To get a building permit in Happy Valley, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Happy Valley’s Building Division at City Hall, 16000 SE Misty Drive, issues structural, mechanical and plumbing permits through the City’s HVWorks portal, while electrical permits and inspections come from Clackamas County.

Authority: Happy Valley Building DivisionCode: 2025 OSSC; 2026 ORSC (phase-in to April 2027)Phone: 503-783-3800
Authority
Happy Valley Building Division16000 SE Misty Drive
Portal
HVWorksApply, pay and book inspections
Minimum fee
$104FY 2026–27 schedule, from July 1, 2026
Inspections
Same day if booked by 6 a.m.Through HVWorks, any hour

In the City of Happy Valley, the Building Division reviews plans and issues structural, mechanical, plumbing, grading and demolition permits, all applied for and paid in the City’s HVWorks online portal. Electrical permits, fees and inspections are handled by Clackamas County. Under the fee schedule that took effect on July 1, 2026, the minimum building permit is $104, plan review is 65% of the permit fee, and the City adds the state surcharge of 12% of the permit fee.

The division works from Happy Valley City Hall at 16000 SE Misty Drive under Building Official Mark Ennis, PE, and answers on 503-783-3800. Happy Valley, entirely in Clackamas County, had 28,916 residents in the Census estimate for 2025. For a new house, the system development charges are far larger than the permit fee itself.

Addresses outside the city limits, including the unincorporated area around the city, are under Clackamas County for building permits; the City publishes a page explaining its limits.

What requires a building permit in Happy Valley?

The Building Division permits new buildings, additions, alterations and repairs under the state codes, and its fee schedule and checklists show the local rules around them.

City permits

  • New houses, which need building, electrical, erosion, mechanical, plumbing and sewer applications plus a Planning/Engineering review application
  • Decks, with their own submittal checklist; any deck 10 feet or more above grade needs engineering (policy POL 13-108)
  • Solar panel structural installations ($157 flat on the prescriptive path)
  • Demolition ($120 per building)
  • Grading of more than 25 cubic yards that is not part of a house foundation permit
  • Sewer connections and septic abandonment

No City permit

  • Grading of 25 cubic yards or less (no permit and no plan review fee)
  • Electrical work: no City permit, because the permit comes from Clackamas County
  • Work in the street: an Engineering right-of-way permit rather than a building permit

What the city decides and what the state holds

The code and its exemptions are statewide. Happy Valley sets its fees, adjusted every July by the West Coast consumer price index under Council Resolution 22-21, its HVWorks process, its submittal checklists and policies, its flood management overlay and land development code, and its construction hours.

Oregon’s building code and its exemptions are the same in Happy Valley as everywhere in the state, and an exemption from the building permit is not an exemption from zoning, land use or a trade permit. Site snow, wind and seismic values come from the state’s Oregon Design Criteria Hub. How Oregon’s statewide code works

Short on time to read all of this?

Get a free quote →

Happy Valley building department: who handles permitting

The Building Division reviews residential, commercial and industrial plans and inspects. Planning handles land use under the Land Development Code, and Engineering issues right-of-way, grading and erosion control permits. Clackamas County runs the City’s electrical program. Sewer and surface water charges go to Clackamas County Water Environment Services (WES), and water service comes mainly from Sunrise Water Authority, with Clackamas River Water in parts of the city.

Happy Valley permitting contacts
DetailInformation
Building DivisionHappy Valley City Hall, 16000 SE Misty Drive, Happy Valley, OR 97086
Phone503-783-3800 (ask for a permit technician for fee questions)
Online portalHVWorks (hvworks.com): applications, payments, inspections
Permit searchBuilding Permits Issued search in the HVWorks self-service site
Electrical permitsClackamas County
CounterBuilding Division front counter at City Hall; staff typically available 8 a.m. to 4 p.m. on weekdays

Permit types

Residential permits

The one- and two-family dwelling checklist (revised April 13, 2026) must be complete before the plan review start date. It asks for proof that land use actions are finished (plat recorded and signed off by Happy Valley Engineering and WES), zoning details such as setbacks, easements, flood plain and seismic soils designation, a soils report on steep slopes or fill, an erosion control plan, and a scaled site plan with 2-foot contours, finished floor elevations, the driveway slope, lot coverage, impervious area and any well or septic system. On a new house with a high deck, the deck engineering must be approved before the house framing inspection, because sloping lots here can put decks as high as 30 feet. Plans must use the City’s design values: roof snow load 25 psf, wind speed 95 mph with exposure B, and seismic design category D. Retaining or basement walls holding more than 4 feet of backfill or a surcharge need drawings and calculations stamped by an Oregon engineer. The City’s forms include a notice to owners about construction responsibilities.

Commercial permits

Commercial projects use the same valuation table, with valuation the greater of the ICC figure for the occupancy and construction type or the applicant’s stated value, plus a commercial fire and life safety review of 40% of the permit fee. Commercial mechanical permits are priced on the value of the mechanical work ($104 minimum) with a 25% plan review. Deferred submittals cost 65% of the structural fee for the deferred part, at least $273 an item, and phased construction review is $273 plus 10% of the total project permit fee. A pre-application consultation with two City staff members costs $164.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

For a new house, the plat must be recorded and the land use decision complete before the checklist is accepted. The WES sewer and surface water SDCs are paid to Clackamas County before the permit is issued, and the City’s transportation and parks SDCs are paid to the City. Engineering issues a Type 1 right-of-way permit for driveway approaches, sidewalks, dumpsters and portable toilets in the street, and Type 2 permits for utility work and paving. Inside the flood management overlay (Land Development Code chapter 16.35), new habitable buildings need a finished floor, and the bottom of any septic tank, at least one foot above the design flood height or the highest flood of record, whichever is higher. FEMA counts Happy Valley among participating flood insurance communities, on a map effective June 17, 2008.

Happy Valley permit costs and fees

The Building Division fees are in the City’s Fiscal Year 2026–27 fee schedule, approved by the City Council and effective July 1, 2026. The City told the state Building Codes Division in May 2026 that the increase was 3.1%, the March-to-March change in the West Coast consumer price index, following 3.6% in August 2024 and 2.2% in August 2025. Valuation follows OAR 918-050-0100: for new houses and additions the ICC Building Valuation Data figure current on April 1 times the floor area, with carports, covered porches, patios and decks counted at 50% of the garage rate.

Happy Valley building fees (FY 2026–27 fee schedule, effective July 1, 2026)
ItemFee or rule
Building permit, valuation $1 to $4,000$104 minimum
$4,001 to $25,000$104 plus $13.34 per added $1,000 over $4,000
$25,001 to $50,000$384.14 plus $9.77 per added $1,000 over $25,000
$50,001 to $100,000$628.39 plus $6.67 per added $1,000 over $50,000
$100,001 and up$961.89 plus $5.59 per added $1,000 over $100,000
Structural plan review65% of the permit fee, residential and commercial
State surcharge12% of the permit fee
New house plumbing$838 one bath, $943 two baths, $1,047 three baths (first 100 feet of water, storm and sewer included)
Residential mechanical$104 minimum; heat pump, furnace or air conditioner $27 each
Temporary certificate of occupancy$273
Re-inspection$104 per hour
Erosion control$437 per building, or $218 when less than 500 sq ft of soil is disturbed

Rather talk it over?

Call 1-855-478-4290 →

Worked example. An addition valued at $80,000 is in the $50,001 to $100,000 band: $628.39 plus 30 × $6.67 ($200.10) gives a permit fee of $828.49. Plan review at 65% is $538.52 and the state surcharge at 12% of the permit fee is $99.42, so the structural permit costs $1,466.43 before plumbing, mechanical, erosion control and the County’s electrical permit.

For new houses the City’s SDC page (rates set July 1, 2025) lists transportation $12,779, parks $10,479 and city storm drainage $216, plus WES surface water ($272) and sanitary sewer ($9,630 for a 2,500 sq ft house) and a Sunrise Water Authority water meter charge of $16,532. Metro’s construction excise tax is 0.12% of value on projects of $100,000 or more, and the school districts charge $1.70 per sq ft for residential space. The City’s own example for a 2,500 sq ft house with a 450 sq ft garage totals $62,599: $7,759 in building permit fees, $50,023 in SDCs and $4,816 in excise taxes.

Trade permits and who may pull them

Happy Valley issues plumbing and mechanical permits itself; a new house needs both, along with sewer and erosion applications. Electrical permits, fees and inspections are issued and regulated by Clackamas County, which administers the City’s electrical program. The City’s operating plan says a residential building permit is not issued until the related trade permits have been applied for and paid, and every application needs proof of a Construction Contractors Board license or the reason the work is exempt.

Rather not deal with the building department?

Get a free quote →

City trade fees

  • Plumbing minimum $104; plumbing plan review 30%, for complex structures only
  • Sewer connection permit $55
  • Septic abandonment $38
  • Residential fire sprinklers: $197 under 2,000 sq ft, $280 up to 3,600 sq ft

Through Clackamas County

  • Electrical permits and their fees
  • All electrical inspections
  • WES sanitary sewer and surface water SDCs

How to apply for a Happy Valley building permit

1. Finish land use first

Make sure the plat is recorded and any land use decision is final, and check the lot for the flood management overlay, easements and seismic soils.

2. Register in HVWorks

Create an account at hvworks.com; the same portal handles building, engineering and business license applications.

3. Complete the checklist

Work through the one- and two-family, deck or site plan checklist and gather the soils report, erosion plan and engineering it calls for.

4. Submit every application together

For a new house file the building, mechanical, plumbing, sewer and erosion applications and the Planning/Engineering review application, and apply to Clackamas County for the electrical permit.

5. Answer corrections

Highlight or cloud minor changes and notes on resubmitted plans.

6. Pay fees and SDCs

Pay City fees and the transportation and parks SDCs in HVWorks and the WES SDCs at Clackamas County before the permit is issued.

Review, corrections and what causes delay

The City’s 2022 operating plan sets out the review path for new houses: within three working days the applicant hears whether the application is complete and whether the house counts as simple or complex. A simple house is reviewed within 10 working days or the applicant is offered three registered third-party review firms, for an administrative fee of 10% of the normal plan review fee; complex houses and commercial projects take two to four weeks. If information is missing, the review can be delayed and then starts over, and the checklist must be complete before the review start date. A plan review by an architect or engineer acting as a certified plans examiner is allowed for houses for a $328 fee.

Inspections in Happy Valley

Book inspections at any hour in HVWorks: log in, open MyWork, find the permit and pick the inspection on its Inspections tab. Requests in by 6 a.m. are scheduled for the same business day unless noted otherwise; call 503-783-3800 if the portal gives trouble. Electrical inspections are booked with Clackamas County. A re-inspection is billed at $104 an hour, and inspection after normal working hours costs $120 an hour with a two-hour minimum. The final certificate of occupancy carries no charge; a temporary one costs $273.

Want this handled start to finish?

Get a free quote →

Any site that disturbs 500 sq ft or more of ground needs an erosion prevention and sediment control permit, with a gravel construction entrance at least 20 by 20 feet and inlet protection downhill. Wet-weather rules run from October 1 to April 30, when soil exposed for more than two days must be seeded or covered, and all exposed soil must be stabilized, with front yard landscaping and street trees in, before the building final.

Construction is allowed from 7 a.m. to 6 p.m. on weekdays and 8 a.m. to 5 p.m. at weekends, but on Sundays the City bars site clearing, earth moving, underground utility work, street or sidewalk paving, foundation framing or pouring, and structural framing.

Happy Valley permit search and official resources

Issued permits can be searched in the “Building Permits Issued” search of the HVWorks self-service site. Copies of files for closed permits are usually ready within five working days of a request, according to the City’s operating plan; ask the Building Division at 503-783-3800.

Inspections are where schedules slip.

Get a free quote →

Happy Valley building permit FAQ

Who issues building permits in Happy Valley?

The City’s Building Division at City Hall, 16000 SE Misty Drive (503-783-3800), through the HVWorks portal. Electrical permits come from Clackamas County.

How much is a building permit in Happy Valley?

From July 1, 2026 the minimum is $104; an $80,000 addition pays $828.49, plus 65% plan review and the 12% state surcharge, $1,466.43 in all for the structural permit.

What does a new house cost in fees?

The City’s own example for a 2,500 sq ft house is $62,599, of which $50,023 is system development charges and only $7,759 is building permit fees.

Can I get a same-day inspection?

Yes, if you book it in HVWorks by 6 a.m. on a business day.

How long does plan review take for a new house?

The City’s operating plan aims for 10 working days on a simple house, or offers third-party review, and two to four weeks for a complex house.

Can I work on Sundays?

Only limited work. Weekend hours are 8 a.m. to 5 p.m., and site clearing, earth moving, underground utilities, paving, foundations and structural framing are not allowed on Sundays.

Simplify Happy Valley permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Oregon. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Happy Valley sooner?

Let Alliance prepare, file, and track your Happy Valley permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Happy Valley permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.