To get a building permit in Ashland, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Ashland’s Building Division at 51 Winburn Way issues every building, electrical, plumbing and mechanical permit in the city, most of them through the City’s Citizen Self Service portal.

Authority: Ashland Building DivisionCode: 2025 OSSC; 2026 ORSC (phase-in to April 2027)Phone: 541-488-5305
Authority
Ashland Building Division51 Winburn Way
Walk-in
Mon–Thu, 9 a.m. to 1 p.m.Office open Mon–Fri, 8 to 4:30
Plan review
65% of permit feeDue at application
New fees
January 1, 2027Resolution 2026-25

The City of Ashland’s Building Division, part of Community Development, reviews plans and issues and inspects structural, electrical, plumbing and mechanical permits for all work in the city. Most permits are applied for in the City’s Citizen Self Service portal, while full packages for new buildings go to the division by email. Plan review is 65% of the structural permit fee, and a new fee schedule adopted on September 15, 2026 takes effect on January 1, 2027.

The division works from 51 Winburn Way, is open Monday to Friday from 8 a.m. to 4:30 p.m. (541-488-5305, Building@ashlandoregon.gov), and keeps walk-in hours Monday to Thursday from 9 a.m. to 1 p.m. for public information requests, inspection scheduling, permit payments and general building and land use questions; for a specific property or a particular staff member, book a meeting. Steven Matiaco is the Building Official. Ashland, in Jackson County, had 20,889 residents in the Census estimate for 2025.

Ashland permits apply inside the city limits. Properties outside them, even within the Ashland School District, go to Jackson County for building permits.

What requires a building permit in Ashland?

New buildings, additions, remodels, higher decks, reroofs on townhouses and new electrical, plumbing or mechanical work all need permits in Ashland. The City adds one point many owners miss: a permit is needed to document a change of use or occupancy of a building even when no construction is planned, so an old house turned into an office must be brought up to the life safety rules for an office.

Permit required

  • New houses, accessory residential units and multifamily buildings
  • Additions, remodels and decks more than 30 inches above grade
  • Pool barriers, and pools filed on the City’s pool permit form with its barrier acknowledgment
  • Changes of use or occupancy, even with no alterations
  • Solar and other renewable energy systems
  • Grading and excavation, fire alarms and sprinklers, signs and fences on the City’s permit list
  • A toilet room or bathroom in an otherwise exempt shed

No building permit (2026 ORSC)

  • Nonhabitable one-story detached structures up to 200 sq ft and 15 feet high, with no sleeping or cooking
  • Decks and porches 30 inches or less above grade within 3 feet of the walking surface
  • Deck, patio or porch covers up to 200 sq ft at least 3 feet from lot lines
  • Reroofing that adds 4 psf or less of dead load, except on townhouses and stacked two-family dwellings
  • Wood, wire mesh and chain link fences up to 7 feet that are not pool barriers

What Ashland decides and what the state holds

The exemptions are the state’s, in sections R105.2 and R101.2.2 of the 2026 Oregon Residential Specialty Code, mandatory since October 1, 2026; R101.2.2 leaves in-ground pools at houses permit-free unless a local ordinance requires a permit, while pool barriers always need one, and Ashland publishes its own pool permit application. Owners who build an exempt shed sign the City’s acknowledgment form, which warns that wiring, plumbing or heating in it still needs permits, that heating it triggers water and sewer system development charges by heated floor area, and that converting it to living space later can be costly. Ashland sets its own fees, wildfire submittal steps, business license rule and inspection policies.

Short on time to read all of this?

Get a free quote →

Oregon’s building code and its exemptions are the same in Ashland as everywhere in the state, and an exemption from the building permit is not an exemption from zoning, land use or a trade permit. Site snow, wind and seismic values come from the state’s Oregon Design Criteria Hub. How Oregon’s statewide code works

Ashland building department: who handles permitting

The Building Division handles plan review and inspections in every trade; BCD’s directory lists Ashland as providing all building permits. Planning reviews land use actions, zoning permits, fences, signs and tree removals, many of them also filed in Citizen Self Service, and Public Works issues right-of-way closures and street and alley excavation permits. Ashland Fire and Rescue reviews fire code items such as access and hydrants. Under Resolution 2026-25 its percentage-based plan check fee becomes an hourly charge in 2027.

Ashland permitting contacts
DetailInformation
Building Division51 Winburn Way, Ashland, OR 97520
Phone and email541-488-5305; Building@ashlandoregon.gov; fax 541-488-6006
HoursMonday to Friday, 8 a.m. to 4:30 p.m.; walk-in Monday to Thursday, 9 a.m. to 1 p.m.
Building OfficialSteven Matiaco, 541-552-2077
Inspection requestsCitizen Self Service, or 541-552-2080
Online portalCitizen Self Service (Tyler EnerGov)

Permit types

Residential permits

Remodels, additions, decks, new homes, accessory dwelling units, solar and separate electrical, mechanical and plumbing permits can all be applied for in Citizen Self Service, and a Carbon Pollution Impact application is required there for every new residential unit. The residential submittal form asks for PDF plans at least 11 by 17 inches, design criteria and a code analysis, gross floor area and total impervious surface, the planning action number if the lot went through land use review, a plot plan with drains, sewer, water and the electrical panel, and a framing section identifying materials that comply with section R327, the code’s wildfire hazard mitigation chapter. It also asks for the distance to the nearest fire hydrant and a Wildfire Mitigation Plan Submittal Form. Roof snow load defaults to 25 psf.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Tenant improvements can be filed online; complete packages for new commercial buildings and new multifamily construction are emailed to the division with plans and supporting documents. Commercial forms include a special inspection agreement, a seismic statement of contractor responsibility, a registered design professional form, a high-piled storage form, a kitchen hood verification and accessibility reports for alterations of existing buildings. Commercial plan review is 65% of the structural permit fee plus 40% for fire and life safety review when it applies; a shell building is valued at 80% of the building valuation and the later tenant improvement at 20%.

What comes before the building permit

Before buying or leasing a site for a business, the City asks owners to check that the use is allowed, what building and zoning work it triggers and which system development charges apply. Pre-application conferences, zoning permits and Type I land use actions are filed in the same portal, and conditions from any planning action must appear on the building plans. The City collects the Ashland School District construction excise tax at permit issuance on new floor area. On FEMA’s Community Status Book, Ashland’s current flood map took effect on April 5, 2017, and the city is a National Flood Insurance Program participant.

Ashland permit costs and fees

Fees until December 31, 2026 are those on the Building Division’s posted schedule, labelled effective July 1, 2026; when the Council adopted the 2026–27 Miscellaneous Fees and Charges on May 19, 2026, it left building and planning fees out of that year’s 3.1% increase. Valuation for new buildings and additions uses the ICC table in force each April 1; carports, covered porches and decks are valued at half the private garage rate, and alterations at fair market value set by the Building Official. The schedule words the surcharge this way: the “State of Oregon permit surcharge is 12% of structural, plumbing, mechanical and electrical components of the overall building permit.” Building permits also pay a Community Development Fee, now 1.2% of the construction valuation.

Rather talk it over?

Call 1-855-478-4290 →
Ashland building fees, Miscellaneous Fees and Charges effective July 1, 2026
ItemFee or rule
Value $1 to $500$92.35 per hour
$501 to $2,000$92.35 for the first $500 plus $10.30 per added $1,000 or fraction
$2,001 to $25,000$112.85 for the first $2,000 plus $8.25 per added $1,000
$25,001 to $50,000$301.65 for the first $25,000 plus $8.25 per added $1,000
$50,001 to $100,000$506.80 for the first $50,000 plus $5.15 per added $1,000
$100,001 and up$763.30 for the first $100,000 plus $4.15 per added $1,000
Plan review65% of the structural permit fee, due at application; fire and life safety 40%
New house plumbing$410.40 one bath, $512.95 two, $589.90 three
New house electrical$138.50 up to 1,000 sq ft, plus $25.65 per added 500 sq ft
Mechanical minimum$76.95
Re-inspection or added plan review$92.35 an hour, half-hour minimum
Demolition$369.35 review for non-exempt structures, plus $92.35 permit
Temporary certificate of occupancy$51.30 per discipline, renewed every 30 days

Worked example. A $150,000 project falls in the top band: $763.30 plus 50 × $4.15 ($207.50) is a permit fee of $970.80. Plan review at 65% adds $631.02, the 12% surcharge $116.50 and the 1.2% Community Development Fee $1,800, for $3,518.32 before trade permits. The example stays in one band because Ashland’s bands do not join: $112.85 plus 23 × $8.25 is $302.60, not the $301.65 the next band starts from.

⚠️ New fees from January 1, 2027. The City Council adopted Resolution 2026-25 on September 15, 2026. From January 1, 2027, permits for houses and townhouses cost $135 up to $15,000 of value, $135 plus $9 per $1,000 to $100,000, $900 plus $5 per $1,000 to $375,000 and $2,275 plus $8 per $1,000 above; other structural permits cost $135 up to $13,000, $130 plus $10 per $1,000 to $100,000 and $1,000 plus $7 per $1,000 above. The Community Development Fee rises to 1.5%, a new 3% technology fee applies to the building permit fee, and Ashland Fire and Rescue’s plan check of 24% of the structural permit and plan check fees becomes $125 an hour, billed only when Fire reviews items outside the building code. The same $150,000 house would pay a $1,150 permit fee.

Hourly charges differ: the exhibit adopted with Resolution 2026-25 was drawn on the version with the 3.1% increase and prints re-inspection and other hourly charges at $95.20 for 2027, while the $92.35 rate on the posted schedule applies until then. The City’s notice to the state estimated the overall increase at 35%, the first since 2020, with smaller projects under $50,000 paying less than now.

Rather not deal with the building department?

Get a free quote →

Trade permits and who may pull them

Ashland issues its own electrical, plumbing and mechanical permits, applied for in Citizen Self Service. The division will not perform inspections until every subcontractor is listed with an Ashland business license number and a CCB number and the licenses have been checked.

Owner doing the work

  • Owner, not for sale, rent, lease or exchange: may do structural, mechanical, plumbing and electrical work
  • Owner building to sell: licensed contractors do the work, unless the owner is a licensed general contractor, who may do the structural and mechanical work and, personally, the plumbing
  • Owner building to rent or lease: structural, mechanical and plumbing work
  • Renters: structural and mechanical work, unpaid and not for sale; the owner’s regular employees: the same, if not for sale

Contractors

  • A Construction Contractors Board license for paid work
  • An Ashland business license for every contractor and subcontractor
  • Licensed electricians and plumbers for hired trade work
  • Landlords may do limited electrical maintenance, such as like-for-like appliance swaps up to 30 amps

How to apply for an Ashland building permit

1. Check the use and zoning

Call or visit during walk-in hours to confirm the use is allowed and whether a planning action, pre-application conference or zoning permit is needed.

2. Create a Citizen Self Service account

The City posts guides for registration, applying and the dashboard; you must be a listed project contact to schedule inspections.

3. Assemble the submittal

Use the residential or commercial package checklist, with the wildfire mitigation form, energy forms and plot plan.

4. File online or by email

Apply in the portal; email complete packages for new multifamily and new commercial buildings to the Building Division.

5. Pay plan review and answer comments

Plan review is due at application; send revisions with the revision request form.

6. List your subcontractors and pay

Give each trade’s business license and CCB numbers, then pay the permit, surcharge and Community Development Fee at issuance.

Review, corrections and what causes delay

Ashland publishes no review clock. Missing subcontractor information stops inspections, a missing energy form puts the application on hold, and changes after approval cost an hourly plan review fee plus any added valuation. A permit expires 180 days after issue with no inspection activity; reactivating it costs $50 for each construction discipline, or half the original fee where that fee was under $50. Refunds are possible only for issued permits with no inspections that have not expired; plan check and fire review fees are not refunded, and a $50 administrative fee is deducted.

Want this handled start to finish?

Get a free quote →

Inspections in Ashland

Inspections are done between 7 a.m. and 3:30 p.m. on 24 hours’ notice. Schedule them in Citizen Self Service, as a listed project contact, or by phone at 541-552-2080. Under the division’s timed inspection policy, a set time is given only for homeowners with competing commitments, contractors who must let the inspector in, meetings with the inspector, concrete pours and pumps, and other cases the inspector approves.

When the inspector asks, the permit holder must expose the property pins and run string lines so the inspector can check distances, or a survey may be required. Re-inspections are billed at the hourly rate with a half-hour minimum, inspections outside business hours at $133.40 an hour per inspector, and a temporary certificate of occupancy at $51.30 per discipline for each 30 days; reissuing a certificate of occupancy is free.

Ashland permit search and official resources

Citizen Self Service lets anyone research permits and applications processed by the City from 2018 on. The Building Division also posts a monthly report of every permit issued by the 10th of the following month, and older records and occupancy history come through the City’s public records request portal.

Inspections are where schedules slip.

Get a free quote →

Ashland building permit FAQ

How much is a building permit in Ashland?

Through December 31, 2026, a $150,000 project pays a $970.80 permit fee, $631.02 for plan review, $116.50 in state surcharge and $1,800 in Community Development Fee. From January 1, 2027 the permit fee for the same house is $1,150, with a 1.5% Community Development Fee and a 3% technology fee.

Can I apply online?

Yes. Most building, trade, planning and public works permits go through Citizen Self Service; full packages for new multifamily and new commercial buildings are emailed to the Building Division.

Do I need a permit for a shed?

Not for a nonhabitable one-story shed up to 200 sq ft and 15 feet tall with no sleeping or cooking. You sign the City’s acknowledgment form, and any wiring, plumbing or heating needs its own permit.

How do I schedule an inspection?

In Citizen Self Service if you are a listed project contact, or by calling 541-552-2080, at least 24 hours ahead. Inspections run from 7 a.m. to 3:30 p.m.

Can I walk in without an appointment?

Monday to Thursday from 9 a.m. to 1 p.m., for information, inspection scheduling and payments. Questions about a specific project are best handled in a scheduled meeting.

Can a homeowner do their own electrical work?

Yes, if you own the home and it is not for sale, rent, lease or exchange, with an electrical permit and inspections.

Simplify Ashland permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Oregon. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Ashland sooner?