To get a building permit in New Philadelphia, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

New Philadelphia’s Service Director’s Office at 150 East High Avenue issues the city’s building, zoning, demolition and right-of-way permits online, in person or by mail, and approval takes about 10 to 14 business days.

Authority: New Philadelphia Service Director’s OfficeCommercial: ECOBA plan approval firstPhone: 330-364-4491
New house
$125Duplex $160 · triplex $300
Approval time
10–14 business daysPay when you apply
Sheds, fences, decks
$50 each projectPools $100
Commercial
ECOBA firstCity permit $350 new build

In New Philadelphia, the Tuscarawas County seat, building and zoning permits come from the Service Director’s Office in the John Knisely Municipal Centre, 150 East High Avenue, Suite 200 (330-364-4491). Applications are filed online, at the counter or by mail, must be paid when submitted, and take about 10 to 14 business days to approve. A new single-family house permit is $125, and sheds, fences, decks and other accessory projects are $50 each. Every commercial improvement needs approval from the East Central Ohio Building Authority before the city permit is issued.

What requires a building permit in New Philadelphia?

The city puts the duty on the owner: property owners are responsible for obtaining all permits, and no work should be scheduled until the permit has been approved. The Service Director’s Office issues these building permits:

  • New residential construction: single-family houses, duplexes, triplexes and rowhouses
  • Residential accessory and upgrade permits: sheds, garages, carports, additions, decks and porches, fences, swimming pools, and concrete driveways, patios, sidewalks and curb cuts
  • New commercial construction and multi-family buildings of four or more units
  • Commercial upgrades: additions, garages, decking, fences, parking lots, sidewalks, driveways and curbs
  • Demolition of residential and commercial buildings
  • Certificates of zoning compliance for a new business or one that moves
  • Excavation and communication right-of-way permits, signage permits, lot splits and combinations, and flood hazard development permits
  • SWPPP permits for soil disturbance of 0.1 acre or more

Each residential permit is checked against the zoning district’s lot coverage and setback limits, and an application that exceeds them is not approved. Concrete counts toward lot coverage, so the form asks for the size of existing driveways, patios and walks as well as the new work.

What New Philadelphia decides and what the state holds

Construction standards come from the statewide codes, and commercial code review is done by ECOBA. The city sets the zoning, fees and local rules: the Planning and Zoning Code adopted in 2024, the flood damage prevention rules in Section 1329.03, stormwater Ordinances 948 and 949 from 2017, contractor licensing for water and sewer work, and the Harry Clever Field airport hazard zone. On October 26, 2026 City Council passed Amended Ordinance 18-2026, which creates a Downtown Historic District and adds Section 1102.04(d)(4) to the zoning code, giving the Design Review Board guidelines for preserving downtown buildings and for the design of new ones. Violations are treated as zoning violations, and the board may waive a standard where meeting it would be an unreasonable economic burden.

New Philadelphia building department: who handles permitting

The Service Director’s Office, under Service Director Ron McAbier, issues the city’s permits and licenses and coordinates construction projects and development plans; its Code Administrator reviews applications against the zoning code. For commercial work the city defers to the East Central Ohio Building Authority, which has been certified to enforce the Ohio Building Code in New Philadelphia since January 11, 2005.

Short on time to read all of this?

Get a free quote →
New Philadelphia permit contacts
OfficeContact
Service Director’s Office (building and zoning permits)150 East High Avenue, Suite 200, New Philadelphia, OH 44663; 330-364-4491, ext. 1275
Online permits and paymentCity Form Center, Building Permits and Stormwater Management categories
Water Office (meters, demolition shut-offs)330-364-4491, ext. 1211
City Health Department, Environmental Health (septic, private wells)150 East High Avenue; 330-364-4491, ext. 1206; office hours 8:00 a.m. to 4:30 p.m.
East Central Ohio Building Authority (commercial plans and inspections)339 Oxford Street, Dover, OH 44622; 330-364-3164
Stormwater plan reviewDiversified Engineering Inc. for the city, 175 Ray Ave NE, New Philadelphia

ECOBA states that detached one-, two- and three-family homes are outside its jurisdiction; for houses, the Board of Building Standards look-up map shows which certified department, if any, covers each address.

New Philadelphia permit types

The city takes applications three ways: through its online Form Center, which also collects payment; in person at Suite 200 of the Municipal Centre; or by mail to the Service Director’s Office. Printable versions of each application are posted for paper filing, with checks payable to the City of New Philadelphia.

Residential permits

A new house application asks for the parcel number from the county auditor’s site, the zoning district, project cost, size and height, the general contractor and the water and sewer contractor, and uploaded plans with every setback from the property lines marked. A water application goes in with every new house, the water and wastewater superintendents sign off on the paper form, and the finished house must display its number under Section 907.03. Upgrade permits cover sheds, garages, carports, additions, decks, porches, fences, pools and concrete work, and one application can include several projects, each paying its own fee. Pools need a fence at least 4 feet high with a locking gate that opens from the inside; above-ground pool walls can form part of that fence. The city does not mark property lines, so hire a surveyor if you are unsure where a fence may go. Residential projects must be finished within one year of approval, or a new permit is needed.

Commercial permits

All improvements to commercial property need ECOBA approval before the city building permit is applied for. The city form asks for the ECOBA number, or a signed statement that ECOBA said no permit is needed, plus architect or engineer details, lot coverage and setbacks. The online form says commercial projects must be finished within one year of approval, while the printable form says two years; confirm which applies when your permit is issued. A new or relocated business also needs a $50 certificate of zoning compliance, because Section 1103.12 forbids using or occupying a new or changed building until the Director of Public Service has issued one.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Stormwater. Disturbing 0.1 acre or more needs an approved stormwater pollution prevention plan before building or zoning permits: an abbreviated plan under 1 acre (including new homes, additions and accessory buildings), and a full plan plus a comprehensive stormwater management plan, after a pre-application meeting, at 1 acre or more.
  • Floodplain. If the residential form’s flood zone box is checked, a flood study may be required, and building in a special flood hazard area needs a $100 development permit with certified elevations.
  • Downtown. Exterior work and new buildings in the new Downtown Historic District follow the Design Review Board’s guidelines.
  • Zoning relief. If the Code Administrator rejects an application, the owner may go to the Board of Zoning Appeals for $100 but must show a hardship.

New Philadelphia permit costs and fees

Fees are printed on the city’s own application forms, and every one is non-refundable under Section 1309.04(a). Applications are not reviewed until the fee is paid.

New Philadelphia permit fees (city application forms)
PermitFee
New single-family house / duplex / triplex$125 / $160 / $300
Rowhouse$100 per unit
Residential structure: addition, garage, shed, deck or porch, carport$50
Residential fence / concrete (driveway, patio, sidewalk, curb cut)$50 / $50
Residential swimming pool$100
New commercial building$350
Multi-family (4 or more units)$100 per unit
Commercial addition to the main building$250
Commercial upgrade: fence, garage, decking or hard surface$50
Demolition$75 residential; $150 commercial
Certificate of zoning compliance$50
Flood hazard area development permit$100 filing fee
Board of Zoning Appeals hearing after a rejection$100
Stormwater plan review (SWP3 and CSMP)$1,500, covering one resubmittal; $500 each further submittal
City stormwater site inspection$150 each

Rather talk it over?

Call 1-855-478-4290 →

Water taps are priced on the Service Director’s tap fee sheet dated June 8, 2022: a 3/4-inch service tap is $1,550, or $2,100 to $2,170 in all with the meter, horn and reader; a 1-inch tap is $1,650 ($2,270 to $2,350 in all) and a 2-inch tap $2,650 ($4,400 to $4,750). Taps outside the city add $500, or $750 for 2 inches, and the city needs two weeks’ notice to schedule one. Commercial projects pay ECOBA’s plan review and inspection fees on top of the city permit.

Worked example. The online upgrade form counts each project separately: a homeowner building a fence and a shed enters a quantity of 2 and pays 2 × $50 = $100.

Trade permits and who may pull them

The city licenses two kinds of contractors: tree trimmers, and the water and sewer contractors who connect buildings to city utilities. Each must post a $1,000 performance bond and proof of insurance, and the building forms remind applicants that the water and sewer contractor must hold a city license before working, under Section 1313.01. Licenses can be applied for online or on paper.

  • Commercial electrical, mechanical and fire protection work is reviewed and inspected by ECOBA as part of its plan approval.
  • Plumbing in Tuscarawas County communities remains under the state, according to ECOBA, which excludes plumbing from its certification; plumbing plans go to the Ohio Department of Commerce’s Division of Industrial Compliance.
  • State licenses: commercial electrical, HVAC, hydronics, plumbing and refrigeration contractors need an Ohio Construction Industry Licensing Board license.

The city makes the property owner responsible for obtaining permits, and its forms ask the owner to name the general contractor and the water and sewer contractor. No other city contractor registration appears among its permits.

How to apply for a New Philadelphia building permit

1. Look up the parcel

Find the parcel number and zoning district on the county auditor’s site and the city zoning map.

2. Check stormwater and flood rules

If you will disturb 0.1 acre or more, get the SWPPP approved first; check whether the lot is in a flood zone.

3. Commercial: get ECOBA approval

Commercial improvements need ECOBA plan approval, or ECOBA’s word that none is required, before the city permit.

4. Prepare the site sketch

Show the improvements, their sizes and setbacks, and existing concrete for the lot coverage figure.

5. Apply and pay

File through the Form Center, at Suite 200 or by mail, paying the fee with the application.

6. Wait for approval

Allow about 10 to 14 business days, and do not schedule work until the permit is approved.

Rather not deal with the building department?

Get a free quote →

Review, corrections and what causes delay

An unpaid application is not reviewed at all. The residential form warns that a project exceeding the district’s lot coverage or missing a setback will not be approved; the route then is a Board of Zoning Appeals hearing, which costs $100 and requires proof of hardship. Stormwater plans start review only after every document and the $1,500 fee are in, and each round of corrections after the first costs $500. Commercial projects also wait for ECOBA, which reviews small jobs on the day of a scheduled appointment in most cases and larger ones in up to two business weeks.

Inspections in New Philadelphia

Commercial construction is inspected by ECOBA: book each inspection at least a day ahead through its online request form or with the inspector, post the approved drawings on site, and expect a re-inspection fee if the work is not ready. ECOBA issues the certificate of occupancy once the completed inspection log reaches its building official.

  • Stormwater sites: the city and its engineer visit at least monthly and bill $150 per visit; the permit holder must also inspect its own controls every 7 days and after more than 0.5 inch of rain in 24 hours.
  • Demolition: start within six months of approval and keep working until finished; have the Water Office remove the meter and disconnect service first, and cap any exposed sewer line.
  • Right-of-way excavation: finish within six months, keep barricades up and make permanent repairs within two months.
  • Floodplain projects: provide certified as-built elevations from a registered engineer or surveyor.

For residential permits, ask the Service Director’s Office (330-364-4491, ext. 1275) which site visits apply; new houses also need the water and wastewater superintendents’ sign-off on the utility connections.

Ohio building code in New Philadelphia

ECOBA enforces the Ohio Building Code for commercial buildings in the city, and plumbing review stays with the state. FEMA’s Community Status Book lists the City of New Philadelphia (community 390545) as participating in the National Flood Insurance Program, with a current flood map dated July 22, 2010; the city’s flood damage prevention rules are in Section 1329.03.

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

New Philadelphia permit search and official resources

There is no public online permit search. For permit history on a property, contact the Service Director’s Office, or file a public records request through the city’s Form Center, which has a records request category. City ordinances and resolutions are posted by year, and the complete Codified Ordinances are available as one document.

Want this handled start to finish?

Get a free quote →

Inspections are where schedules slip.

Get a free quote →

New Philadelphia building permit FAQs

How much is a permit for a new house in New Philadelphia?

$125 for a single-family house, $160 for a duplex and $300 for a triplex, paid with the application.

How long does approval take?

About 10 to 14 business days, and the city asks that no work be scheduled until the permit is approved.

Do I need a permit for a fence, shed or driveway?

Yes. Fences, sheds, garages, decks, carports and concrete work each need a $50 residential upgrade permit.

What are the pool rules?

A $100 permit, and a fence at least 4 feet high with a locking gate that opens from the inside; above-ground pool walls can count as the fence.

Who approves commercial projects?

The East Central Ohio Building Authority (330-364-3164) first, then the city for its $350 new commercial permit or upgrade permit.

Which contractors need a city license?

Tree trimmers and water and sewer contractors, each with a $1,000 performance bond and proof of insurance.

Is there a historic district downtown?

Yes. Amended Ordinance 18-2026, passed October 26, 2026, created a Downtown Historic District with Design Review Board guidelines.

Who handles septic systems and wells in the city?

The New Philadelphia City Health Department’s environmental health staff, at 330-364-4491, ext. 1206.

Simplify New Philadelphia permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in New Philadelphia sooner?

Let Alliance prepare, file, and track your New Philadelphia permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about New Philadelphia permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.