Portland, Texas Building Permit Guide

Portland’s Development Services department at the City Annex issues every building and trade permit in the city through iWorQ, under the 2021 codes adopted July 1, 2025 and Texas windstorm rules.

Authority: City of Portland Development ServicesCode: 2021 I-Codes, 2020 NEC, 2015 IECCPhone: 361-777-4550
Office
City Annex, 601 Moore Ave.361-777-4550
Portal
iWorQPermits, contractors, inspections
New home review
Up to 15 business daysOther permits 2–5 days
Inspection cut-off
4:00 p.m.For next business day

Building permits inside Portland city limits come from the City’s Development Services Department at the City Annex, 601 Moore Avenue (361-777-4550), and are applied for in the City’s iWorQ portal or on the lobby computer at the Annex. New homes and commercial buildings can take up to 15 business days to process, most other permits 2–5 days, and every contractor must be registered with the City first.

What requires a permit in Portland?

A permit is needed to build, alter or enlarge any structure, including swimming pools and fences, and to install, alter, repair or replace electrical wiring, plumbing or mechanical equipment. The City issues these permit types:

Building and site

  • New residential and new commercial buildings
  • Additions and remodels, and accessory structures
  • Foundations and foundation repair
  • Roofing, and window, siding or door replacement
  • Fences, pools, driveways and concrete
  • Demolition, and grading and site preparation, including excavation and fill
  • Construction trailers, storage pods and roll-off containers
  • Signs, solar panels and work in the right-of-way

Trades and other

  • Electrical, plumbing, gas and mechanical
  • Generators
  • Irrigation systems
  • Fire sprinkler, suppression and alarm systems (Fire Marshal)
  • Certificates of occupancy for new buildings, new uses, new tenants, name changes and changes of ownership
  • Short-term rentals and bed and breakfasts
  • Garage sales and vending machines

Portland Development Services: who handles permitting

All permits are issued by Development Services, which also runs planning and zoning and inspections. Plans for new construction are reviewed by Bureau Veritas under a professional services agreement with the City. Averi DeVault, P.E., is Director of Development Services.

Short on time to read all of this?

Get a free quote →
Portland permitting contacts
DetailInformation
OfficeCity of Portland Annex, 601 Moore Avenue, Portland, TX 78374
Phone and email361-777-4550; permits@portlandtx.gov
HoursMonday to Thursday 7:30 a.m. to 5:30 p.m.; Friday 7:30 to 11:30 a.m.
OnlineiWorQ portals for permits, contractor registration, zoning and code enforcement
City Hall1900 Billy G. Webb Drive; 361-777-4500

The City’s Chief Building Official, at the same 361-777-4550 number, is listed in the state floodplain directory as Portland’s floodplain administrator. Portland lies in San Patricio County, with a small unpopulated part in Nueces County; land outside the city limits is outside the City’s permit system.

Portland applications, forms and contractor registration

Permits are issued in the name of the property owner or of the licensed contractor doing the work. Contractors register each calendar year (January 1 to December 31) in the iWorQ contractor portal with proof of their state licence and insurance; the registration number becomes the access code for booking inspections. Working for pay on a permitted job without registering is a misdemeanor punishable by a fine of up to $500 a day.

The Development Forms page posts the City’s supporting documents:

  • Address assignment and verification, and the homestead affidavit
  • Commercial plan submittal requirements and plan review checklist
  • Electrical, gas and generator one-line diagrams
  • Foundation certificate and wind brace report
  • Asbestos statement and backflow prevention test form
  • Swimming pool packet
  • Short-term rental and bed and breakfast application

The City’s Permit Requirements and Inspection Checklist lists the documents and inspections for every permit type; incomplete applications are not accepted.

Portland permit cost

Fees come from the Development Fee Schedule, updated March 14, 2024. Small residential jobs are flat fees:

Not sure this scope needs a permit?

Get a free quote →
Portland residential permit fees
PermitFee
Roofing$170
Pool$115
Accessory structure$55
Solar$55
Window, siding or door$50
Foundation repair$50
Fence$35
Driveway or concrete$35
Storage pod$25
Demolition of an accessory structure$30
Permit renewal or extension$85
Contractor registration$150 a year; landscaping contractors $60

New buildings, additions, remodels and demolitions are charged by project value, which must be at least 80% of the International Code Council’s building valuation data and includes all building systems and site work. New single-family, multi-family and commercial projects also pay a plan review fee from a second table, and a technology fee is charged on top. For a project valued at $250,000, the building permit fee is $1,150 plus 150 × $6.50, or $2,125, and the plan review fee is $450 plus 150 × $2.50, or $825.

Multi-family and commercial projects also pay fire code plan review and inspection fees, starting at $500 and $750 for projects up to $250,000.

Portland trade permits

Portland residential trade permit fees
PermitFee
Electrical$40
Gas$40
Mechanical$40
Plumbing$35; reroute or tunnel work $115
Irrigation$35 plus meter and tap fees if needed

Plumbers, irrigators, electricians and air-conditioning contractors need state licences as well as City registration. Mechanical permits need a 2021 Manual J, S and D load and duct design, plumbing tunnel jobs need an engineer’s letter, irrigation permits close with a backflow test report, and generators need the gas and electrical one-line and the generator manual. Fire sprinkler, suppression and alarm systems are reviewed by the Fire Marshal.

Rather talk it over?

Call 1-855-478-4290 →

What to submit for a new home

With the application

  • New Residential Building Permit Application packet
  • Engineered plans: title sheet, site plan, foundation, floor, framing and roof plans, elevations, mechanical, electrical and plumbing plans, and sections and details
  • 2021 REScheck energy report
  • TDI windstorm form WPI-1

To close the permit

  • TDI windstorm certificate WPI-8
  • Engineer’s foundation certificate
  • Elevation certificate
  • Termite report
  • Third-party energy report and any other third-party inspection reports

Any foundation over 1,000 sq ft must be designed and inspected by a Texas-licensed professional engineer, and new or remodeled assembly, educational, hazardous, institutional and R-1 and R-2 residential occupancies must be designed by a registered design professional. Commercial projects add engineered fire plans, a code analysis sheet, a 2021 COMcheck and a stormwater notice of intent.

How to get a Portland building permit: 6 steps

1. Check zoning and the plat

Every project must be on a properly platted lot with the right zoning; zoning questions go through the City’s zoning portal.

2. Register the contractors

Each contractor registers for the calendar year in the iWorQ contractor portal and pays $150.

3. Use the checklist

Gather the documents the Permit Requirements and Inspection Checklist lists for the permit type, including the WPI-1 for windstorm work.

4. Apply in iWorQ or at the Annex

Submit online or on the lobby computer at 601 Moore Avenue, where staff can help.

5. Wait for review

New homes and commercial buildings take up to 15 business days, with plans reviewed by Bureau Veritas; most other permits take 2–5 days.

6. Inspect and close out

Request each inspection in the portal, then file the closure documents and get the certificate of occupancy walkthrough.

Rather not deal with the building department?

Get a free quote →

Inspections in Portland

Contractors request inspections in the iWorQ citizen portal, using their registration number as the access code and choosing a morning or afternoon visit. Requests in by 4:00 p.m. are scheduled for the next business day; later requests go to the next two business days. Results are posted in the portal by the end of the business day. If an inspection is missed, the City requires an engineer’s letter to sign off the work.

The checklist lists 23 inspections for a new home: setback, temporary electric pole, plumbing rough, water service and sewer yard, foundation, electrical, mechanical and gas rough, plumbing top-out, framing, stucco and brick ties, energy insulation, construction electric and gas final with meter release forms, the trade and building finals, energy final, the driveway flatwork (by Public Works) and a certificate of occupancy walkthrough with the Building Official. Framing inspections do not replace the Texas Department of Insurance windstorm inspections.

Local Portland details

Windstorm: roofing, windows, siding, doors, accessory structures, solar panels and generators all need the TDI WPI-1 at application and the WPI-8 certificate before the permit closes. During a hurricane warning, the Building Official can order loose outdoor objects and building materials on homes, businesses and construction sites to be secured or stored.

Flood zones: the City’s flood hazard areas come from the Flood Insurance Study for the City of Portland dated November 4, 2016, and new homes close out with an elevation certificate.

Certificates of occupancy: a new CO is needed for each new tenant, new use, business name change or change of ownership, and utilities are released in the new tenant’s name only after it is issued.

Want this handled start to finish?

Get a free quote →

Land next to state land: work on land adjoining state-owned or General Land Office land needs a boundary survey by a licensed state land surveyor.

Texas building code

Texas has no single statewide building code: state law makes the International Residential Code the base code for homes in cities and the International Building Code the base for commercial buildings, with each city choosing the edition and its own amendments, while the National Electrical Code and the energy code apply statewide. Outside city limits most counties issue no building permits for homes. Texas building code rules

Portland permit search and official resources

Inspections are where schedules slip.

Get a free quote →

Frequently asked questions

Who issues building permits in Portland, Texas?

The City’s Development Services Department at the City Annex, 601 Moore Avenue (361-777-4550, permits@portlandtx.gov).

What permit system does Portland use?

iWorQ, for permit applications, document uploads, fee payment, contractor registration and inspection requests.

How long does a Portland permit take?

Up to 15 business days for new homes and commercial buildings, and typically 2–5 business days for other permits.

How much is a roofing or fence permit?

$170 for a residential roof and $35 for a fence. Roofing also needs the TDI WPI-1 and WPI-8 windstorm forms.

Which codes are adopted?

The 2021 International Building, Residential, Fire, Fuel Gas, Mechanical, Plumbing, Existing Building and Swimming Pool and Spa Codes, the 2020 National Electrical Code and the 2015 Energy Conservation Code, effective July 1, 2025.

When are inspections requested?

In the citizen portal by 4:00 p.m. for the next business day.

Simplify Portland permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Texas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Portland sooner?

Let Alliance prepare, file, and track your Portland permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Portland permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.