To get a building permit in Milwaukie, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Milwaukie’s Building Division at City Hall, 10501 SE Main Street, issues every building, electrical, plumbing and mechanical permit inside the city limits through Oregon ePermitting.

Authority: Milwaukie Building DivisionCode: 2025 OSSC; 2026 ORSC (phase-in to April 2027)Phone: 503-786-7623
Authority
Milwaukie Building Division10501 SE Main Street
Counter
Mon–Thu, 9 a.m. to 1 p.m.Phones 8 a.m. to 5 p.m.
Plan review
75% of permit feePaid before review starts
Trades
All issued by the CityElectrical included

In Milwaukie, the City’s Building Division reviews plans and issues and inspects structural, electrical, plumbing and mechanical permits for all work inside the city limits. Contractors file through Oregon ePermitting, and homeowners call 503-786-7623 for help getting started. Under the fee schedule the City Council adopted on June 16, 2026, a structural permit costs at least $150.75, and plan review adds 75% of the permit fee, payable before review begins.

The division works from City Hall, 10501 SE Main Street, where the in-person counter is open Monday to Thursday from 9 a.m. to 1 p.m.; staff answer the phone from 8 a.m. to 5 p.m. Patrick McLeod is the Building Official. Milwaukie had 22,114 residents in the Census estimate for 2025, all of them on the Clackamas County side; a small part of the city’s area lies in Multnomah County.

Mailing addresses can mislead here: a Milwaukie address does not mean a parcel is inside the city. The City points applicants to Clackamas County’s CMap to confirm which jurisdiction holds a property before they apply.

What requires a building permit in Milwaukie?

Milwaukie treats each permit type as a separate application. A building (structural) permit covers new structures, structural changes and signs; mechanical, electrical and plumbing permits cover their own systems; fire sprinklers, alarms, suppression and fire lines always need a permit, with no exemptions. Site work is permitted separately: an erosion control permit applies once more than 500 sq ft of soil is disturbed, and a grading permit once grading reaches 50 cubic yards.

Permit required

  • New houses, duplexes, ADUs, additions and structural remodels
  • A barrier fence for a swimming pool, under the code’s statewide rule
  • Signs, apart from wall signs of 25 lbs or less, which still need a planning sign permit
  • Any fire sprinkler, alarm or suppression work
  • Accessory buildings over 200 sq ft (400 sq ft on a parcel of 2 acres or more), or taller than 15 feet to the average height of the highest roof
  • Reroofing that adds more than 4 psf of dead load, or any reroof of a townhouse or stacked two-family dwelling or with building-integrated solar panels

No building permit (2026 ORSC)

  • A nonhabitable one-story detached accessory building of 200 sq ft or less and no more than 15 feet high
  • Decks, porches and platforms whose walking surface is no more than 30 inches above grade
  • Patio and porch covers up to 200 sq ft that stay 3 feet or more from lot lines
  • Above-grade and on-ground pools, and in-ground pools at houses unless a local ordinance requires a permit (their barriers still need one)
  • Fences of wood, wire mesh or chain link up to 7 feet, and retaining walls that do not support a regulated building, protect its users or hold back soil that could affect it (a city may regulate those over 4 feet)
  • Siding repair, retrofitted insulation, gutters, and window replacements that change no structural member

Short on time to read all of this?

Get a free quote →

What Milwaukie decides and what the state holds

The exemption lists come from sections R101.2.2 and R105.2 of chapter 1 of the 2026 Oregon Residential Specialty Code, mandatory statewide since October 1, 2026; its technical chapters become mandatory on April 1, 2027, and commercial work has followed the 2025 Oregon Structural Specialty Code since April 1, 2026. Milwaukie sets the fees, the order of planning, erosion control and building inspections, its zoning and natural resource rules, its right-of-way permits and its system development charges.

Oregon’s building code and its exemptions are the same in Milwaukie as everywhere in the state, and an exemption from the building permit is not an exemption from zoning, land use or a trade permit. Site snow, wind and seismic values come from the state’s Oregon Design Criteria Hub. How Oregon’s statewide code works

Milwaukie building department: who handles permitting

The Building Division administers the state code for all four trades, while other Clackamas County cities such as West Linn and Sandy send electrical permits to the County. Milwaukie’s operating plan does send commercial plumbing plans to Clackamas County’s commercial plumbing inspector for review, and the County runs park and camp permits. Development Services Engineering handles right-of-way permits, stormwater, erosion control and SDC assessments, and the Planning Division reviews zoning, setbacks and natural resources on building permits.

Milwaukie permitting contacts
DetailInformation
Building DivisionCity Hall, 10501 SE Main Street, Milwaukie, OR 97222
Phone and email503-786-7623; building@milwaukieoregon.gov
Counter hoursMonday to Thursday, 9 a.m. to 1 p.m.
Building OfficialPatrick McLeod
Online portalOregon ePermitting (Accela), for applications, fees, plans and inspections
Trades issuedStructural, electrical, plumbing and mechanical, all by the City

Permit types

Residential permits

Anything with two or fewer dwelling units is a residential application under the Oregon Residential Specialty Code; three or more units makes it commercial. A short-term rental starts with Planning, and the City then asks for a structural permit application, a floor plan, bedroom window details and alarm locations, closed with a final inspection before the business license is issued. The ePermitting menu offers separate records for structural work, new one- and two-family dwellings, manufactured dwellings, demolition, electrical, mechanical, plumbing, alarm or suppression systems, signs, site development (erosion control or grading) and right-of-way access. The portal decides which types a user may start from the licenses linked to the account, so a homeowner emails the address and a description of the job to building@milwaukieoregon.gov for instructions. The City publishes its own forms for building, electrical, mechanical, plumbing, grading, manufactured dwelling and relocation permits, a homeowner construction responsibilities form, moisture content and fire sprinkler or alarm affidavits, plus a fee estimator for a new single-family house.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial plans carry a fire and life safety review at 50% of the structural permit fee on top of the 75% plan review, and essential facilities pay a seismic review of 1% of the structural and mechanical permit fees. Deferred submittals cost 70% of the permit fee for the deferred portion, $300 minimum, and phased reviews $300 plus 10% of the total project permit fee, capped at $1,500 a phase. Commercial electrical plan review is 25% of the electrical permit fee and commercial plumbing review 30%; the City’s FAQ notes that electrical and plumbing plan reviews still need two paper sets, although everything else is digital.

What comes before the building permit

Planning reviews zoning, setbacks and natural resource overlays on every new building or addition, for a fee of $250 on a major review and $25 on a minor one such as solar or a demolition’s erosion control; land use applications start at $250 for a Type I decision. Development Services Engineering issues the erosion control permit ($250 for a single-family home in 2026–27), right-of-way permits for driveways, sidewalks and utility connections, and SDC estimates (engineering@milwaukieoregon.gov). FEMA’s status book places Milwaukie among participating flood-program communities, on a map revised June 17, 2008, and the City’s floodplain development permit costs $200 plus actual cost. A parcel still on septic gets its permit from Clackamas County’s Septic and Onsite Wastewater Program, DEQ’s agent.

Milwaukie permit costs and fees

Building fees are in section 2 of the City’s Consolidated Fee Schedule for fiscal years 2027 and 2028, effective July 1, 2026 under Resolution R33-2026 (adopted June 16, 2026); the August 28, 2026 revision rewrote section 2 for state compliance and clarity, with the same rates for both years. New buildings and additions are valued with the ICC table updated each April 1. The schedule says the state surcharge “shall be collected in an amount as required by State law”, and the Building Division’s fee page puts it at 12% of the permit fee.

Rather talk it over?

Call 1-855-478-4290 →
Milwaukie building fees, Consolidated Fee Schedule FY 2027–2028 (effective July 1, 2026)
ItemFee or rule
Structural permit, valuation $1 to $5,000$150.75 (also the minimum)
$5,001 to $25,000$150.75 plus $15.50 per added $1,000
$25,001 to $50,000$460.75 plus $11.50 per added $1,000
$50,001 to $100,000$748.25 plus $7.80 per added $1,000
Over $100,000$1,138.25 plus $6.50 per added $1,000
Structural plan review75% of the permit fee; commercial fire and life safety review 50% more
Technology fee5% of the permit fee, all programs unless stated otherwise
Mechanical, plumbing or electrical minimum$155.90
New house plumbing$654.90 one bath, $723.65 two baths, $860.00 three baths
New house electrical, up to 1,000 sq ft$315.15, plus a set amount per added 500 sq ft
Prescriptive solar PV$100
Reinspection, or added plan review$110 each, or $110 an hour
Temporary certificate of occupancy$180 for 30 days

Worked example. A remodel valued at $80,000 falls in the $50,001 to $100,000 band: $748.25 plus 30 × $7.80 ($234) is a structural permit fee of $982.25. Plan review at 75% adds $736.69 and the 5% technology fee $49.11, and the state surcharge at 12% of the permit fee is $117.87, for $1,885.92 before any trade, planning or erosion control permits.

Two more notes from the City’s fee pages. Its All About Fees page says residential mechanical, electrical and plumbing permits carry no plan review fee, while the adopted 2026 schedule, which is the controlling document, lists mechanical plan review at 50% for both residential and commercial work. School construction excise tax applies when square footage is added, and Metro’s and the affordable housing tax apply once the valuation passes $100,000. System development charges apply to new dwelling units such as a house or ADU and some commercial projects, not to remodels or additions.

Trade permits and who may pull them

Because Milwaukie runs its own electrical program, an electrician pulls the electrical permit from the City in ePermitting, as plumbers and mechanical contractors do for their work; residential trade fees are added up from each application’s fixture or item list, with a $155.90 minimum. A new house is priced by floor area for electrical and by bathroom count for plumbing. Licensed contractors may also buy state minor labels for small jobs such as a water heater or furnace swap, and the City inspects those labels when BCD forwards them.

Rather not deal with the building department?

Get a free quote →

Who may do the work

  • Paid contractors need an active Construction Contractors Board license, and electricians and plumbers a BCD trade license
  • The City’s FAQ: an owner may do the work on a home they own and do not intend to sell
  • State law limits owner electrical work to property not for sale, rent or lease
  • Staff check licenses before issuing any permit

Milwaukie trade notes

  • Commercial plumbing plans go to Clackamas County’s plumbing inspector
  • Electrical and plumbing plan reviews need two paper sets
  • Master electrical permits: $100 to set up, $110 an hour for inspections
  • Changing contractors on a permit is decided case by case

How to apply for a Milwaukie building permit

1. Confirm the parcel is in the city

Look the address up on Clackamas County’s CMap and check zoning and overlays with the Planning Division.

2. Choose the right permit records

Pick each separate permit the job needs: structural, the trades, site development and right-of-way.

3. Apply in ePermitting

Contractors register, link their licenses and submit online; homeowners call 503-786-7623 or email the Building Division for instructions, then upload digital plans.

4. Pay the plan review fee

An invoice arrives by email, and plans join the review queue only once it is paid; they are reviewed in the order received and sent to the other divisions.

5. Answer questions and pay the balance

A “Ready To Issue” email lists the remaining fees; once paid, the permit is issued and the approved plans can be downloaded.

6. Print the plans and build

Keep the printed approved set on site and request each inspection at the right stage.

Review, corrections and what causes delay

The operating plan commits to telling residential applicants within three working days whether an application is complete, and for structural, mechanical and plumbing work needing in-depth review, to listing deficiencies within 15 business days and generally issuing within 15 business days of a complete application with intake fees paid. Those targets exclude Planning, Engineering, land use and natural resource approvals, which often set the real pace; a simple short-term rental conversion typically takes about four weeks. An unpaid plan review fee stops the clock entirely, and an application or permit idle for 180 days expires unless the Building Official approves a written extension.

Inspections in Milwaukie

Request inspections at buildingpermits.oregon.gov or in the state’s ePermitting inspections app, which the City recommends. A request made before 7 a.m. is done the same business day, and inspections typically run from 7 a.m. to 5 p.m.; the operating plan schedules inspectors Monday to Thursday. Times are not guaranteed, but you may ask for morning or afternoon, and a note such as a lock box code should go on every request because different inspectors may come. Permits stay valid for 180 days, so keep inspections moving.

Want this handled start to finish?

Get a free quote →

The City’s sequence starts with the preliminary erosion control inspection, then a planning inspection of zoning and setbacks on new buildings and added floor area, which must pass before any footing or foundation inspection and can take Planning up to 48 hours. Building inspections follow at each stage. Every other final, including erosion control, planning, right-of-way and each trade permit, must be approved and all fees paid before the final building inspection; the Building Official issues the certificate of occupancy when that final passes. A reinspection fee may be charged after the second rejection for the same item.

Milwaukie permit search and official resources

Milwaukie permits from 2013 on can be searched in Oregon ePermitting; for older records, use the City’s public records request form. Under the state retention schedule the City keeps residential plans for two years and commercial plans for ten years after the final.

Inspections are where schedules slip.

Get a free quote →

Milwaukie building permit FAQ

Who issues electrical permits in Milwaukie?

The City of Milwaukie. Its Building Division issues and inspects electrical permits along with structural, plumbing and mechanical ones.

How much is a building permit in Milwaukie?

The structural minimum is $150.75, and an $80,000 remodel pays $982.25 plus 75% plan review, a 5% technology fee and the 12% state surcharge, about $1,886 in all.

Can a homeowner apply without a contractor license?

Yes. ePermitting only shows permit types tied to an account’s licenses, so homeowners call 503-786-7623 or email building@milwaukieoregon.gov for instructions.

How soon can I get an inspection?

Requests made before 7 a.m. are done the same business day; you can ask for morning or afternoon but not a set time.

Do I need a permit for a shed?

Not for a nonhabitable one-story detached shed of 200 sq ft or less and no more than 15 feet high, but Planning may still have setback rules for it.

Do SDCs apply to my remodel?

No. Milwaukie charges system development charges on new dwelling units, such as a house or ADU, and some commercial projects, not on remodels or additions.

How do I find an old permit?

Search Oregon ePermitting for permits since 2013, or file a public records request for older ones.

Simplify Milwaukie permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Oregon. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Milwaukie sooner?

Let Alliance prepare, file, and track your Milwaukie permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Milwaukie permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.