Tuscarawas County government has no county zoning resolution and no building or zoning department, the County Planning Commission confirmed in an October 21, 2026 letter. Commercial, industrial, institutional and larger multi-family buildings are reviewed by the East Central Ohio Building Authority (ECOBA) at 339 Oxford Street in Dover (330-364-3164) everywhere except Barnhill, Port Washington and Roswell, which use the state. Houses are outside ECOBA’s scope; local permits come from the cities and villages and from the zoning offices of Dover, Sandy and Lawrence townships, and the County Health Department permits septic systems and wells.
What requires a building permit in Tuscarawas County?
Which approvals a project needs depends on where it is and what it is. The County Planning Commission’s October 2026 letter lists the bodies that require building or development permits:
- Commercial, industrial, institutional and multi-family buildings of four or more units or four or more stories: plan approval from ECOBA, or from the state in Barnhill, Port Washington and Roswell
- Zoning and building permits in Dover, Sandy and Lawrence townships, each of which has its own zoning and building inspector
- Local permits inside every city and village, from that municipality’s own office
- Development in flood-impacted areas, reviewed through the Tuscarawas Soil and Water Conservation District
- Land in the Harry Clever Field airspace zone, regulated by airport hazard zoning administered by the City of New Philadelphia
- Land under a federal flowage easement around the U.S. Army Corps of Engineers reservoirs and flood-control dams
County agencies add their own permits: the County Health Department for sewage treatment systems and private water systems, and the County Engineer for driveways and other work in county road rights-of-way. ECOBA’s list of commercial projects needing approval includes new buildings, additions, alterations and changes of use, industrialized units, storage tanks, towers, signs, tents, swimming pools, fences over 7 feet and retaining walls over 4 feet. It does not review detached one-, two- and three-family homes under four stories, one-story detached accessory buildings under 120 square feet, or agricultural buildings.
What the county decides and what the state holds
The building codes are statewide, and ECOBA notes that even the homes outside its review must be built to the Residential Code of Ohio. Under state law, where no department certified for residential buildings has jurisdiction, the owner is not required to submit plans for a house (ORC 3791.04(A)(1)); the Board of Building Standards look-up map shows whether a certified residential department covers a given address. The county itself controls subdivisions and lot splits through its Planning Commission, county road access through the Engineer, and septic and well rules through the Health Department.
Tuscarawas County building department: who handles permitting
ECOBA was created by the county commissioners and is run as a division of the Economic Development and Finance Alliance of Tuscarawas County. The Board of Building Standards certified it for the county’s townships on November 1, 2004 and added Dover and New Philadelphia on January 11, 2005; its 2024 policy covers the whole county except Port Washington, Barnhill and Roswell, which the state’s Division of Industrial Compliance serves. ECOBA’s Chief Building Official is Nicholas L. Montan. Plumbing is excluded from its certification: the state keeps plumbing jurisdiction throughout Tuscarawas County.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| East Central Ohio Building Authority (commercial plans and inspections) | 339 Oxford Street, Dover, OH 44622; 330-364-3164; fax 330-364-4690 |
| Ohio Division of Industrial Compliance (commercial in Barnhill, Port Washington, Roswell) | Factory and Building Plans Examination, 4661 Belpar Street, Canton, OH 44718; 800-643-4842 |
| State plumbing section (all of the county) | 800-523-3581, ext. 2; inspections ext. 1, per ECOBA |
| County Planning Commission (subdivisions, lot splits, private drives) | 125 East High Avenue, Suite 210, New Philadelphia; 330-365-3246; 8:00 a.m. to 4:30 p.m. |
| Tuscarawas County Health Department (septic, wells, home-sale inspections) | 897 East Iron Avenue, Dover, OH 44622; water quality program 330-343-5550 |
| County Engineer (county road permits) | Permit forms on the Engineer’s page; fees due before approval |
| Tuscarawas Soil and Water Conservation District (flood-impacted areas) | 85 East Iron Avenue, Dover; 330-339-7976 |
Cities, villages and townships
The county has three cities and sixteen villages (Baltic lies partly in Holmes County). The Planning Commission tells applicants to contact each city or village directly for its building regulations and permits.
| Community | Local permits / commercial plans |
|---|---|
| New Philadelphia (17,424) | Service Director’s Office, 150 East High Avenue / ECOBA |
| Dover (12,947) | Building and Zoning Department, 321 North Wooster Avenue / ECOBA |
| Uhrichsville (5,145) | City offices / ECOBA |
| Newcomerstown, Strasburg, Dennison, Sugarcreek, Gnadenhutten, Tuscarawas, Bolivar, Baltic, Midvale, Mineral City, Parral, Stone Creek, Zoar | Village offices / ECOBA |
| Port Washington, Barnhill, Roswell | Village offices / Ohio Division of Industrial Compliance |
| Dover, Sandy and Lawrence townships | Township zoning and building inspectors: 330-343-6413, 330-365-1002 and 330-874-2731 / ECOBA |
| Other townships | No county zoning; ECOBA for commercial work |
Tuscarawas County permit types
Because the county issues no building permit itself, a rural project gathers approvals from several offices. The County Auditor’s parcel search and the county tax-map GIS show which township or municipality a parcel is in, which decides the local office.
Not sure this scope needs a permit?
Get a free quote →Residential permits
- Sewage treatment system. Work with a septic designer, submit the plans to the Health Department, which visits the site and approves the design, then hire a registered installer; a permit to install must be issued before any work on the system, and the department makes a final inspection. Keep the planned leach field or mound area free of traffic and grading during construction. Inside New Philadelphia, the city’s own health department answers septic and well questions.
- Private water system. A well needs a Health Department installation permit; registered water system contractors drill and complete it.
- Township or village zoning. In Dover, Sandy and Lawrence townships and in the municipalities, a zoning or building permit comes from the local office.
- County road access. A new drive onto a county road needs the Engineer’s $20 drive permit; other work in the county right-of-way needs a right-of-way permit.
- Selling a home. A property with a well or septic system cannot be sold or transferred until the system is evaluated and the Health Department issues a certificate of transfer, unless the transfer is exempt.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and industrial buildings, apartment buildings with four or more units and buildings of four or more stories need plan approval before construction. ECOBA asks for construction documents sealed, signed and dated by a registered design professional, uploaded to an online Box folder with its Application for Plan Approval and fee worksheet; it can also issue phased approvals and annual approvals for ongoing alterations. Plumbing plans go to the state with the state’s own application.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Lot creation. Lot splits, major subdivisions and dedicated private drives go through the County Planning Commission, whose forms were updated in 2025 and October 2026; the forms include an affidavit for skipping Health Department review when a new lot is vacant or agricultural.
- Septic suitability. The site review ($425) confirms a lot can take a sewage system before a house is designed around it.
- Flood and flowage areas. Check with Soil and Water for flood-impacted land and with the Corps of Engineers for flowage easements near its reservoirs.
- Local zoning. Clear township or municipal zoning first where it exists.
Tuscarawas County permit costs and fees
There is no county building permit fee because there is no county building department. The posted fees belong to ECOBA (commercial plan approval), the Health Department (2026 environmental health fees) and the County Engineer (fees effective July 22, 2026).
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| ECOBA structural plan exam and inspection | $275 processing + $10.50 per 100 sq ft |
| ECOBA mechanical, electrical or fire suppression | $275 + $6.50 per 100 sq ft, each |
| ECOBA fire alarm | $275 + $6.50 per device |
| ECOBA re-examination of plans / preliminary review | $250 + $150 an hour / $150 an hour |
| ECOBA re-inspection penalty / certificate of occupancy | $150 / $75 |
| Sewage system site review | $425 |
| New or replacement household sewage system permit | $774 |
| Sewage system alteration / tank-only replacement | $535 / $285 |
| Private water system installation permit (single family) | $484 |
| Point-of-sale inspection: water / sewage / both | $75 + lab / $350 / $425 + lab |
| County Engineer drive permit, new drive on a county road | $20 |
| County Engineer right-of-way permit / special hauling permit | From $200 / $100 |
Worked example (ECOBA). Plan approval for the structural work on a 2,000 sq ft commercial building is $275 + 20 × $10.50 = $485; mechanical and electrical approvals for the same floor area are $275 + 20 × $6.50 = $405 each. ECOBA’s schedule, dated effective November 1, 2017, bases fees on the area affected, which may extend beyond the construction itself, and the state’s 3% assessment on nonresidential fees is collected on top. A new septic system costs $425 for the site review plus $774 for the installation permit, $1,199 in all before the installer’s price. Lot split and subdivision fees are on the Planning Commission’s fee schedule.
Trade permits and who may pull them in Tuscarawas County
Commercial electrical, mechanical, fire suppression and fire alarm work is reviewed and inspected by ECOBA (or the state in the three excluded villages) as part of the building’s plan approval, each with its own line on the fee worksheet. Plumbing everywhere in the county stays with the state’s plumbing section, so commercial plumbing plans are sent to the Division of Industrial Compliance.
Rather not deal with the Tuscarawas County building department?
Get a free quote →- State licenses: commercial electrical, HVAC, hydronics, plumbing and refrigeration contractors need an Ohio Construction Industry Licensing Board license.
- Septic contractors: the Health Department registers sewage system installers and service providers for $325 each, and only a registered installer may build a system under permit.
- Well contractors: private water systems are installed and evaluated by registered water system contractors.
- Local registration: the county has none, but cities and villages may require it; Dover, for example, registers electrical, plumbing, HVAC and roofing businesses every year.
ECOBA’s pages describe no homeowner exemption for commercial buildings. For a house outside any certified residential department, an owner deals mainly with the Health Department, the Engineer and the local zoning office.
How to apply for permits in Tuscarawas County
Use the auditor’s parcel search to find the township or municipality, then check the BBS look-up for certified departments.
Contact the city or village, or Dover, Sandy or Lawrence township, about zoning and local building permits.
File lot splits, subdivisions or private-drive applications with the County Planning Commission.
Order the septic site review and well permit from the Health Department before final house plans.
Schedule a plan exam, upload sealed plans and pay the plan approval fee; send plumbing plans to the state.
Apply to the County Engineer for a drive or right-of-way permit before building a drive onto a county road.
Review, corrections and what causes delay
ECOBA reviews small commercial projects, roughly eight sheets or up to $500,000 of work, on the day of a scheduled appointment in most cases, and larger projects within about two business weeks; appointments should be requested one to two business days ahead, and approved plans can be downloaded only after every fee is paid. For rural houses the septic review is the key step: the site, soils and design must pass the Health Department’s review before a permit to install is issued. Road permits are not approved until the Engineer’s fee is paid.
Inspections in Tuscarawas County
Each agency inspects its own approvals. ECOBA inspects commercial construction: request inspections at least a day ahead online or through the inspector, have the approved drawings posted, the lot lines marked and the site open, and send the completed inspection log to the building official for the certificate of occupancy. A missed or premature inspection carries a $150 penalty.
- Septic systems: the Health Department makes the final inspection and approves or disapproves the installation.
- Plumbing: state plumbing inspections are requested through the state plumbing section.
- Property sales: wells and septic systems are evaluated before transfer by the Health Department or, for wells, a registered water system contractor.
- Houses: where a township, city or village issues local permits, ask that office which site checks it makes.
Want this handled start to finish?
Get a free quote →Ohio building code in Tuscarawas County
ECOBA enforces the Ohio Building Code for commercial buildings across most of the county, and the state does so in Barnhill, Port Washington and Roswell. FEMA’s Community Status Book lists Tuscarawas County’s unincorporated area (community 390782) as participating in the National Flood Insurance Program, with a current flood map dated October 19, 2018; Dover and New Philadelphia participate separately.
Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Tuscarawas County permit search and official resources
Records sit with the office that issued the approval. The Health Department posts well and septic permit records online for residents and accepts public records requests in person at 897 East Iron Avenue, by e-mail, by mail or by phone at 330-343-4928, without requiring the request in writing. Ask ECOBA for commercial plan approvals and certificates of occupancy, the Planning Commission for lot split and subdivision files, and the township, city or village for local permits.
- Building permits and zoning in Tuscarawas County, County Planning Commission, October 21, 2026
- Tuscarawas County Planning Commission
- Planning Commission forms, fee schedule and meeting dates
- County Engineer permit forms and fees
- East Central Ohio Building Authority
- ECOBA jurisdiction and state plumbing note
- ECOBA step-by-step plan approval guide
- ECOBA fee schedule
- ECOBA plan examination and inspection policy
- County Health Department: wells, septic and point of sale
- 2026 environmental health fees
- Tuscarawas Soil and Water Conservation District
- BBS building department look-up
- Ohio Construction Industry Licensing Board
Inspections are where schedules slip.
Get a free quote →Tuscarawas County building permit FAQs
Does Tuscarawas County have a building department?
No. The County Planning Commission’s October 21, 2026 letter says the county government has no building or zoning department and no county zoning resolution.
Who approves commercial buildings?
ECOBA, 339 Oxford Street, Dover (330-364-3164), everywhere except Barnhill, Port Washington and Roswell, where the state’s office in Canton does.
Does ECOBA review houses?
No. Detached one-, two- and three-family homes are outside its jurisdiction, though they must still meet the Residential Code of Ohio.
Which townships issue their own zoning and building permits?
Dover, Sandy and Lawrence townships, each with its own zoning and building inspector, according to the county letter.
How much does a new septic system permit cost?
$425 for the site review and $774 for the installation permit under the Health Department’s 2026 fees.
Do I need a well and septic inspection to sell a house?
Yes, unless the transfer is exempt: the system must be evaluated and a certificate of transfer issued before the sale closes.
Who handles plumbing permits?
The state keeps plumbing jurisdiction in all of Tuscarawas County; ECOBA’s certification excludes plumbing.
What does a county driveway permit cost?
$20 for a new drive onto a county road, under the County Engineer’s fees effective July 22, 2026.
Simplify Tuscarawas County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Tuscarawas County sooner?
Let Alliance prepare, file, and track your Tuscarawas County permits while your crew stays on the job.
More Ohio permitting guides
Dover
Read guide →New Philadelphia
Read guide →Coshocton County
Read guide →Twinsburg Building Permit Guide
Read guide →Union County Building Permit Guide
Read guide →University Heights Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Tuscarawas County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.