In North Bend, the City’s Building Department, part of Public Works, reviews plans and issues and inspects structural and mechanical permits; electrical and plumbing permits are not sold by the City. Applications go to the Permit Technician at City Hall, 835 California Avenue (541-756-8525). Fees follow Resolution 3379, adopted by the City Council on January 27, 2026, and plan review is 65% of the structural permit fee.
Derek Windham, the City’s Engineering Coordinator and Building Official, answers code, construction and plan review questions at 541-756-8505. City Hall, at the corner of California and McPherson Avenues, is open Monday to Friday from 8 a.m. to 5 p.m.; calls missed before or after hours are returned by the end of the next business day. North Bend, in Coos County, had 9,966 residents in the Census estimate for 2025.
City permits cover land inside North Bend’s city limits. Unincorporated land around the city is served by Coos County’s building department in Coquille.
What requires a building permit in North Bend?
North Bend’s “Do I need a building permit?” handout says a permit is needed to build, enlarge, alter, move or demolish any one- or two-family dwelling or related structure. It singles out work homeowners often assume is minor: replacing wallboard on the garage side of the wall between the garage and the house, replacing insulation in the exterior envelope, and moving bearing walls.
Permit required
- New homes, additions, remodels, manufactured homes and accessory structures
- Adding or removing a room, building a stairway, or finishing an attic, garage or basement as living space
- Cutting new window or door openings or widening existing ones
- Reroofing that adds more than 4 psf of dead load, and photovoltaic roof panels or roof coverings
- Retaining walls over 4 feet from the bottom of the footing, or any wall carrying a driveway or building load
- Moving more than 50 cubic yards of earth, or any cut or fill on sites near waterways or slope hazards (excavation permit)
- Furnaces, ducted heating and cooling, chimney-vented appliances and gas piping (mechanical permit)
No building permit (2026 ORSC)
- One-story nonhabitable detached sheds up to 200 sq ft and 15 feet to the average roof height (400 sq ft on a parcel of 2 acres or more)
- Decks and porches whose walking surface is 30 inches or less above grade
- Deck, patio or porch covers up to 200 sq ft that stay 3 feet from lot lines
- Wood, wire mesh and chain link fences up to 7 feet, except pool barriers
- Above-grade and on-ground pools; in-ground pools at houses unless a local ordinance requires a permit
- Painting, flooring, cabinets, gutters, siding not required to be fire rated
Short on time to read all of this?
Get a free quote →What the city decides and what the state holds
The exemptions above come from sections R105.2 and R101.2.2 of the 2026 Oregon Residential Specialty Code, whose chapter 1 has been mandatory since October 1, 2026. The City’s printed handout already uses the 15-foot shed height, but its Residential Building Permit Requirements web page still quotes the older 10-foot limit measured from the floor, and both still require a permit whenever new sheathing goes on a stripped roof, which the 2026 code exempts when the added dead load is 4 psf or less. What North Bend controls is local: its fee resolution, the excavation and right-of-way permits under Titles 10 and 15 of the City Code, zoning setbacks and lot coverage, which apply even when no building permit is needed, and the demolition policy.
Oregon’s building code and its exemptions are the same in North Bend as everywhere in the state, and an exemption from the building permit is not an exemption from zoning, land use or a trade permit. Site snow, wind and seismic values come from the state’s Oregon Design Criteria Hub. How Oregon’s statewide code works
North Bend building department: who handles permitting
The City’s Building, Planning and Engineering staff share one office at City Hall. The Permit Technician handles general permitting, zoning, application and fee questions and books inspections; the Building Official covers code questions and plan review and, as Engineering Coordinator, also handles sewer and storm locations, curb cuts, street cuts and work in the right-of-way. The City Planner (541-756-8535) handles land use, annexations, subdivisions and parking development.
Electrical and plumbing permits come from Coos County Community Development, 60 E. Second Street, Coquille (541-396-7770). The Building Codes Division’s Local Building Department Directory lists the County as North Bend’s issuer for both trades, and the County’s building page says its inspectors cover plumbing and electrical work across the whole county, while its structural inspector serves everywhere except Coos Bay and North Bend. The City’s printed handout, which also quotes older code wording, still names a state office in Coos Bay.
| Detail | Information |
|---|---|
| Building Department | North Bend City Hall, 835 California Avenue (PO Box B), North Bend, OR 97459 |
| Permit Technician | 541-756-8525: permits, fees, zoning questions and inspection requests; buildingpermits@northbendoregon.gov |
| Building Official | Derek Windham, Engineering Coordinator/Building Official, 541-756-8505 |
| Hours | Monday to Friday, 8 a.m. to 5 p.m. |
| City Planner | 541-756-8535 |
| Electrical and plumbing | Coos County Community Development, Coquille: 541-396-7770; inspection line 541-266-1098 |
Permit types
Residential permits
A house project in North Bend usually needs a City structural permit and a City mechanical permit, plus electrical and plumbing permits from the outside issuer. The City’s site plan sheet asks for a drawing to scale showing property boundaries, every structure and the setbacks, and the handout asks for the same drawing even for a shed that needs no building permit, so staff can check the zoning. Owners of one- and two-family dwellings may hire a licensed contractor or do the building and mechanical work themselves. Two state rules sit inside the mechanical permit: anyone installing liquid propane gas systems must be licensed by the Office of State Fire Marshal, and a boiler or pressure vessel needs a State of Oregon installation permit as well as the City’s mechanical permit, whatever its size.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
The City reminds applicants that commercial building and mechanical requirements differ from residential ones and asks them to call the department first. Commercial plans pay structural plan review at 65% of the permit fee and fire and life safety review at 40% of the applicable permit fee when it is required; commercial mechanical permits are priced by the value of labor and materials, starting at $46.29. Phased projects pay $330.66 plus 10% of the phase’s permit fee, up to $1,500 a phase, and deferred submittals 65% of the fee on the deferred portion. Signs and commercial fire sprinkler and alarm systems use the structural valuation table.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
Zoning comes first: the City’s Urban Form map gives each lot’s zone, allowed uses, setbacks, height and lot coverage, and the North Bend GIS map shows utilities, elevation and natural features. Land use reviews, partitions and annexations go to the City Planner and the Planning Commission. Driveway curb cuts, street cuts and any work in the public right-of-way need Engineering’s permit, and grading over 50 cubic yards, or any cut or fill near a waterway or slope hazard, needs an excavation permit. Each structure taken down needs its own demolition permit, even when a new building replaces it, and plans for altering a building built before 1990 may need an environmental assessment under DEQ rules.
North Bend permit costs and fees
Building fees are in Exhibit A to Resolution 3379, which the City Council adopted unanimously on January 27, 2026 after a public hearing and which took effect on February 1, 2026. The resolution raised existing fees by 2.8%, the 2026 Social Security cost-of-living rate: since voters approved Charter Measure 6-176 in May 2020, North Bend may not add new fees without a public vote and may raise existing fees only each year by that rate. Exhibit A lists the state surcharge on its own line, “12% x associated permit fee,” and notes that the rate is subject to annual increase.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee or rule |
|---|---|
| Valuation $1 to $500 | $25.81 |
| $501 to $2,000 | $25.81 for the first $500 plus $3.86 per added $100 or fraction |
| $2,001 to $25,000 | $83.86 for the first $2,000 plus $15.46 per added $1,000 or fraction |
| $25,001 to $50,000 | $439.44 for the first $25,000 plus $11.61 per added $1,000 |
| $50,000 to $100,000 | $729.69 for the first $50,000 plus $7.73 per added $1,000 |
| $100,001 and up | $1,116.19 for the first $100,000 plus $6.45 per added $1,000 |
| Structural plan review | 65% of the structural permit fee; fire and life safety review 40% when required |
| Added plan review for changes | $103.00 an hour, half-hour minimum |
| Residential mechanical | $70.84 minimum; a furnace up to 100,000 BTU or a heat pump $17.03 each |
| Manufactured dwelling placement | $335.95, plus the $30 state fee |
| Demolition | $135.67 residential, $335.95 commercial |
| Prescriptive solar panels | $135.27 |
| Reinspection or investigation | $103.00 each, or $103.00 an hour for investigations |
| State surcharge | 12% of the associated permit fee |
Worked example. A project valued at $150,000 is in the top band: $1,116.19 plus 50 × $6.45 ($322.50) gives a structural permit fee of $1,438.69. Plan review at 65% adds $935.15 and the 12% state surcharge on the permit fee $172.64, for $2,546.48 before mechanical, electrical and plumbing permits. The example stays above $100,000 because the $501 to $2,000 band does not quite lead into the next one: $25.81 plus 15 × $3.86 is $83.71, not the $83.86 the next band starts from.
Other lines in Exhibit A: a residential fire sprinkler system costs $193.23 up to 2,000 sq ft, rising to $515.31 above 7,200 sq ft; grading permits start at $32.20 for 50 cubic yards or less and $49.59 for 51 to 100; inspections outside normal hours cost $103.00 an hour with a two-hour minimum. The figures the City sent the Building Codes Division with its notice in November 2025 differed by a few cents in some bands; the table above uses the adopted exhibit.
Rather not deal with the building department?
Get a free quote →Trade permits and who may pull them
North Bend issues only one trade permit itself, the mechanical permit, which covers heating, cooling and ventilation systems with ductwork or a chimney vent and gas piping between the meter and any appliance, indoors or out. Electrical and plumbing permits come from Coos County, so a remodel with new circuits or fixtures involves two permit offices.
Who may do the work
- Paid contractors need a Construction Contractors Board license
- Owners of one- and two-family dwellings may do their own building and mechanical work
- Propane installers need an Office of State Fire Marshal license
- Hired electrical and plumbing work needs state-licensed tradespeople
Where to file
- Structural and mechanical: North Bend Building Department
- Electrical and plumbing: Coos County Community Development
- Boilers and pressure vessels: a state installation permit plus the City permit
- Curb cuts, street cuts, right-of-way: City Engineering
How to apply for a North Bend building permit
Use the Urban Form map or call the Permit Technician to learn the zone, setbacks, height limit and lot coverage for the lot.
Show the property lines, every existing and proposed structure and the distances between them, as the City’s site plan sheet asks.
Include foundation, floor, framing and elevation drawings, and engineering where the design needs it; commercial projects should call first.
File at City Hall or by email to buildingpermits@northbendoregon.gov; the City also uses Oregon ePermitting for select permits and inspections.
Buy electrical and plumbing permits from Coos County, and Engineering permits for any curb cut, street cut or right-of-way work.
Pay the permit, plan review and state surcharge, keep the approved plans on site and book inspections in order.
Review, corrections and what causes delay
The City publishes no review time. Revisions, additions or changes after review cost $103.00 an hour, so a complete first submittal with a site plan that shows every setback avoids most delay. A permit expires if work does not start within 180 days of issue or stops for 180 days, but each inspection that shows the work progressing extends every permit at that address by 180 days, and the Building Official may grant written extensions for good cause. An expired permit can be reinstated for 50% of the original permit fee within 90 days of expiring, 75% between 90 and 180 days, or $80 when only final inspections remain; after 180 days the permit is void and its record file is closed.
Want this handled start to finish?
Get a free quote →Inspections in North Bend
City inspectors work Monday to Friday from 1:30 to 4 p.m. Call 541-756-8525 at least 24 hours before the inspection you need, and 48 hours before a final inspection on a new structure. Electrical and plumbing inspections are done by Coos County inspectors, so book them with the County (541-266-1098).
Each reinspection costs $103.00, as does each inspection beyond the number a permit allows. Inspections outside normal hours are billed at $103.00 an hour with a two-hour minimum, and work found started without a permit is charged an investigation fee of $103.00 an hour.
North Bend permit search and official resources
For an existing permit, its inspections or an old building file, contact the Building Department at 541-756-8525; permits handled in Oregon ePermitting can also be looked up in its public search. Flood maps for North Bend date from December 7, 2018, FEMA’s effective date for this participating National Flood Insurance Program community; the City’s Planning Department administers its floodplain rules.
- North Bend Building Department
- Do I need a building permit? (City handout)
- Site plan requirements
- Residential building permit requirements
- Residential mechanical permit requirements
- Demolition permit policy
- Permit expiration, extension and reinstatement
- January 27, 2026 council packet with Resolution 3379 and the 2026 fee exhibit
- Coos County Building Department (electrical and plumbing)
- BCD Local Building Department Directory
- 2026 Oregon Residential Specialty Code, chapter 1
- FEMA Community Status Book for Oregon
- Oregon ePermitting
- Oregon Construction Contractors Board
Inspections are where schedules slip.
Get a free quote →North Bend building permit FAQ
Does North Bend issue electrical and plumbing permits?
No. The City issues structural and mechanical permits; Coos County Community Development in Coquille issues and inspects North Bend’s electrical and plumbing permits, as BCD’s directory and the County’s own page both say.
How much is a building permit in North Bend?
It depends on the project value. A $150,000 project pays $1,438.69 for the permit, $935.15 for plan review and $172.64 in state surcharge under the fees in force since February 1, 2026.
When are inspections done?
Monday to Friday between 1:30 and 4 p.m. Call 541-756-8525 a day ahead, or two days ahead for a final on a new building.
Do I need a permit for a shed?
Not for a one-story nonhabitable shed of 200 sq ft or less and no more than 15 feet high, but it must still meet the zoning setbacks and lot coverage, so bring a site plan.
Do I need a permit to move dirt?
An excavation permit is needed to move more than 50 cubic yards of earth, or for any cut or fill on a site affected by a waterway or slope hazard.
Can my building permit be revived after it expires?
Within 180 days, yes: for 50% of the original permit fee up to 90 days after expiry, 75% from 90 to 180 days, or $80 if only final inspections are left.
Simplify North Bend permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Oregon. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in North Bend sooner?
Let Alliance prepare, file, and track your North Bend permits while your crew stays on the job.
More Oregon permitting guides
Coos County
Read guide →Coos Bay
Read guide →Douglas County
Read guide →Ontario Building Permit Guide
Read guide →Oregon City Building Permit Guide
Read guide →Polk County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about North Bend permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.