Skip to main content
Municipal GuideUtahMapleton · Utah County

Mapleton, Utah Building Permit Guide

Mapleton City’s Community Development Department issues building permits inside the city through the MGO Connect portal.

Authority: Mapleton Community DevelopmentFiling: MGO Connect portalPhone: 801-489-6138
Authority
Mapleton Community Development125 West 400 North
Apply / Intake
MGO Connect portalHelp line 866-957-3764
Inspections
Booked in MGO Connect$55 if work is not ready
2025 Population
16,275U.S. Census estimate

Mapleton’s Community Development Department issues building permits inside the city, and every application is filed online through the MGO Connect portal, which is also used to book inspections. A basement finish permit costs $300 and a solar permit $165, while a new house also pays impact fees for parks, public safety, storm water and pressurized irrigation with the building permit.

What requires a building permit in Mapleton?

The city’s 2026 FAQ says a permit is needed whenever you build, enlarge, alter, repair, move or demolish a building, change its occupancy, or install, alter or replace an electrical, gas, mechanical or plumbing system. City Code 18.12.050 also requires a city permit for any work on a street, curb, gutter or sidewalk.

Permit needed

  • New homes, additions and accessory buildings over 200 sq ft
  • Basement finishes, unless only exempt finish work is done
  • A second kitchen in a house (family use only)
  • Accessory apartments, with a separate accessory apartment permit
  • Solar and wind systems
  • Signs
  • Electrical, gas, mechanical and plumbing work beyond minor repairs

No building permit (city FAQ)

  • One-story detached structures up to 200 sq ft
  • Fences up to 7 feet
  • Retaining walls up to 4 feet, measured from the bottom of the footing
  • Detached decks up to 200 sq ft and no more than 30 inches above grade
  • Painting, flooring, cabinets, countertops and similar finish work
  • Minor electrical, gas and mechanical repairs

Exempt projects still have to meet zoning rules such as fence heights and accessory building setbacks.

Who issues building permits in Mapleton?

Mapleton City permits and inspects building work inside city limits through its Community Development Department, which also runs planning and zoning. Chris Swenson is the City Building Official. City Code adopts the State Construction Code and the state fire code (most recently amended by Ordinance 2026-05 on March 18, 2026). Before the city issues a permit, a contractor must show a current Utah contractor licence, liability insurance and workers’ compensation insurance. Land outside the city is permitted by Utah County’s Building Division.

Short on time to read all of this?

Get a free quote →
Mapleton permitting contact
DetailInformation
DepartmentMapleton Community Development (building)
AddressMapleton City Building, 125 West 400 North (Community Center Way), Mapleton, UT 84664
Phone801-489-6138
Building Official801-806-9110
HoursMonday to Thursday, 8:00 a.m.–5:30 p.m.; Friday, 8:30 a.m.–5:00 p.m.
Apply and book inspectionsMGO Connect portal (help line 866-957-3764)

Applications and forms

Building permit applications must be submitted online through MGO Connect (MyGovernmentOnline). Log in or choose New Account, then apply for a building permit and upload the plans. For a new house, the land disturbance permit is applied for in the same online submission.

  • Utah Owner/Builder Certification Agreement, the state form for owners building or remodeling their own home, linked from the city’s Forms page
  • Accessory Apartment Application ($125 permit) and Second Kitchen Agreement Application
  • Sign Permit Application ($75)
  • Right-of-Way Utility Excavation Permit for work in a city street ($150 base fee plus street cut fees)
  • Zoning Verification Application ($25)
  • Project and Site Plan Application for commercial sites ($300)

Permit costs and fees in Mapleton

Mapleton sets permit fees by City Council resolution. The fee schedule for fiscal 2026-27, adopted with the budget by Resolution 2026-32 on June 3, 2026, lists these building and utility fees:

Mapleton building and connection fees (Resolution 2026-32, 2026-27)
ItemFee
Building permit (major projects)Based on the IBC with a .005 multiplier
Basement finish$300
Solar or wind permit$165
Special inspection$55
Sign permit$75
Accessory apartment permit$125
Land disturbance permit, single-family lot$300
Culinary water connection$600 (1-inch) to $2,280.67 (3-inch)
Secondary irrigation connection, 1-inch$150 if developer installed; $400 if city installed
Secondary irrigation inspection$150
Sewer connection$250

Not sure this scope needs a permit?

Get a free quote →

Impact fees on a house are split in two. Culinary water ($2,780 for a 1-inch meter) and sewer ($3,503.62 for a 1-inch meter) are paid before the subdivision plat is recorded. The rest is paid with the building permit:

Mapleton residential impact fees paid with the building permit (2026)
FeeAmount per lot
Parks and recreation$5,861
Public safety$402.52
Storm water$975.86 (lot under ½ acre); $1,854.13 (over ½ acre)
Pressurized irrigation$6,597 (under ½ acre); $8,796 (½ to 1 acre); $10,995 (over 1 acre)

For a house on a lot under half an acre, that is $13,836.38 at permit time. Commercial projects pay public safety impact fees per 1,000 sq ft ($302.50 commercial, $112.93 office, $79.82 industrial) plus water, sewer, storm water and $6,597 per pressurized irrigation connection. The Forms page still links the January 2024 impact fee sheet, which shows lower amounts; the 2026 sheets on the Fee Schedules page are the current ones.

Electrical, plumbing and mechanical work

The city’s building inspectors check trade work as part of the building inspection sequence. Under-slab plumbing, electrical and mechanical work is inspected before it is buried, the 4-way and gas line inspection covers framing with rough electrical, mechanical, fuel gas and plumbing, and the permanent power inspection checks the service panel before the utility connects it. Stand-alone trade work beyond the minor repairs listed as exempt needs a permit through MGO Connect.

Application documents and site rules

Upload the plans and documents in MGO Connect with the application. For a basement finish, the plans must show the use of every finished room, all electrical outlets and egress windows in bedrooms. Plans for a new house or accessory building also have to meet the zoning standards the city publishes:

Rather talk it over?

Call 1-855-478-4290 →
  • Setbacks in the A-2, RA-1, RA-2, R-2 and R-2-B zones: 30 feet front and corner side, 10 feet side, 25 feet rear, and a garage facing a street 20 or 25 feet from the back of the sidewalk
  • Building height up to 40 feet (30 feet in the PO-1 zone)
  • Accessory buildings: no more than 20% of the rear yard; 3 feet from side and rear lines if under 15 feet tall, 10 feet if 15–24 feet tall; no unpainted metal roofs; metal buildings of 500 sq ft or more need 30% non-metal siding
  • Accessory apartments: owner-occupied; attached units need a 6,000 sq ft lot and a side or rear entrance, detached units an 11,000 sq ft lot and a size cap of 1,000 to 1,400 sq ft

How to apply: 6-step Mapleton process

1. Check the zoning

Find the zone on the city zoning map and check setbacks, height and accessory building rules in Title 18.

2. Open an MGO Connect account

Create a New Account or log in from the Building page; the help line is 866-957-3764.

3. Apply and upload plans

Submit the building permit application and plans; add the land disturbance permit for a new house in the same submission.

4. Answer review comments

Community Development reviews the plans and returns comments through the portal.

5. Pay fees and receive the permit

Pay the permit, connection and impact fees due at building permit; contractors must be approved with licence and insurance.

6. Book inspections through final

Schedule each inspection in MGO Connect; every permit needs a final inspection.

Mapleton building inspections

All inspections are scheduled through the MGO Connect portal. If you want a specific date or time, request it up to three days ahead. If the work is not ready when the inspector arrives, the city charges a $55 re-inspection fee, and no further inspections are done until it is paid at the City Office by cash, card or check.

Rather not deal with the building department?

Get a free quote →
Mapleton residential inspections
InspectionWhat is checked
Setback, footings and site toiletPlacement against setbacks, excavation, forms and steel, the ufer ground; a restroom must be on site
Foundation and subgrade insulationForms and reinforcing steel; insulation below grade or under the slab
Temporary powerPedestal, grounding rod and GFCI outlets
Suspended concrete and under slabPrecast and cast-in-place floors and porch caps; under-slab plumbing, electrical and mechanical
ShearStructural sheathing and foundation straps before the weather barrier (can be combined with the 4-way)
4-way and gas lineFraming and all rough trades; windows and exterior doors must be installed
Weather barrier and stucco, lath and flashingBarrier and flashing before siding, masonry or roofing; lath after penetrations are sealed
Permanent powerService panel before utility hook-up
InsulationInsulation, doors, windows and HVAC equipment against the energy code
DrywallFire-rated drywall only (since March 1, 2024)
Shower panFilled to within ½ inch of the top for at least 15 minutes
FinalFinished work in place before use or occupancy; no personal items moved in before occupancy

Local Mapleton details that matter

Water rights: new residential subdivisions must convey water to the city before the plat is recorded: 0.45 acre-feet per unit for indoor use and 2.5 acre-feet per irrigable acre for outdoor use. Shares in Hobble Creek, Mapleton Irrigation or (west of Highway 89) East Bench Canal can be transferred directly; other water needs a change application with the State Engineer.

Fences: in front yards a solid fence can be 3 feet and an open fence 5 feet, with no chain link; side and rear fences can be 6 feet, plus 2 feet of deer fencing if the top part is at least 50% open.

Want this handled start to finish?

Get a free quote →

Street work and damage guarantees: work in the right-of-way needs a utility excavation permit, and where heavy equipment will be used the city can require a guarantee for repair of streets, curb, gutter and sidewalk before it issues the building permit.

Subdividing by deed: splitting a parcel by recording a deed without a city-approved plat violates city code and can lead to building permits being withheld.

Utah building code

Utah adopts one construction code for the whole state; cities and counties enforce it, and any local amendments are set by the Legislature. Utah rules

Official Mapleton permitting resources

Mapleton City pages, documents and code:

Inspections are where schedules slip.

Get a free quote →

Mapleton permit FAQs

Who issues building permits in Mapleton?

Mapleton City’s Community Development Department, for property inside city limits. Applications go through the MGO Connect portal.

How much does a building permit cost in Mapleton?

Major building permits are based on the IBC with a .005 multiplier. Flat fees include $300 for a basement finish, $165 for solar and $75 for a sign. A house on a lot under half an acre also pays $13,836.38 in impact fees at permit time.

Do I need a permit to finish my basement?

Yes, unless the work is limited to exempt finish work. The permit is $300, and the plans must show room uses, outlets and bedroom egress windows.

Do I need a permit for a shed or deck?

Not for a one-story detached structure up to 200 sq ft, or a detached deck up to 200 sq ft and 30 inches high. Setbacks still apply.

How do I schedule an inspection?

In MGO Connect. Ask up to three days ahead for a specific date or time; work that is not ready costs $55 to re-inspect.

Can I have an accessory apartment?

In most residential zones, yes, if the owner lives on the property. It needs a $125 accessory apartment permit and must meet lot size and parking rules.

Simplify Mapleton permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Utah. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Mapleton sooner?

Let Alliance prepare, file, and track your Mapleton permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Mapleton permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.