In Sandy, the City’s Building Division reviews plans, issues permits and inspects structural, mechanical and plumbing work, while Clackamas County issues and inspects every electrical permit in the city. Under the Master Fee Schedule dated July 1, 2026, the building permit minimum is $98 and plan review adds 70% of the permit fee. New sewer connections are restricted by a development moratorium that the City Council has renewed in stages since October 2022.
The division is part of the Development Services Department at City Hall, 39250 Pioneer Boulevard, open Monday to Friday from 8 a.m. to 4 p.m. (503-489-2173, building@ci.sandy.or.us). Terre Gift is the Building Official, and the department is led by Development Services Director Kelly O’Neill Jr. Sandy, a Clackamas County city, had 13,323 residents in the Census estimate for 2025.
The City permits land inside Sandy’s city limits only; Clackamas County Building Codes in Oregon City permits the unincorporated land around it and sells the electrical permits for Sandy itself.
What requires a building permit in Sandy?
Sandy’s own pages explain the common cases, but some of the FAQ answers predate the 2026 Oregon Residential Specialty Code, whose chapter 1 has been mandatory since October 1, 2026. Where they differ, the lists below follow the state code and say what the City’s page states. The City’s plumbing page is specific: a permit is needed to replace a water heater or underground piping, alter piping inside a wall, ceiling or floor, add a fixture where none was, install a new backflow device, or after an emergency repair to more than 5 feet of pipe.
Permit required
- New houses, additions, ADUs and structural alterations, priced on project value
- Accessory buildings over 200 sq ft or taller than 15 feet to the average roof height; the City’s FAQ, using older wording, also lists every garage or carport able to hold a vehicle
- Patio or porch covers over 200 sq ft, or closer than 3 feet to a lot line
- Fences over 7 feet, and any fence that serves as a pool barrier
- Plumbing changes inside walls, water heater swaps and new fixtures
- Grading and erosion control work, demolition and manufactured home placement, each on its own City form
No permit
- A nonhabitable one-story detached accessory building of 200 sq ft or less and 15 feet or less in height
- Decks and porches no more than 30 inches above grade; the City’s FAQ still says decks over 200 sq ft need a permit
- Uncovered patios, and above-grade or on-ground pools; in-ground pools at houses need no building permit unless a local ordinance requires one
- Replacing a sink, toilet or faucet not concealed in a wall, a hose bibb or a water filter
Short on time to read all of this?
Get a free quote →What Sandy decides and what the state holds
Permit exemptions come from sections R101.2.2 and R105.2 of the 2026 Oregon Residential Specialty Code; its technical chapters become mandatory on April 1, 2027, and the 2025 Oregon Structural Specialty Code has governed commercial work since April 1, 2026. Sandy sets its fees and SDCs, its development code (setbacks, design standards, fence heights, construction hours), the sewer moratorium and its business license rules, which do not accept the Metro license.
Oregon’s building code and its exemptions are the same in Sandy as everywhere in the state, and an exemption from the building permit is not an exemption from zoning, land use or a trade permit. Site snow, wind and seismic values come from the state’s Oregon Design Criteria Hub. How Oregon’s statewide code works
Sandy building department: who handles permitting
Sandy’s Building Division is a small office: the Development Services Director, the Building Official, a permit technician and an executive assistant. Planning in the same department handles land use, design review and the residential design standards. Clackamas County Building Codes handles all electrical work for Sandy, and the State of Oregon runs the ePermitting system the City uses.
| Detail | Information |
|---|---|
| Building Division | City Hall, 39250 Pioneer Blvd., Sandy, OR 97055 |
| Phone and email | 503-489-2173; building@ci.sandy.or.us |
| Office hours | Monday to Friday, 8 a.m. to 4 p.m. |
| Building Official | Terre Gift, 503-489-2164 |
| Inspection requests | Oregon ePermitting, the ORinspect app or 1-888-299-2821 |
| Electrical permits | Clackamas County, 150 Beavercreek Road, Oregon City; 503-742-4240; Monday to Thursday, 8 a.m. to 4 p.m. |
Permit types
Residential permits
Contractors can buy plumbing, mechanical and structural permits that need no plan review straight through Oregon ePermitting, 24 hours a day. Work that needs plan review uses the City’s 2026 application forms, which carry the Development Services Department’s address and phone and ask for a valuation that covers equipment, materials, labor, overhead and profit. A new house package draws on the July 2025 residential application checklist, the September 2025 site plan checklist, the residential design standards worksheet, a driveway slope worksheet, a residential erosion control plan agreement, the January 2026 subcontractor list, the moisture content sheet, the City’s design criteria and its engineer or architect signature requirement. An application expires if the permit is not picked up within 180 days of being deemed ready to issue.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial plan review costs 70% of the permit fee, the same rate as for houses, plus 55% for fire and life safety review and 1% for seismic review where they apply. Commercial mechanical work is priced on its own valuation table, from $98 for jobs up to $1,000, and medical gas piping and fire sprinkler or alarm systems use the structural valuation table. Phased permits cost $287 plus 10% of the total project permit fee, up to $1,500 a phase, and deferred submittals 10% of the permit fee for the deferred portion, at least $250. Permanent signs need a sign permit ($87 plus a fee on the sign’s value from the building table).
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
Land use comes first, and that is where the moratorium bites: subdivisions, most partitions, ADUs, duplex conversions and design reviews that add sewer flow cannot be accepted while it lasts. Remodels and additions that do not increase sewer flow are unaffected, according to the City’s moratorium FAQ, and development served by an on-site septic system is exempt from the application ban; septic permits in Clackamas County come from the County’s Septic and Onsite Wastewater Program as DEQ’s agent. Erosion control needs its own permit ($172 for a single-family dwelling plus $98 plan review). The City’s FAQ adds a zoning rule for backyards: a pool, hot tub or other outdoor water deeper than 18 inches must be enclosed by a fence or railing 4 to 8 feet high with self-closing, self-latching gates. On FEMA’s list of flood-program participants, Sandy’s effective map is the one issued January 18, 2019.
Sandy permit costs and fees
Building fees are in section 3 of the City’s Master Fee Schedule dated July 1, 2026, which the City says is usually updated once a fiscal year. Valuation follows the ICC Building Valuation Data table in force each April 1. In the schedule’s words, all building, plumbing and mechanical permits are subject to a State of Oregon surcharge of 12%, payable with the permit and subject to change at the State’s discretion.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee or rule |
|---|---|
| Valuation up to $500 (minimum) | $98 |
| $500.01 to $2,000 | $98 plus $5 per added $100 |
| $2,000.01 to $25,000 | $173 plus $13 per added $1,000 |
| $25,000.01 to $50,000 | $472 plus $10 per added $1,000 |
| $50,000.01 to $100,000 | $722 plus $7 per added $1,000 |
| Over $100,000 | $1,072 plus $6 per added $1,000 |
| Plan review | 70% of the permit fee; $150 for a simple one- or two-family dwelling plan |
| Plumbing and mechanical plan review | 40% of their permit fees |
| Technology fee | 3% of the total Building Division fees |
| New house plumbing | $515 one bath, $628 two, $745 three |
| Reinspection | $98 each; after-hours inspections $136 an hour, two-hour minimum |
| Temporary certificate of occupancy | $287 a month |
| Prescriptive solar PV | $183 |
Worked example. A $60,000 garage addition falls in the $50,000.01 to $100,000 band: $722 plus 10 × $7 ($70) makes a building permit fee of $792. Plan review at 70% adds $554.40, the 12% state surcharge on the permit fee is $95.04, and the 3% technology fee on the City’s $1,346.40 is $40.39, for $1,481.83 before plumbing, mechanical or County electrical permits.
A new home also pays system development charges: $12,766 for water per equivalent dwelling unit, $13,163 for wastewater per equivalent residential unit, $12,117.67 for parks and $9,716 for streets per single-family dwelling, before meter costs. The City posted notice of a December 7, 2026 public hearing on revised wastewater SDCs. Under the City’s refund policy, no fee of $300 or less is refunded and requests must come within 180 days.
Trade permits and who may pull them
Sandy issues plumbing and mechanical permits; simple plumbing repairs are priced per fixture ($30 each, $98 minimum), and most residential mechanical items cost $19 to $33 each. Electrical permits are handled entirely by Clackamas County, whose page notes that state law allows no electrical work until a permit has been issued. Sign and fire system permits go through the Building Division.
Rather not deal with the building department?
Get a free quote →Who may do the work
- The City’s plumbing page: either hire a licensed plumbing contractor or, as the owner, do it yourself; friends, tenants and general contractors may not
- Plumbing contractors need a CCB license and journeyman plumbers a BCD license
- An owner may do electrical work on their own home only if it is not for sale, rent or lease, with a County permit
Sandy rules
- Contractors need a City of Sandy business license; Sandy does not accept the Metro license
- Homeowners are exempt from the business license
- The contractor pulling a permit must obtain all permits for its work
- Agree in advance who books each inspection
How to apply for a Sandy building permit
Ask Planning whether the project needs land use review and whether it adds sewer flow; projects that do may have to wait for allocated capacity.
Use the residential application checklist, the site plan checklist and the design standards worksheet, with engineering where the City’s signature requirement calls for it.
Licensed contractors buy no-review permits in Oregon ePermitting; plan-review applications go in on the City’s 2026 forms to the Development Services Department.
Plan review is 70% of the permit fee; the 12% state surcharge is paid with the permit.
Electrical work needs its own permit from Clackamas County before any wiring starts.
Collect it within 180 days of the ready-to-issue notice, then schedule inspections in ePermitting.
Review, corrections and what causes delay
Sandy does not publish a plan review target. Several steps outside the building code can hold a project: land use and design review, sewer capacity under the moratorium, and the engineering, driveway slope and erosion control sheets in a new house package. Plans revised after review cost $115 an hour in added review. Staff may ask for more information on any ePermitting application, and a ready permit not collected within 180 days lapses.
Inspections in Sandy
Sandy inspects Monday to Thursday, 9 a.m. to 4 p.m. Inspections are booked in Oregon ePermitting at BuildingPermits.Oregon.gov, through the ORinspect app or by phone at 1-888-299-2821; the State, not the City, supports the system (503-373-7396). Add notes such as a contact name or preferred time to the request. For plumbing, new water piping must be operational and exposed, and inspectors may ask for drain lines to be plugged and filled with water.
Want this handled start to finish?
Get a free quote →A reinspection costs $98, and inspections outside normal hours $136 an hour with a two-hour minimum. Electrical inspections are booked with Clackamas County under its own permit. Homeowners may work on their property from 7 a.m. to 10 p.m. on weekdays and 8 a.m. to 10 p.m. at weekends, per the City’s construction hours policy.
Sandy permit search and official resources
Sandy permits issued through Oregon ePermitting can be found with the portal’s public permit search, which shows status and inspection results. For older paper files, contact the Building Division at 503-489-2173.
- Sandy Building Division
- Building permit applications (updated 2026)
- Residential building permit forms, new construction
- Plumbing permits: when you need one
- Building contact information
- Master Fee Schedule, July 1, 2026
- Building policies, including refunds
- Pause on new sewer connections: FAQ
- Resolution 2026-04, development moratorium
- Wastewater SDC hearing notice, December 7, 2026
- Clackamas County electrical permits
- 2026 Oregon Residential Specialty Code, chapter 1
- BCD Local Building Department Directory
- FEMA Community Status Book for Oregon
- Oregon ePermitting
- Oregon Construction Contractors Board
Inspections are where schedules slip.
Get a free quote →Sandy building permit FAQ
Who issues electrical permits in Sandy?
Clackamas County. The City issues structural, mechanical and plumbing permits; call the County at 503-742-4240 for electrical.
How much is a building permit in Sandy?
At least $98. A $60,000 project pays $792 plus 70% plan review, the 12% state surcharge and a 3% technology fee, about $1,482.
Can I build an ADU in Sandy now?
ADU applications that need a new sewer connection or more flow fall under the moratorium in Resolution 2026-04, which runs from June 1, 2026 for six months unless extended; a hearing on extending it was set for November 2, 2026.
Does the moratorium stop my remodel?
Not if the remodel or addition does not change the sewer connection in a way that increases flow, according to the City’s FAQ.
When are inspections done?
Monday to Thursday, 9 a.m. to 4 p.m., booked online, in the ORinspect app or at 1-888-299-2821.
Can I do my own plumbing?
Yes, as the owner of the building, with a permit; friends, tenants and general contractors may not do it for you.
Do I need a permit for a fence?
Only over 7 feet, or when the fence forms part of a pool barrier; corner-lot and front-yard height limits still apply.
Simplify Sandy permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Oregon. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Sandy sooner?
Let Alliance prepare, file, and track your Sandy permits while your crew stays on the job.
More Oregon permitting guides
Clackamas County
Read guide →Happy Valley
Read guide →Lake Oswego
Read guide →Sherwood Building Permit Guide
Read guide →Silverton Building Permit Guide
Read guide →Springfield Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Sandy permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.