Conroe issues building permits through the Building Inspections and Permits Department, and the operational fact that matters most right now is recent: as of December 8, 2025 the city uses OpenGov as its online portal for building permits and inspections. BluePrince portal access ended December 5, 2025.
That transition is a hard cutover, not a parallel run. All permit applications and inspection requests must be submitted through OpenGov, and contractors and applicants need to create an account in the new system to apply, schedule inspections, make payments, and track project activity.
The fee schedule moved at the same time. An updated schedule was approved by City Council effective November 13, 2025 and is reflected in the new permitting system, with fees generated once all required information is entered on an application.
Applies inside Conroe city limits in Montgomery County. The Woodlands, Willis, Montgomery, and Oak Ridge North sit nearby with their own arrangements, and unincorporated Montgomery County runs separately. Confirm the parcel before filing.
If you last permitted in Conroe before December 2025, your portal is gone. BluePrince access ended December 5, 2025 and OpenGov went live December 8. All permit applications and inspection requests now run through OpenGov, and an account has to be created before anything can be filed. The city publishes a how-to guide for account setup.
What requires a permit in Conroe?
Conroe requires a permit for construction and alteration work affecting structure, systems, or occupancy, reviewed against the codes the city has adopted — which include the 2012 International Residential Code and 2012 International Building Code as adopted by the State of Texas, the 2009 International Existing Building Code, and the 2015 International Energy Conservation Code under the State Energy Conservation Office.
Those editions are worth checking against your design assumptions. Several are older than what neighbouring jurisdictions enforce, and designing to a newer edition than the city has adopted creates its own review friction.
Permit required
- New residential and commercial construction, additions
- Structural and load-bearing alterations
- Interior remodels and commercial finish-out
- Reroofing and exterior envelope work
- Electrical, plumbing, and mechanical work
- Fences, accessory structures, and signs
- Pools and spas
- Change of occupancy or use; demolition
Typically exempt
- Painting, wallpapering, tiling, and floor coverings
- Cabinet and countertop replacement
- Routine maintenance not affecting structure or systems
- Like-for-like replacement of existing fixtures
Conroe building department: who handles permitting
The Building Inspections and Permits Department handles plan review, permit issuance, and construction inspections inside city limits, operating from 700 Metcalf Street.
Following the December 2025 transition, applications, inspection scheduling, payment, and project tracking all run through the OpenGov Applicant Portal. Permit and inspection fees may be paid online through Stripe within OpenGov, or in the office by cash, check, or credit card.
| Detail | Information |
|---|---|
| Authority | City of Conroe Building Inspections and Permits Department |
| Office | 700 Metcalf Street, Conroe, TX 77301 |
| Online portal | OpenGov Applicant Portal — live since December 8, 2025 |
| Previous portal | BluePrince — access ended December 5, 2025 |
| Payments | Stripe through OpenGov, or cash, check, or credit card in office |
| Checks | Payable to City of Conroe |
| Business hours | Monday–Thursday 7:30 a.m.–5:00 p.m.; Friday 8:00 a.m.–4:30 p.m. |
| Fee schedule | Updated and approved by City Council effective November 13, 2025 |
Create the OpenGov account before you need it. The city publishes a how-to guide for account creation, and because the cutover was complete rather than phased, a contractor who has not registered cannot file at all — regardless of prior history with the city.
Conroe permits: record types and what each covers
A building permit is one record among many. Building Inspections issues work under separate record types inside OpenGov, and filing under the wrong one is a rejection rather than a correction. Conroe adds a gate ahead of the record type that is unusually recent: an OpenGov account, because the city cut over completely from BluePrince in December 2025 and no legacy path remains.
Residential permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | New dwellings, additions, and accessory structures over the exempt threshold | Full plan review (structural, energy, zoning) | Valuation-based |
| Renovation / alteration | Structural or load-bearing changes, layout changes, substantial repair | Plan review scaled to scope | Valuation-based |
| Reroof | Roof covering replacement and most major roof repair | Product approval review; dry-in and nail-off inspections | Valuation or squares |
| Solar photovoltaic | Rooftop or ground-mount PV installation or replacement | Structural plus electrical review | Flat or system-size based |
| Solar thermal | Passive water heating or pool heating systems | Plumbing and structural review | Flat or per-permit minimum |
| Electrical | Service changes, panel upgrades, new circuits, most wiring alterations | Trade review; filed against the building permit | Per-permit minimum or per-device |
| Plumbing | New piping, repipes, water heaters, fixtures, gas piping | Trade review; filed against the building permit | Per-permit minimum or per-fixture |
| Mechanical / HVAC | Changeouts that are not like-for-like, ductwork, refrigeration | Trade review; filed against the building permit | Per-permit minimum or per-unit |
| Windows and doors | Replacement units and opening protection | Product approval review for wind-borne debris | Valuation or per-opening |
| Pool and spa | In-ground and above-ground pools, spas, barrier and enclosure work | Plan review plus barrier and electrical bonding | Valuation-based |
| Fence and accessory | Fences, sheds, decks, and carports over the exempt threshold | Zoning plus structural where applicable | Flat or valuation-based |
| Demolition | Full or partial demolition of a structure | Utility disconnect verification required | Flat |
Commercial permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | Ground-up commercial, industrial, and multifamily | Full multi-discipline plan review | Valuation-based |
| Tenant improvement | Interior build-outs and suite fit-ups | Plan review across affected disciplines | Valuation-based |
| Renovation / alteration | Structural, envelope, or system changes to an existing building | Plan review scaled to scope | Valuation-based |
| Change of use | Converting a building from one occupancy classification to another | Zoning, life-safety, and accessibility review | Valuation or flat |
| Reroof | Commercial roof covering replacement | Product approval review plus fire review where applicable | Valuation or squares |
| Solar photovoltaic | Commercial rooftop, carport, and ground-mount PV | Structural, electrical, and often fire review | Valuation or system-size based |
| Electrical | Service, distribution, and branch circuit work | Trade review | Valuation or per-device |
| Plumbing | Supply, waste, vent, and gas systems | Trade review | Valuation or per-fixture |
| Mechanical / HVAC | Rooftop units, ductwork, exhaust, and refrigeration | Trade review | Valuation or per-unit |
| Fire protection | Sprinkler, standpipe, alarm, and suppression systems | Fire prevention plan review | Valuation or per-device |
| Sign | Wall, monument, and illuminated signage | Zoning plus electrical where illuminated | Flat or per-sign |
| Demolition | Full or partial commercial demolition | Utility disconnect and environmental clearance | Flat or valuation-based |
Residential
- Single-discipline review in most cases
- Master permit with trades filed against it
- Owner-builder route exists but carries statutory affidavits
- Product approval drives roofing and opening protection
Commercial — multi-discipline
- Concurrent review across building, fire, and zoning
- Signed and sealed plans across every affected discipline
- Accessibility and life-safety review attach to change of use
- Impact and concurrency fees can apply on top of permit fees
Solar permits in Conroe
Solar is permitted as its own record type in most Texas jurisdictions rather than rolled into a general building permit, and residential and commercial photovoltaic are usually separate records with different document sets. Solar thermal — passive water and pool heating — is a third, distinct record.
A photovoltaic submittal is reviewed on two tracks at once: structural (roof load path, attachment spacing, uplift) and electrical (conductor sizing, rapid shutdown, point of interconnection). A single-line diagram and a signed and sealed structural attachment detail are the two attachments most often missing on a first submittal.
Texas HOA law is narrower than most installers assume. Under Tex. Prop. Code §202.010 a property owners' association cannot prohibit a solar energy device outright, and any dedicatory provision that does is void — but the statute expressly preserves the association's right to require prior architectural approval and to impose placement and appearance conditions. Approval cannot be unreasonably withheld, and conditions that cut estimated production materially are not enforceable. Practically: get the HOA submittal moving in parallel with the permit rather than treating it as optional.
Texas SB 1202 changed this materially on September 1, 2025. Codified at Tex. Local Gov't Code §247.0025, it lets authorized third parties — licensed engineers, electrical inspectors, and Texas master electricians — perform the plan review and inspections for a home backup power installation instead of the jurisdiction. The definition covers generators, energy storage systems, and associated equipment serving a one- or two-family dwelling at 600 volts or less. Construction may begin on submission of the notice, the third party has 15 days to report results, and the regulatory authority must issue the approval on a short statutory clock. Jurisdictions that process work this way do not review or inspect it, and responsibility for code compliance sits with the third-party reviewer and the contractor of record. Note the boundary: it is a backup-power provision, so a straight grid-tied photovoltaic array with no storage is not automatically inside it, and separate electrical or plumbing permits are still generally required for service release. Confirm how Conroe is administering SB 1202 before assuming either path.
Utility interconnection runs parallel to the building permit, not inside it. Permission to Operate is issued by the utility after the final electrical inspection clears, and in deregulated territory the interconnecting utility is the wires company rather than the retail provider.
Roofing permits in Conroe
A roof covering replacement requires a permit in most Texas municipalities. Repairs below the local threshold may not, but the threshold is scope-specific and set locally — confirming it with the building department before tear-off is cheaper than an after-the-fact permit.
Texas has no statewide product approval system, so there is no central listing to check a roofing product against. Compliance runs against the code edition the jurisdiction has actually adopted and the local amendments layered on top of it. Those amendments are where the binding requirements live, and they change from city to city inside the same county.
Texas Department of Insurance windstorm certification — the WPI-8 process — applies only in the designated seaward counties along the Gulf. Conroe is not a seaward county, so WPI-8 certification does not attach here and roofing contractors licensed for inland work do not need TDI appointment for this jurisdiction.
Hail is the governing weather risk across most of inland Texas, not wind. Impact-resistant Class 3 and Class 4 shingles carry insurance premium credits from most carriers, and under Tex. Prop. Code §202.011 a property owners' association cannot prohibit shingles that are wind or hail resistant, or that improve energy efficiency, provided they otherwise match the roof's appearance requirements.
Reroof inspections are typically sequenced by the jurisdiction, commonly a decking or nail-off inspection before the covering goes down and a final afterward. Covering the deck before the required intermediate inspection means tearing it back open.
Texas has no statewide building code and no statewide general contractor license. The code edition and the amendments that bind your submittal are adopted locally, and contractor registration with the jurisdiction is frequently the gate that has to clear before a record type can even be filed. On commercial work, projects over the statutory threshold also register separately with TDLR for Texas Accessibility Standards review, which runs outside the building permit entirely.
Conroe sits in Montgomery County north of Houston at roughly 105 to 115 mph ultimate design wind speed under the adopted code, inland of the TDI designated catastrophe area and outside any windstorm certification requirement — unlike the coastal Houston-area jurisdictions further south. Hail and tropical remnants drive claims here rather than direct hurricane wind.
Conroe permit cost and fees
Conroe permit fees follow the city fee schedule updated and approved by City Council effective November 13, 2025, now reflected within the OpenGov permitting system. Fees are generated once all required information is entered on the application.
Because the schedule changed recently, prior-project figures are not a reliable guide. Confirm current fees in the portal rather than budgeting from a Conroe job that predates November 2025.
| Fee component | How it works |
|---|---|
| Building permit | Per the fee schedule effective November 13, 2025 |
| Trade permits (E / P / M) | Separate fee per trade, filed by the licensed contractor |
| Fee generation | Fees generate in OpenGov once required application information is entered |
| Payment | Stripe through the OpenGov portal, or in office by cash, check, or credit card |
| Re-inspection | Charged when a checkpoint fails and is re-requested |
| Certificate of Occupancy | Required before occupancy or business opening on qualifying work |
Want a precise number for a specific Conroe project? Send us the scope and valuation and we’ll return a fee estimate against the current schedule alongside a filing timeline.
Conroe trade permits
Electrical, plumbing, and mechanical work each need their own permit pulled by the state-licensed contractor for that trade, filed through OpenGov. Texas licenses the trades and does not license general contractors.
Electrical
Service and panel work, new circuits, solar PV, EV charging, and backup power — performed by a TDLR-licensed electrician.
Plumbing
New plumbing, repipes, water heaters, fixtures, and gas piping — performed by a TSBPE-licensed plumber.
Mechanical / HVAC
Installations, non-like-for-like changeouts, ductwork, and venting, reviewed against the adopted mechanical and energy codes.
Specialty
Fences, signs, pools, accessory structures, and demolition each run their own record and review path through the portal.
Conroe permit application: how to apply step by step
Verify the work needs a permit and the parcel is inside Conroe rather than unincorporated Montgomery County or a neighbouring jurisdiction.
Visit the OpenGov Applicant Portal and register as a contractor or applicant. The city publishes a how-to guide. This is mandatory since the December 2025 cutover.
Conroe enforces the 2012 IRC and IBC, 2009 IEBC, and 2015 IECC. Design to those rather than to a newer edition used elsewhere in the metro.
File with the plan set and supporting documents. Fees generate once all required information is entered.
Pay through Stripe in the portal or in the office by cash, check, or credit card. Checks are payable to City of Conroe.
All inspection requests must be submitted through the portal. Clear the sequence to final and obtain a certificate of occupancy where required.
Inspections in Conroe
All inspection requests must be submitted through the OpenGov Applicant Portal, which also carries permit status, payments, and project activity tracking. The Building Inspections department performs construction inspections against the adopted codes.
Because the portal changed in December 2025, inspection history and open permits from the BluePrince era are worth confirming with the department directly on any property with prior permitting activity.
Keep the permit posted and approved plans on site, and address correction notices before requesting a re-inspection.
Conroe permit search and official resources
- City of Conroe — permit and inspection information
- Conroe — permit applications and information
- Texas Department of Licensing and Regulation
- Texas State Board of Plumbing Examiners
Frequently asked questions
Who issues building permits in Conroe?
City of Conroe Building Inspections and Permits Department issues building permits for everything inside Conroe city limits, handling plan review, permit issuance, and construction inspections. Work outside the city limits falls to Montgomery County, and Texas counties have sharply limited building authority in unincorporated areas.
How do I get a permit in Conroe?
Confirm the scope triggers a permit and that zoning allows it, prepare the plan set and site plan, file through OpenGov Applicant Portal with contractor licensure in place, respond to plan review comments, pay fees and take issuance, then run the inspection sequence through final. Contractor credentialing is the step most often missed and it blocks everything downstream.
What codes apply in Conroe?
Texas has no mandatory statewide building code. Municipalities adopt and amend model codes themselves, so Conroe enforces 2012 IRC and IBC (state adopted), 2009 IEBC, 2015 IECC. The local amendments are where the binding requirements live, and they differ from neighboring cities working off the same model code. Confirm the current adopted editions with the department before designing to a specific one.
Which portal does Conroe use for permits?
OpenGov, effective December 8, 2025. Contractors and applicants create an account and can submit permit applications, schedule inspections, make payments, and track project activity directly through the portal. All permit applications and inspection requests must be submitted through OpenGov. BluePrince portal access ended December 5, 2025, so there is no legacy route — if you have not created an OpenGov account, you cannot file.
What building codes does Conroe enforce?
The 2012 International Residential Code and 2012 International Building Code as adopted by the State of Texas, the 2009 International Existing Building Code, and the 2015 International Energy Conservation Code under the State Energy Conservation Office. Because Texas has no mandatory statewide building code beyond the state-adopted baseline, editions vary between neighbouring cities — confirm Conroe’s current adopted set with the department before designing.
Is my property in Conroe or unincorporated Montgomery County?
Montgomery County has grown quickly along the I-45 corridor and the answer is not reliably visible from a mailing address. Conroe permits and inspects inside its city limits through Building Inspections and the OpenGov portal, while unincorporated Montgomery County operates under the standard Texas county framework with far narrower authority over residential construction. The Woodlands is a third arrangement again — a special-purpose township rather than a general-law city. Confirm the parcel before filing.
Do I need a permit to install solar panels in Conroe?
Yes. Photovoltaic installations in Conroe are permitted under a dedicated solar record type reviewed on both a structural and an electrical track. Solar thermal — passive water and pool heating — is a separate record. Under Tex. Prop. Code §202.010 a homeowners' association cannot ban a solar energy device outright, but it may still require prior architectural approval and impose reasonable placement conditions, so run the HOA submittal alongside the permit. Since September 1, 2025, Tex. Local Gov't Code §247.0025 (SB 1202) also permits third-party plan review and inspection of home backup power installations — generators and energy storage for one- and two-family dwellings at 600 volts or less — in place of jurisdiction review. Utility interconnection and Permission to Operate still run in parallel.
Does a roof replacement require a permit in Conroe?
Yes, in most cases. A roof covering replacement requires a permit in most Texas municipalities including Conroe, though minor repairs can fall below the local threshold. Texas has no statewide product approval system and no central product listing, so compliance runs against the locally adopted code edition and its local amendments. Hail rather than wind is the governing risk inland, and Tex. Prop. Code §202.011 bars an HOA from prohibiting wind or hail resistant shingles.
What is the difference between a residential and a commercial permit in Conroe?
Residential work is generally a single-discipline review filed as a master permit with trades filed against it. Commercial work in Conroe runs concurrent review across building, fire, and zoning, requires signed and sealed plans for every affected discipline, and can carry impact and concurrency fees on top of permit fees. Change of use adds accessibility and life-safety review.
Do trade permits need to be pulled separately in Conroe?
Yes in most cases. Electrical, plumbing, and mechanical work is permitted separately by the licensed contractor for each trade and filed against the master building permit. Each trade permit carries its own fee and its own inspection sequence.
What happens if I file under the wrong permit type in Conroe?
The application is rejected rather than corrected. Conroe Permits and Licensing closes the record, the filing is resubmitted under the correct record type, and the review clock restarts from zero. Confirming the record type before filing is the cheapest step in the entire process.
Can I apply for all Conroe permit types online?
Yes, and it is mandatory. Since December 8, 2025 all permit applications and inspection requests must be submitted through the OpenGov Applicant Portal, where you can also make payments and track project activity. Payment runs through Stripe in the portal, or in office by cash, check, or credit card with checks payable to City of Conroe. The city publishes a how-to guide for creating an account.
Simplify Conroe permitting with Alliance Permitting
A complete portal cutover in December 2025, a fee schedule that moved a month earlier, and adopted code editions that differ from neighbouring cities — Conroe is a jurisdiction where recent institutional knowledge matters more than long experience. Alliance Permitting is a permit expediter for Conroe: we file in the current system against the current schedule.
Trusted by leading builders and brands — including Dream Finders Homes, Tesla, Verizon, Hyatt, and Sunnova.
Contractors and builders choose Alliance for Conroe because we deliver:
- Local expertise — we know the OpenGov workflow and the adopted code editions Conroe actually enforces.
- Complete oversight — track every permit and inspection across all your jobs in one place.
- Error-free submissions — AI pre-checks plus expert review catch issues before they become correction cycles.
Alliance Permitting is a permit documentation and submission company: we prepare your paperwork, file it correctly, and coordinate with the authority having jurisdiction through issuance. We are not a contractor and do not perform licensed plan review or inspections; that work stays with your team and the jurisdiction.
Ready to break ground in Conroe sooner?
Let Alliance prepare, file, and track your Conroe permits while you stay focused on building. Get a free, no-obligation quote today.
More Texas permitting guides
This guide is provided by Alliance Permitting for general informational purposes and reflects publicly available information believed accurate as of July 2026. Permit requirements, fees, and processes change; always confirm current details with City of Conroe Building Inspections and Permits Department before filing. This is not legal advice.