Crook County, Oregon Building Permit Guide

To get a building permit in Crook County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Crook County’s Building Department at the courthouse in Prineville issues every building permit in the county, the City of Prineville included; most permits can be applied for, paid and scheduled on Oregon ePermitting.

Authority: Crook County Community Development, Building DepartmentCode: 2026 ORSC, 2025 OSSCPhone: 541-447-3211
Authority
County Building Department300 NE 3rd St., Room 12, Prineville
Fees
FY 2026–27 scheduleEffective July 1, 2026
Inspections
Next business daySame day only if booked online by 7 a.m.
Permit life
180 daysEach approved inspection adds 180

The Crook County Building Department, part of Community Development in the county courthouse, issues all building permits in Crook County, including inside Prineville, the county’s only city. Contractors and owners can apply, pay and book inspections on Oregon ePermitting, though inspection cards are still picked up at the office. Under the fiscal 2026–27 schedule a new house valued at $150,000 carries a $976.00 structural permit fee, plus 75 percent plan review, the 12 percent state surcharge and a county code compliance fee.

What requires a building permit in Crook County?

The department reviews and inspects work under the state building codes and Title 15 of the Crook County Code, Buildings and Construction. Its residential forms cover one- and two-family dwellings, manufactured homes, accessory structures, remodels and additions, demolition and removal, residential solar and the separate electrical, mechanical and plumbing permits; the fee schedule adds re-roofing “when required,” fire sprinkler systems, floodplain development review and changes of occupancy.

Permit or county review needed

  • New houses, with mechanical plans filed alongside the structural plans for stick-built homes
  • Manufactured home placement, $704 for the placement permit
  • Accessory buildings, additions and remodels on the structural application
  • Farm and equine buildings, which go through a $76 agricultural exemption review
  • Development in a mapped floodplain, reviewed for $195
  • A change of occupancy with no structural work, $197

No building permit (2026 ORSC)

  • Detached one-story accessory buildings that are nonhabitable, up to 200 sq ft and 15 ft high (400 sq ft on 2 acres or more)
  • Decks, platforms and porches whose walking surface stays within 30 inches of grade
  • Window awnings projecting no more than 54 inches without extra support
  • Reroofing adding 4 psf of dead load or less, except for townhouses, solar roofing and roofs held to locally adopted wildfire standards
  • Fixed docks with no superstructure, in-ground pools at houses and freestanding tanks, unless a local ordinance requires a permit

The exemptions come from sections R105.2 and R101.2.2 of the 2026 Oregon Residential Specialty Code, whose chapter 1 is mandatory from October 1, 2026. Pool-barrier fences always need a permit. A shed under the exemption can still need county planning approval: the planning fee list includes a $100 site plan review for an accessory structure under 200 sq ft with no plumbing, electrical or mechanical work.

What the county decides and what the state holds

The county adopts its fee schedule each fiscal year and adds charges of its own on top of the state-based permit fees: a code compliance fee that pays for code enforcement and an advanced planning fee for long-range planning on larger projects. It also sets local installation details in its Applicable Regulations and Minimum Criteria sheet, such as an 18-inch frost depth. The codes, trade licensing and the 12 percent surcharge come from the state.

Short on time to read all of this?

Get a free quote →

Crook County building department: who handles permitting

The Building Codes Division’s Local Building Department Directory lists Crook County for all building permits in Prineville, Powell Butte, Paulina, Post and the rest of the county. There is no city building department, so the county also issues the trade permits inside Prineville.

Who handles what
PlaceBuilding and trade permitsLand useSeptic
PrinevilleCrook County Building DepartmentCity of PrinevilleCrook County On-Site program where sewer is not available
Unincorporated county, including Powell Butte, Paulina and PostCrook County Building DepartmentCrook County Planning DepartmentCrook County On-Site program
Crook County Community Development contacts
OfficeDetails
Building DepartmentCrook County Courthouse, 300 NE 3rd St., Room 12, Prineville, OR 97754; 541-447-3211; bld@crookcountyor.gov; Building Official Randy Davis
Planning DepartmentSame address and phone; plan@crookcountyor.gov
On-Site SepticSame address and phone; onsite@crookcountyor.gov
Parks and recreation district feeCity of Prineville, 541-447-2367

The county warns that fraudulent emails asking for wire transfers have come from addresses ending in @usa.com, and that only messages from @crookcountyor.gov or @accela.com addresses are genuine.

Permit types and approvals before filing

Residential permits

The dwelling and manufactured home applications are built to include everything needed to start, while other projects add separate discipline applications. A residential submittal includes the county applications, the zoning, moisture and lighting acknowledgements, the HVAC and whole-house ventilation checklist, an initial flood elevation certificate, the property owner statement, a complete plan set and a copy of the land use approval. Electronic plans are accepted as one PDF per discipline; uploads of single plan pages are rejected. In subdivisions that require fire sprinklers, the sprinkler plans and calculations come with the house application. The forms list also includes a residential dwelling contractor verification form.

Commercial permits

Commercial work has its own application page. A fire and life safety review at 40 percent of the structural fee is required on every structure over 4,000 sq ft and on any project the building official names. A complex or large project can book a pre-application consultation at $197 an hour with a two-hour minimum; phased projects pay $330 plus 10 percent of the total permit fee, capped at $1,500 a phase, and deferred submittals 65 percent of the fee on the deferred part, at least $315.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Land use: outside Prineville the county Planning Department issues the land use approval; applications go by email, in person or by mail. A residential site plan review is $1,124, an accessory structure review $305 and an accessory dwelling unit $1,286, each plus a code compliance fee ($189 on planning fees of $1,001 to $5,000).
  • Septic: the county On-Site program, working under DEQ authority, needs a site evaluation ($889) with at least three test holes before a construction permit ($1,098 for a standard system, more for capping fill, pressure distribution or sand filters); a DEQ surcharge is added, and the county may double a septic fee if work starts before the permit.
  • Parks district: a dwelling or manufactured home inside the Parks and Recreation District pays that district’s fee before the permit issues.
  • Floodplain: an initial flood elevation certificate is part of a residential submittal where it applies.

Building permit fees

The county’s fee schedule for fiscal year 2026–27 took effect July 1, 2026. Structural fees use the ICC valuation table current on April 1 each year.

Crook County structural permit fees (FY 2026–27)
Valuation or itemFee
$1 to $5,000$126 (the minimum structural fee)
$5,001 to $25,000$126 for the first $5,000, plus $10.00 per additional $1,000 or fraction
$25,001 to $50,000$326 for the first $25,000, plus $7.50 per additional $1,000 or fraction
$50,001 to $100,000$513.50 for the first $50,000, plus $5.00 per additional $1,000 or fraction
$100,001 and up$763.50 for the first $100,000, plus $4.25 per additional $1,000 or fraction
Structural plan review75% of the structural permit fee
Code compliance fee, new house or manufactured dwelling0.18% of valuation, up to $420
Code compliance fee, accessory buildings and additions0.18% of valuation, up to $299
Advanced planning fee0.30% of valuation, up to $105,000; waived under $300,000
Re-inspection or added inspection$132 each
New house plumbing (one kitchen)$364, $486 or $609 for one, two or three bathrooms
New house electrical$212 up to 1,000 sq ft, plus $35 per additional 500 sq ft
Residential re-roofing, when required$188
Temporary certificate of occupancy$284 residential; $473 commercial

Rather talk it over?

Call 1-855-478-4290 →

State surcharge, in the county’s words: the 12% state surcharge is “Required to be added to Building Permit Fees as per the State of Oregon, ORS 455.210(4) & (5) and 455.220(1),” and the mechanical, plumbing and electrical sections each say their permits are “subject to a State Surcharge of 12% of the total permit fee.” Residential demolition ($110) is marked as not subject to it.

Worked example: a new house valued at $150,000 is in the top band: $763.50 plus 50 × $4.25 = $976.00. Plan review adds $732.00, the 12 percent surcharge on the permit fee $117.12 and the code compliance fee $270.00, for $2,095.12; the advanced planning fee is waived below $300,000, and trade permits, land use and septic fees are extra.

Trade permits and who may pull them

All electrical, mechanical and plumbing permits in the county, Prineville included, come from the Building Department, each on its own application. Plumbing plan review, where needed, is 30 percent of the plumbing fee, and mechanical plan review 75 percent; residential mechanical work is priced per appliance, such as $20 for a heat pump or furnace up to 100,000 BTU and $22 for a wood or pellet stove, over the $126 minimum.

  • Owners: the county’s answer to “Can I do my own work?” is “In most cases, yes.” State law sets the limits: ORS 479.540 for owners wiring residential or farm property of their own or their immediate family that is not for sale, exchange, lease or rent, and ORS 447.060 for plumbing not done for hire.
  • Contractors: a contractor needs a Construction Contractors Board license, and electricians and plumbers working for hire need their state licenses. If the contractor changes, the county must be told in writing, and a new permit may be needed.
  • Owner-builders: the property owner statement on the residential forms list is the county’s form for owners; ORS 701.325 requires anyone exempt from CCB licensing to state the reason when applying.

Rather not deal with the Crook County building department?

Get a free quote →

How to apply

1. Get land use approval

From the county Planning Department outside Prineville, or the city inside it; the approval is part of the building submittal.

2. Clear septic or sewer

Apply to the On-Site program for a site evaluation if no sewer serves the lot.

3. Assemble the submittal

Applications, acknowledgements, ventilation checklist, owner statement and plans, one PDF per discipline if filed electronically.

4. File

On Oregon ePermitting, by email to bld@crookcountyor.gov, in person or by mail; large projects can ask for a pre-application meeting first.

5. Pay in two parts

The plan review fee is invoiced when the application is entered and must be paid before review starts; the rest is invoiced when the permit is ready to issue.

6. Pick up the cards

Collect the job locator card and inspection cards at the office after issue.

Review, corrections and what causes delay

Review does not start until the plan review fee is paid, and individual page uploads are rejected. Extra review caused by changes is $132 an hour with a half-hour minimum, and a change after approval goes on the revision application. Applications and permits stay active for 180 days, each approved inspection adds another 180, and the county emails or mails a notice before expiry; an extension request can be filed but is not guaranteed.

Inspections

Unless you ask for a later date, inspections happen the next business day between 8 a.m. and 4 p.m. Book through the ePermitting app or website; a same-day inspection is possible only when it is booked there before 7 a.m., and inspections booked by phone with the office cannot be same-day. Voicemail requests are not guaranteed. Because much of the county has no reliable cell coverage, the inspection cards, job location card and approved, legible color plans must be on site; without them an inspection can be marked not ready or denied, with added fees.

The county’s minimum criteria sheet sets the test pressures inspectors expect: at least 5 pounds of air for 15 minutes on waste and vent piping, 50 pounds for 15 minutes on water lines and 10 pounds for 15 minutes on gas piping. Water service lines go at least 30 inches deep, gas lines at least 18 inches with yellow tracer wire, and sewer lines carry green tracer wire.

Want this handled start to finish?

Get a free quote →

Code editions and flood maps

The 2026 Oregon Residential Specialty Code applies to new applications, with its construction chapters optional against the 2023 edition until April 1, 2027; commercial work is under the 2025 structural and mechanical codes, and the 2026 electrical and plumbing codes took effect October 1, 2026. The county’s May 2026 criteria sheet still lists the earlier residential, plumbing and electrical editions. Site wind and snow loads come from the Oregon Design Criteria Hub or the ASCE hazard tool. Both Crook County and Prineville take part in the National Flood Insurance Program (FEMA Community Status Book), with flood maps dated February 2, 2012.

Oregon’s building code and its exemptions are the same in Crook County as everywhere in the state, and an exemption from the building permit is not an exemption from zoning, land use or a trade permit. Site snow, wind and seismic values come from the state’s Oregon Design Criteria Hub. How Oregon’s statewide code works

Crook County building permit FAQ

Does Prineville have its own building department?

No. Crook County issues all building and trade permits inside Prineville; the city handles zoning and is the contact for the parks district fee.

What does a permit for a new house cost?

At $150,000 of value: $976.00 permit, $732.00 plan review, $117.12 surcharge and $270.00 code compliance, before trade and septic fees.

Can I get a same-day inspection?

Only by booking on the ePermitting app or website before 7 a.m.; phone requests to the office are scheduled for a later day.

Can I apply online?

Most permits can be applied for and paid on Oregon ePermitting, but the inspection cards are picked up at the office.

Who issues septic permits?

The county On-Site program; a site evaluation is $889 and a standard system permit $1,098, plus the DEQ surcharge.

Do I need a permit for a small shed?

Not a building permit if it is one story, nonhabitable, 200 sq ft or less and no more than 15 ft tall, but outside Prineville the county’s planning review of one with no utilities costs $100.

Permit search and official resources

Permit history for every property in the county is public on Oregon ePermitting, and the county posts a user guide for the site and a research guide for the public. If a search comes up empty, the Planning Department takes requests at plan@crookcountyor.gov.

Inspections are where schedules slip.

Get a free quote →

Simplify Crook County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Oregon. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Crook County sooner?

Let Alliance prepare, file, and track your Crook County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Crook County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.