Clay County’s Zoning Administrator in Vermillion issues building permits for rural Clay County and for the joint zoning area around Vermillion; the cities of Vermillion, Wakonda and Irene issue their own.

Authority: Clay County Planning & ZoningPermit: County zoning building permit; 2009 IBC in the Vermillion joint areaPhone: 605-677-7145
County permit
$75 + $2 per $1,0002026 price chart
Office
211 W Main St, Suite 205Vermillion; phone or text 605-677-7145
Joint zoning area
About 16 sq miAround Vermillion, permits from the County
Rural address
$100911 application for a new site

Outside the cities, Clay County building permits are issued by the County Zoning Administrator, 211 W Main Street, Suite 205, Vermillion (phone or text 605-677-7145). The 2026 fee is $75 plus $2 for every $1,000 of construction cost, so a $300,000 house costs $675, plus $100 for a 911 address if the site has none. Vermillion, Wakonda and Irene issue permits inside their own limits.

What needs a building permit in rural Clay County?

The County zoning ordinance (the 2013 revision, compiled through Ordinance 2024-04) forbids any enlargement, extension, conversion or structural alteration of a building without a building permit from the Zoning Administrator. The County permit form covers these kinds of development:

County building permit

  • New homes (separate New Home Building Permit form)
  • Accessory structures
  • Agricultural structures
  • Commercial and industrial buildings
  • Additions and remodels
  • Moving a building
  • Demolition

Related County approvals

  • 911 rural address for a new site ($100)
  • Conditional use permit ($200)
  • Variance ($100)
  • Rezoning or ordinance amendment ($250)
  • Plat application ($100)
  • Floodplain review in special flood hazard areas

In the joint zoning area around Vermillion, a permit is needed to build, alter or repair a building or structure, except for minor nonstructural changes that do not change the use.

Who issues building permits in each part of Clay County?

Noah Westergaard is the County’s Planning and Zoning Administrator and also serves as Floodplain Administrator. The three incorporated places in the county run their own permits:

Short on time to read all of this?

Get a free quote →
Building permit offices in Clay County
AreaWho issues building permitsContact
Unincorporated Clay CountyCounty Zoning Administrator (building permit under the County zoning ordinance)211 W Main Street, Suite 205, Vermillion; 605-677-7145
Joint zoning area (about 16 sq mi around Vermillion)County Zoning Administrator, under the Joint Zoning Regulations; copies of each application go to the City of Vermillion within five working daysSame County office
Vermillion (pop. 11,720)City of Vermillion Code Enforcement Department; applications through GovWellBuilding Official, 605-677-7088
Wakonda (338)City; the building permit is signed by a board member or the Finance Officer, and code enforcement is contracted to Code Enforcement Specialists, LLCCity Hall, 111 Ohio Street; 605-267-3118
Irene (195 in Clay County; the city also extends into Turner and Yankton counties)City Hall, under the City’s zoning ordinance110 S Till Avenue; 605-263-3476

Wakonda’s City Hall is open Wednesday 8:30 a.m. to 5:30 p.m. and Thursday and Friday 8:30 a.m. to 2:00 p.m. Irene’s website lists City Hall hours of 8:00 a.m. to 5:00 p.m. on one page and 7:30 a.m. to 4:00 p.m. on another.

Clay County permit forms and the Planning Commission

The County posts 2026 versions of its forms on the Zoning page:

  • Clay County Building Permit: owner or agent, parcel ID and short legal description, type of development, a description with build plans attached, and the cost of construction. The form prints the minimum lot sizes and setbacks for each district.
  • New Home Building Permit: adds the house description and a section showing that the water and electrical utilities were contacted and approved service.
  • 911 Application: assigns a rural address; the County notifies Equalization, the 911 dispatcher and the post office and orders the address sign.
  • Plat, rezone and conditional use applications for the Planning Commission.

The County posts an application cut-off date about three weeks before each Planning Commission meeting (October 26 for the November 16 meeting, November 30 for December 21), and asks applicants to contact the Zoning Administrator by 9:00 a.m. on the Thursday before the meeting to be added to the agenda; if nothing is on the agenda the meeting is cancelled. Remaining 2026 County meetings are October 20, November 16 and December 21 at 5:15 p.m.; joint area meetings are November 23 and December 21 at 5:30 p.m.

Not sure this scope needs a permit?

Get a free quote →

Clay County permit fees (2026 price chart)

Clay County Planning & Zoning fees, 2026
Item2026 fee
Building permit$75 plus $2 per $1,000 of estimated construction cost
911 address application$100
Conditional use permit$200
Variance application$100
Rezone or amendment petition$250
Board of Adjustment appeal$100
Plat application$100

Worked example: a new house with an estimated cost of $300,000 pays $75 plus 300 × $2, or $675. If the site still needs a rural address, the New Home form adds $100, for $775.

City fees: Wakonda’s building permit form charges $5 per $1,000 of project cost. Irene sets its fees by City Council resolution, with the schedule held by the City’s authorized official at City Hall. Vermillion’s 2026 Comprehensive Fee Schedule uses a value-based table, starting at $30 for work under $1,000.

Electrical, plumbing and septic in Clay County

The County’s permit form makes the applicant acknowledge that state wiring and plumbing inspections are required where they apply. Electrical permits and inspections come from the South Dakota Electrical Commission and plumbing from the South Dakota Plumbing Commission, both in the countryside and in the cities; Clay County is in the Plumbing Commission’s Southeast region (605-280-9243). The County’s 2011 building code ordinance for the joint area repeats that electrical and plumbing permits and inspections are obtained through the two state commissions.

Rather talk it over?

Call 1-855-478-4290 →

In the Aquifer Protection Overlay zones the zoning ordinance requires new or replacement septic tanks and drain fields to meet the state rules (the ordinance names the former Department of Environment and Natural Resources, now the Department of Agriculture and Natural Resources).

What to bring for a Clay County permit

  • The completed County permit form (or the New Home form), with the parcel ID and short legal description
  • A description of the work and the build plans
  • A site plan showing the lot dimensions and the size, shape and position of the building, so setbacks can be checked
  • The estimated construction cost, which sets the fee
  • For a new house: confirmation from the water and electric utilities, and a 911 application if there is no address yet
  • For a new house in the A-1 Agricultural or NRC district: a Right to Farm Notice Covenant filed with the Register of Deeds before the permit is issued

In the joint area, someone applying for the owner may be asked for a sworn affidavit from the owner confirming the work is authorized.

Getting a Clay County building permit, step by step

1. Place the parcel

Check whether it is in Vermillion, Wakonda, Irene, the joint zoning area or the rural county.

2. Check lot size and setbacks

Compare the lot with the district minimums printed on the permit form; apply for a variance or conditional use if needed.

3. Arrange address and utilities

For a new home, file the 911 application and contact the water and electric providers.

4. Record the covenant

In the A-1 or NRC district, file the Right to Farm covenant before a new house permit can be issued.

5. Submit and pay

Send the form, plans and fee to the Zoning Administrator at 211 W Main Street, Suite 205.

6. Build on time

Start within 90 days, finish the bulk of the work within a year, and book the state electrical and plumbing inspections.

Rather not deal with the Clay County building department?

Get a free quote →

Inspections and expiry of County permits

A County permit expires if the work has not begun within 90 days or is not substantially complete within one year of issue. The County Assessor’s office may visit when the project is finished to review it for assessment.

In the joint zoning area the Zoning Administrator is charged with making the inspections needed to confirm compliance, and the County’s Ordinance 2011-05 adopted the 2009 International Building Code there, naming the City of Vermillion Code Compliance Office as the enforcement agency. Electrical work gets a state rough-in and final inspection; the Plumbing Commission asks for at least 72 hours’ notice.

Local Clay County details

Floodplain: the 2020 Flood Damage Prevention Ordinance (Ordinance 2021-01) makes the Zoning Administrator the Floodplain Administrator. The Zoning page also links FEMA guidance for homeowners after a flood.

Joint zoning with Vermillion: the joint area has its own zoning ordinance and map, adopted with the City of Vermillion, and its own Planning Commission meeting schedule. Building permits there still come from the County.

Right to farm: anyone building a new house in the A-1 or NRC district records a covenant acknowledging nearby farm operations, such as crop work, livestock production and spraying.

Wakonda timing: Wakonda’s permit requires construction to start within 60 days of approval, or a new application is needed.

South Dakota building code

South Dakota has no state-enforced building code: each city or county decides whether to adopt one. The state Electrical and Plumbing Commissions permit and inspect those trades, except in a few cities that run their own inspections. South Dakota rules

Official Clay County permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Inspections are where schedules slip.

Get a free quote →

Clay County building permit FAQs

Who issues building permits in Clay County?

The County Zoning Administrator (605-677-7145) for rural land and the joint zoning area around Vermillion. Vermillion, Wakonda and Irene issue permits inside their city limits.

How much is a Clay County building permit?

$75 plus $2 per $1,000 of estimated construction cost under the 2026 price chart, so a $300,000 home costs $675. A new rural address adds $100.

How long do I have to start building?

Ninety days from issue, and the work must be substantially complete within one year or the permit expires.

Does the County inspect electrical and plumbing work?

No. The South Dakota Electrical Commission and Plumbing Commission permit and inspect that work.

Do I need anything extra to build a house on farmland?

Yes. In the A-1 Agricultural and NRC districts, a Right to Farm Notice Covenant must be filed with the Register of Deeds before the County issues the permit.

Who handles permits just outside Vermillion?

In the joint zoning area, apply to the Clay County Zoning Administrator, who shares each application with the City of Vermillion.

Simplify Clay County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in South Dakota. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Clay County sooner?

Let Alliance prepare, file, and track your Clay County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Clay County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.