the parcel before you assume a single counter handles everything, because the electrical track runs on its own timetable and its own inspector.
- Electrical work follows chapter 19.28 RCW and the state electrical rules at chapter 296-46B WAC, performed by a certified electrician working for a licensed electrical contractor.
- Plumbing work follows the Uniform Plumbing Code as adopted by the state, performed by a plumber certified under chapter 18.106 RCW.
- Mechanical and fuel gas work follows the state mechanical and fuel gas provisions, permitted locally.
Permit required
- Service installations, panel upgrades, new circuits, solar PV and EV chargers
- New plumbing, repipes, water heater change-outs, fixtures, backflow and gas piping
- HVAC installation and change-out, ductwork, venting and commercial kitchen exhaust
- Sprinkler, standpipe and fire alarm work on commercial and multi-family structures
Typically exempt
- Replacing a fixture, switch, receptacle or light with no alteration to wiring or piping
- Clearing a stoppage without replacing or rearranging concealed piping
- Filter, thermostat and routine component service
- Like-for-like appliance repair that does not alter the connection
How to apply for a Redmond building permit
Work anticipated between the first of October and the thirtieth of April needs a city-approved wet weather plan.
One may be required as part of the wet weather plan where work is near wetlands, streams, steep slopes or their buffers.
All land use permits required by the zoning code must be obtained before any building or construction permit may be issued.
Construction and landscape drawings, performance bonds and engineering fees, reviewed by every applicable division.
Composite drawing file with no external references, geo-referenced to the state plane system and tied to the city coordinate system.
Submit approved mylars at least twenty-four hours ahead; the meeting is scheduled within five business days of the request.
Review, corrections and what actually causes delay
In Washington the first cause of delay is the energy code, because the state code is its own instrument and more demanding than the international one most designers default to. After that comes critical areas review, which reaches ordinary residential work near wetlands, streams, steep slopes and shorelines and adds its own study and mitigation timeline. Then the electrical split, where a project waits on a city inspection that was never going to happen because the electrical permit sits with the state. Then edition confusion, because the state adopts in two groups and the parts do not all move together. Build review time into the schedule and confirm the checklist with Redmond Development Services before filing.
Approvals do not stay live indefinitely. Permit validity periods are set locally on top of the state code, so they differ between neighbouring jurisdictions and cannot be assumed from a previous job. On phased or financed work, confirm the expiry window and keep the permit alive with progress inspections.
Inspections in Redmond
Where a permit is required, standard checkpoints include footing and foundation, framing, rough-in plumbing and mechanical, insulation and energy code compliance, fire systems on commercial work, and final, with a certificate of occupancy before the building is used. The applicant and the contractors attend the pre-construction meeting with city staff, and the meeting is the gate to breaking ground rather than a formality afterwards.
The point to plan around is that the electrical inspections may be booked with a different body entirely. Where the state Electrical Program holds the electrical permit, its inspector attends on the state’s schedule and the local inspector will not sign off electrical work. Sequencing a cover-up around two independent inspection queues is the practical skill on a Washington job.
Do not cover work before the required inspection has been approved. Keep the issued permits — plural — the approved plans and the energy code documentation available on site.
Redmond permit search and official resources
Permit records in Washington are split the same way the permits are. Where Redmond Development Services is the authority for the City of Redmond, it holds the building, plumbing and mechanical records — but the electrical record for most projects sits with the state Electrical Program instead. If you are buying, refinancing or renovating, check both, because a clean local record does not mean the electrical work was ever permitted.
Confirm the edition, the local amendments and the electrical route. Washington sets a mandatory statewide minimum under chapter 19.27 RCW, but the edition moves in two groups on a three-year cycle and every jurisdiction may amend upward. All three questions have to be answered for the parcel and the filing date.
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Redmond civil site permits
- Redmond Zoning Code 21.76.020, overview of the development process
- Redmond Zoning Code 21.76.050, permit types and procedures
- Redmond applications and forms
- Chapter 19.27 RCW, the State Building Code Act
Frequently asked questions
What is a wet weather plan and do I need one?
A city-approved plan for erosion and sediment control, required for any work anticipated to occur during the rainy season, which the city defines as the first of October to the thirtieth of April. An erosion control bond may be required as part of it where there will be work near critical areas such as wetlands, streams, steep slopes or their buffers.
Can I apply for the building permit before the land use permit?
No. All land use permits required by the zoning code must be obtained before any building or construction permit may be issued, and civil construction drawings must be approved before a building or clearing and grading permit issues.
Is there any exception to that sequence?
One, and it is narrow. The administrator may allow the approval of building permits for residential structures within the neighbourhood residential zoning district in advance of civil construction drawing approval, where the applicant has executed an agreement with the city.
How quickly can I get a pre-construction meeting?
Within five business days of the request. Submit paper copies of the approved mylars to the development services centre at least twenty-four hours before requesting it, and the applicant and contractors attend with city staff.
Which code edition applies?
The state edition as amended by the city. Washington has a mandatory statewide building code. The codes enumerated in chapter 19.27 RCW, the State Building Code Act, are adopted and amended by the State Building Code Council within the Department of Enterprise Services and are required in all cities and counties, so local government administers and enforces them rather than choosing whether to have them. The two thousand twenty-one editions took effect on the fifteenth of March, two thousand twenty-four after two delays, and the two thousand twenty-four editions are dated to take effect on the third of May, two thousand twenty-seven. Adoption runs in two groups over a two-year timeline, so the building, residential, mechanical and plumbing parts do not all move on the same day. A city or county may amend upward from the state minimum but cannot opt out of it.
Who registers my contractor?
The state. Washington registers contractors rather than licensing them. Under chapter 18.27 RCW a contractor registers with the Department of Labour and Industries, files a continuous surety bond of thirty thousand dollars as a general contractor or fifteen thousand as a specialty contractor, and keeps liability insurance on file, renewing every two years. Registration is not a competence test and does not authorise trade work: electrical certification comes under chapter 19.28 RCW and plumbing under chapter 18.106 RCW. The electrical permit itself usually comes from the state rather than the city, because the Electrical Program at Labour and Industries issues electrical permits and carries out electrical inspections for most of Washington under chapter 296-46B WAC.
Simplify Redmond permitting with Alliance Permitting
Redmond writes its sequence into code, which means it can be planned exactly. We plan it, including the seven months of rainy season.
Trusted by leading builders, developers, and national contractors — 22 years of filing in the jurisdictions we write about.
Contractors and builders choose Alliance for Redmond because the work is done by people who have stood at the counter:
- Twenty-two years of filing, so the edition and the electrical route are settled before submission
- We confirm which state code group governs each part of the work on your filing date
- State contractor registration, bond and insurance verified as active before filing
- Energy code and critical areas documentation prepared rather than discovered in review
- Two inspection queues sequenced so a cover-up never waits on the wrong inspector
Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Redmond sooner?
Let Alliance prepare, file, and track your Redmond permits while your crew stays on the job.
More Washington permitting guides
This guide is provided by Alliance Permitting for general information about Redmond permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.