Garfield County issues no building permits; Enid permits inside the city, and the county commissioners permit only floodplain development, driveway entrances and road crossings.

Authority: Garfield County Commissioners (floodplain and road permits)Filing: 114 W. Broadway, Room 101, Enid, or permits@garfieldok.comPhone: 580-237-0227
2025 population
61,779
County building permits
None
Enid Community Development
580-616-7213
Floodplain elevation
1 ft above base flood elevation

Garfield County does not issue building permits: the state’s code commission lists it as a non-issuing county, and it is not on the State Fire Marshal’s list of counties that review and inspect buildings. The Board of County Commissioners (114 W. Broadway, Room 101, Enid; 580-237-0227) issues the county’s own permits for floodplain development, driveway entrances and road crossings. Inside Enid, the city’s Community Development Department (580-616-7213) permits and inspects construction.

Who issues permits in Garfield County?

For unincorporated land there is no county building permit or building inspection. The Commissioners’ Permits page carries the permits the county does issue:

Garfield County permits
PermitWhere to file
Floodplain Development Permit ($25)Garfield County Commissioners, Attn: Floodplain Administrator, 114 W. Broadway, Room 101, Enid, OK 73701; 580-242-6013 (the OWRB lists the county administrator at 580-541-1941); permits@garfieldok.com
Driveway entrance on a county roadBoard of County Commissioners; notify the district commissioner or the Highway Superintendent at least 5 days before work
Road crossing or line installationCounty Clerk, by noon on the Wednesday before a commissioners’ meeting, with the fee check
Courthouse lawn and gazebo useCommissioners’ office, 580-237-0227

The fourteen incorporated places split as follows, according to the State Fire Marshal’s July 2026 list of jurisdictions that do their own plan review, permits and inspections and the Uniform Building Code Commission’s jurisdiction list:

Short on time to read all of this?

Get a free quote →
Building permits in Garfield County’s towns
TownBuilding permits
EnidCommunity Development Department; applications by email to EnidCD@enid.org or at the office; 580-616-7213, Monday to Friday 8 a.m. to 5 p.m.
DrummondTown of Drummond, added to the State Fire Marshal list in March 2026; 580-493-2900
CovingtonThe state lists disagree: on the State Fire Marshal list since January 2026, but marked as not issuing permits by the code commission; ask the town, 580-864-7428
Breckenridge, Carrier, Douglas, Hillsdale, Hunter, KremlinListed by the state as not issuing permits
North EnidTown office issues building and roofing permits; processing can take up to 10 working days, and roofing without a permit carries a $275 fine; 220 Redwood, 580-234-5941 ext. 3
Fairmont, Garber, Lahoma, WaukomisNot on the State Fire Marshal list and not marked as non-issuing by the state; ask the town: Fairmont 580-358-2282, Garber 580-863-2254, Lahoma 580-796-2600, Waukomis 580-758-3242

Trades, septic and commercial buildings

Outside the permitting towns there are no county electrical, plumbing or mechanical permits; contractors carry Oklahoma Construction Industries Board licences, and Enid issues trade permits inside the city.

Septic: the Oklahoma Department of Environmental Quality permits on-site sewage systems through its 581 soil report and an Authorization to Construct, and DEQ or a certified installer inspects the installation.

Commercial buildings: with no county building authority, commercial plans for unincorporated Garfield County go to the State Fire Marshal through its Accela Citizen Portal.

Garfield County permit costs

There is no county building permit fee. The county’s permit documents set these costs and responsibilities:

Not sure this scope needs a permit?

Get a free quote →
  • Driveway entrances: for an agricultural or residential entrance, the commissioners provide up to one 30 ft culvert per property, with the type and size chosen by the district commissioner; any further culverts or driveways are the owner’s cost. A commercial entrance is built with materials and labor supplied by the business.
  • Floodplain permits: $25, set in Section 5.7 of the county’s 2019 Floodplain Regulations.
  • Road crossings and line installations: paid by check to the Garfield County Commissioners with the application, under the schedule below; facility owners must also restore the road and right-of-way at their own expense when a site is decommissioned.
Garfield County road crossing fees (schedule of August 2022)
ItemFee
Road bored$500 per line
Cut or trenched$2,500 per line
Over-the-road crossing$2,500
Overhead line$500
Parallel overhead line$500 per mile
Parallel water line$250 per mile per line
Crossing through an existing culvert or under a bridge$250
30-day renewalSame as the original permit

Inside Enid and the other permitting towns, building permit fees follow the town’s own schedule.

Rather talk it over?

Call 1-855-478-4290 →

What the floodplain application asks for

Floodplain Development Permit

  • General description and legal description of the work, with directions to the site
  • A FEMA FIRMette or other map with the site circled; FIRM map number and effective date; flood zone
  • Latitude and longitude and the name of the creek, lake or water body
  • Type of work: new construction, addition, remodel, demolition, manufactured home, fill, excavation, storage, mining, drilling or pipeline
  • Lowest finished floor, lowest adjacent grade and base flood elevation, with the engineer and surveyor named
  • Whether the site is in the floodway, and whether locations outside the floodplain were considered

Road crossing or line

  • Completed crossing permit (February 2024 revision)
  • A notification letter listing the route, legal descriptions and abutting landowners
  • For a culvert in county right-of-way, a storm-water mitigation plan
  • The fee check, payable to the Garfield County Commissioners

How to plan a project in unincorporated Garfield County

1. Confirm the site is outside a permitting town

Inside Enid, file with Community Development; check the town table above for the smaller towns.

2. Check the flood map

If the site is in a special flood hazard area, file the Floodplain Development Permit before any building, fill or excavation.

3. Plan the entrance

Apply for a driveway entrance and give the district commissioner or Highway Superintendent 5 days’ notice before work.

4. File any road crossing

Lines under or over county roads need the crossing permit, filed with the County Clerk by Wednesday noon before a board meeting.

5. Get the septic authorization

Order DEQ’s soil report and Authorization to Construct.

6. Send commercial plans to the State Fire Marshal

Use the Accela Citizen Portal.

Rather not deal with the Garfield County building department?

Get a free quote →

Inspections

No county inspector checks buildings in unincorporated Garfield County. The floodplain permit authorizes county staff to enter the site to inspect, and a registered engineer, architect or land surveyor must certify the finished floor elevation or floodproofing. After a road crossing, the contractor calls the Highway Superintendent’s office for an on-site inspection. DEQ or a certified installer inspects septic systems, and the State Fire Marshal inspects commercial buildings it permits.

Local Garfield County rules

Floodplain: a home’s lowest floor, including any basement, must be at least 1 ft above the base flood elevation; a non-residential building must be elevated 1 ft or floodproofed. Utility equipment must be elevated, and water and sewer lines need automatic backflow devices. Work in a floodway is permitted only on an engineer’s study showing no rise in the base flood elevation. The Board of County Commissioners signs off each floodplain permit.

County roads: crossings must be bored, never blasted, and trenching needs the commissioner’s approval. Buried lines go at least 5 ft below the road center and 4 ft below the ditch bottom, overhead lines need 20 ft of clearance, and no boring or ditching is allowed within 50 ft of a quarter-section corner or 200 ft of a bridge.

Oklahoma building code

Oklahoma sets statewide minimum codes (the 2024 editions since September 14, 2026) that cities enforce and may strengthen; most counties issue no building permits for unincorporated land, though a few do. Oklahoma rules

Want this handled start to finish?

Get a free quote →

Official Garfield County permit resources

Garfield County permit FAQs

Inspections are where schedules slip.

Get a free quote →

Does Garfield County issue building permits?

No. The state lists Garfield County as issuing no building permits. The county issues floodplain, driveway entrance and road crossing permits.

Who issues building permits in Enid?

The City of Enid Community Development Department, which takes applications at its office or by email to EnidCD@enid.org (580-616-7213, Monday to Friday 8 a.m. to 5 p.m.).

How high must a house sit in a Garfield County floodplain?

At least 1 ft above the base flood elevation, certified by a registered engineer, architect or land surveyor.

Will the county supply a culvert for my driveway?

For an agricultural or residential entrance, the commissioners provide up to one 30 ft culvert per property; extra culverts and commercial entrances are the owner’s cost.

Who approves a septic system in Garfield County?

The Oklahoma Department of Environmental Quality, which issues the Authorization to Construct.

Where do I file a county floodplain permit, and what does it cost?

The fee is $25. File with the Garfield County Commissioners, Attn: Floodplain Administrator, 114 W. Broadway, Room 101, Enid (580-242-6013, permits@garfieldok.com).

Simplify Garfield County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Oklahoma. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Garfield County sooner?

Let Alliance prepare, file, and track your Garfield County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Garfield County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.