Mercedes issues building and trade permits through its Planning & Development Department, using online forms; homes are charged $0.30 per square foot plus a $150 plan review fee.

Authority: City of Mercedes Department of Planning & DevelopmentCode: 2015 I-Codes in the city codePhone: 956-565-3114 ext. 128, 129 or 130
Authority
Planning & DevelopmentCity Hall, 400 S. Ohio Ave.
Filing
Online permit applicationEmail planning@cityofmercedes.com
New home fee
$0.30 per sq ftPlus $150 plan review
Permit life
6 monthsWork must start within 6 months

Inside Mercedes city limits, building, electrical, plumbing, mechanical and gas permits come from the City’s Planning & Development Department at City Hall, and applications are filed through the City’s online permit form. A new house is charged $0.30 per square foot plus a nonrefundable $150 plan review fee, and starting work before the permit is issued can double the fee.

What requires a permit in Mercedes?

The City’s permit application and fee schedule cover these kinds of work:

Permit needed

  • New buildings, additions and remodels
  • Repairs and foundations
  • Residential re-roofs
  • Fences, decks, carports and storage sheds
  • Residential swimming pools
  • Driveways and curb cuts
  • Demolition and moving a building
  • Signs
  • Electrical, plumbing, mechanical and gas work, including irrigation systems
  • Digging or trenching in the public right-of-way
  • Water wells

No building permit

  • Moving, lowering or removing non-loadbearing walls inside a single-family home, under section 3.02.006 of the city code
  • Any electrical, plumbing or mechanical work done as part of that remodel still needs its own trade permit
  • The City still requires a building permit where life safety issues are evident

For a repair or remodel of a commercial building, the City needs an asbestos test report before it issues the permit.

Mercedes building department: who handles permitting

Planning & Development handles building permits, contractor registration, inspections, zoning, subdivisions, signs and right-of-way excavation for property inside Mercedes city limits. The Fire Marshal’s Office reviews building plans for fire safety and handles fire inspections.

Mercedes permitting contacts
DetailInformation
DepartmentPlanning & Development, City Hall
Phone956-565-3114, ext. 128, 129 or 130
Emailplanning@cityofmercedes.com
Address400 S. Ohio Ave., Mercedes, TX 78570
Fax956-565-8592
Fire Marshal’s Office105 North Ohio; 956-565-3114 ext. 312

Short on time to read all of this?

Get a free quote →

Mercedes permit forms and contractor registration

The City takes permit requests through online forms on its website rather than a separate portal:

  • Permit Application, one form for new work, additions, remodels, driveways, roofs, fences, moving, signs and repairs. It asks for the project value, the lot, block and subdivision, the existing and new use, and the foundation, wall and roof materials, and is signed by both the property owner and the contractor.
  • Demolition Application, the same form with demolition selected.
  • Contractor Registration, which costs $150, with a $100 renewal. General contractors, sign contractors, house movers and backflow testers register; the code exempts electrical, plumbing and mechanical contractors from the fee under state law. Attach a driver licence, any state master licence and proof of general liability insurance, and list the employees allowed to pull permits and request inspections.
  • ROW Excavation Permit, for digging, trenching or underground utility work in the public right-of-way.
  • Water Well Permit Application.

A permit expires if work does not start within 6 months of issue or stops for 6 months, and no building may be occupied before the Certificate of Occupancy.

Mercedes permit cost

Fees are set in Article A4.000 of the fee schedule in the city code. Homes pay a flat rate per square foot, and commercial and multifamily buildings are priced on construction value using the ICC building valuation table.

Mercedes building permit fees (Appendix A)
ProjectFee
New house or residential building$0.30 per sq ft
Residential plan review$150, nonrefundable, paid at submittal
Commercial, value up to $2,000$65
Commercial, $100,001–$500,000$932.25 for the first $100,000 plus $5.25 per extra $1,000
Commercial, over $1,000,000$5,263.25 for the first $1,000,000 plus $3.25 per extra $1,000
Commercial plan review35% of the building permit fee
Full remodel$300
Residential re-roof$200
Residential swimming pool$350
Carport, deck, foundation or general repairs$150 each
Fence or storage shed$50 each
Demolition, up to 1,000 sq ft$100 plus a $25 inspection fee; $20 per extra 500 sq ft
Certificate of Occupancy (not single-family)$75 to $400, by floor area

Not sure this scope needs a permit?

Get a free quote →

For example, a 2,000 sq ft house pays a $600 building permit fee and the $150 plan review fee, before trade permits. A commercial application is not treated as received until its plan review fee is paid. Energy code (RES-check) report review adds $20 for a home and $50 for other buildings. Every fee can be doubled when work starts before the permit is issued.

Mercedes trade permits

Electrical, plumbing, mechanical and gas permits are issued by Planning & Development. Each has a $45 base fee and a $50 re-inspection fee, plus item charges:

Mercedes trade permit fees (Appendix A)
PermitFee
Electrical$45 base; $4 per circuit; $25 new meter service; $15 temporary pole; $35 working clearance
Plumbing$45 base; $5 per fixture; $6 water heater; $50 irrigation system; $25 grease trap
Mechanical$45 base; $6 per ton for the first 4 tons, $3 per ton to 10 tons, $1.50 above
Gas$45 base; $30 gas line test; $10 gas line repair
Emergency inspection$30 with less than half a day’s notice; $80 after 4:30 p.m.

Rather talk it over?

Call 1-855-478-4290 →

Fire sprinkler and fire alarm systems are marked on the building permit application, and the Fire Marshal’s Office reviews the fire protection side of the plans and takes inspection requests through its online Fire Marshal Inspection Request form.

Mercedes permit application: how to apply step by step

1. Check zoning first

Planning & Development can confirm the property’s zoning; a new use may need a conditional use permit ($200), variance ($250) or rezoning ($300) first.

2. Register the contractor

Submit the online Contractor Registration with licences and insurance before the contractor applies for permits.

3. Fill in the online Permit Application

Give the project value, legal description, materials and scope, with the owner’s and contractor’s signatures.

4. Send plans and pay plan review

Pay the $150 residential plan review fee, or 35% of the permit fee for commercial work, and add the asbestos report for a commercial remodel.

5. Pay the permit fee and start within 6 months

Collect the permit before any work begins, because unpermitted work can be ordered removed as well as double-charged.

6. Call inspections and get the CO

Request each stage inspection from Planning & Development and do not occupy the building before the Certificate of Occupancy.

Inspections in Mercedes

Planning & Development inspects the work once a permit is issued. If construction has gone past the point where an inspection can still be done, the City can require the work to be removed and fine the owner or contractor. A failed first inspection carries a $35 re-inspection fee on the application form; the trade fee tables set re-inspections at $50.

Rather not deal with the building department?

Get a free quote →
Inspections the City lists for new residential construction
TradeInspections
BuildingFoundation, framing, insulation, infiltration, nail pattern, driveway if any, final
ElectricalRough-in, working clearance, final
MechanicalRough-in, vent, final
PlumbingUnderground rough, drain-waste-vent rough, final

The City’s shorter residential list also names the temporary power pole, plumbing and setbacks, the building sewer or yard line, and the curb break. Commercial jobs add tenant separation, fire wall, sprinkler, grease trap where there is commercial food equipment, re-energizing the electrical service, parking with accessible spaces and ramps, and landscaping.

Local details for building in Mercedes

Utility connections: new water, wastewater and trash accounts are opened in person at the Business Office in City Hall, Monday to Friday 8:00 a.m. to 5:00 p.m. Deposits are $100 for homeowners, $250 for renters and $500 for businesses, plus a $10 service fee, and an address that has never had service may also owe water meter, tap and water rights fees. A property without service for six months must be inspected before it is turned on.

Windstorm design: the city code does not apply windstorm and engineered design requirements to additions of 500 sq ft or less or to non-living accessory buildings such as storage buildings and carports.

Subdivisions: plats go through the City’s Subdivision Review application and checklist and the Standard Design Manual; the plat fee is $600 plus $30 per lot, and a preconstruction conference costs $100.

Mobile homes and signs: placement of mobile and manufactured homes follows the City’s Mobile Homes Ordinance, and signs need a sign permit under the Sign Ordinance.

Historic preservation: the City has a 7-member Historic Preservation Commission that meets quarterly at the Library, 434 S. Ohio Avenue, to protect local landmarks and districts.

Want this handled start to finish?

Get a free quote →

Texas building code

Texas has no single statewide building code: state law makes the International Residential Code the base code for homes in cities and the International Building Code the base for commercial buildings, with each city choosing the edition and its own amendments, while the National Electrical Code and the energy code apply statewide. Outside city limits most counties issue no building permits for homes. Texas building code rules

Mercedes permit search and official resources

Inspections are where schedules slip.

Get a free quote →

Frequently asked questions

How much is a building permit for a new house in Mercedes?

$0.30 per square foot plus a $150 nonrefundable plan review fee, so $750 for a 2,000 sq ft house before trade permits.

Who handles building permits in Mercedes?

The City’s Planning & Development Department at City Hall, 400 S. Ohio Ave., phone 956-565-3114 ext. 128, 129 or 130.

Do I need a permit to move an interior wall in my house?

Not for a non-loadbearing wall in a single-family home, under the city code; any wiring, plumbing or mechanical work involved still needs a trade permit.

How much is a fence or roof permit in Mercedes?

A fence permit is $50 and a residential re-roof is $200.

What happens if I start work without a permit?

The permit fee can be doubled, and if the work is past the point of inspection the City can order it removed and fine the owner or contractor.

How long is a Mercedes building permit good for?

Six months. It lapses if work does not start within 6 months of issue or is suspended for 6 months.

Which building codes does Mercedes use?

The city code lists the 2015 International codes and the 2014 National Electrical Code, and treats later editions as adopted once the City has assessed them.

Simplify Mercedes permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Texas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Mercedes sooner?

Let Alliance prepare, file, and track your Mercedes permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Mercedes permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.