Skip to main content
Municipal GuideOhioTuscarawas County · Dover

Dover, Ohio Building Permit Guide

To get a building permit in Dover, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Dover’s Building and Zoning Department on North Wooster Avenue approves every building project in the city, from houses and garages to pools and fences, while commercial plans also go to the East Central Ohio Building Authority on Oxford Street.

Authority: Dover Building & Zoning DepartmentCommercial: East Central Ohio Building AuthorityPhone: 330-343-6740
City office
321 N. Wooster Ave.Mon–Fri 8:00–4:30
Home permit
$25 or $50Up to / over $5,000 of work
Commercial city permit
$125 to $500Plus ECOBA plan approval
Trade contractors
Yearly registrationElectrical, plumbing, HVAC, roofing

In Dover, the Tuscarawas County city, the Building and Zoning Department at 321 North Wooster Avenue (330-343-6740) must approve any building project, including new homes and commercial buildings, additions and renovations, garages, sheds, pools and fences, and it enforces the city’s zoning rules. A residential permit costs $25 for work up to $5,000 and $50 above that. Commercial projects need plan approval and inspections from the East Central Ohio Building Authority (ECOBA), the certified commercial department at 339 Oxford Street (330-364-3164), and electrical, plumbing, HVAC and roofing businesses register with the city every year.

What requires a building permit in Dover?

The city’s rule is broad. Dover residents must apply for and receive approval for any building project, and the department lists the usual ones: new housing and commercial building starts, additions and renovations, accessory buildings such as garages and sheds, swimming pools and fences. Its FAQ adds that exterior improvements count too, naming siding and replacement windows, along with decks and storage barns.

City approval needed

  • New houses and commercial buildings
  • Additions and renovations
  • Garages, sheds and storage barns
  • Decks
  • Siding and replacement windows
  • Swimming pools, above or below ground
  • Fences
  • Advertising signs

Outside ECOBA’s plan review

  • Detached one-, two- and three-family homes under four stories
  • One-story detached accessory buildings under 120 sq ft
  • Agricultural buildings
  • Sidewalks and driveways, unless raised 30 inches or part of an accessible route
  • Ordinary maintenance and minor repairs

The right-hand list is ECOBA’s, not the city’s: it shows what the commercial building department does not review, and those projects may still need a Dover permit. On commercial buildings, ECOBA requires plan approval for re-roofing when at least 100 square feet is replaced or recovered or the roofing material changes, and for fences over 7 feet, retaining walls over 4 feet, signs, towers and pools.

What Dover decides and what the state holds

The building codes are statewide. The city’s own page reminds owners that the Residential Code of Ohio is a legal requirement for anyone who builds, alters, adds to, repairs or replaces parts or equipment of a house. What Dover controls is zoning: area and use requirements for residential and commercial lots, setbacks, lot coverage, fence and pool placement and signs. The FAQ notes a newer ordinance that bans pole signs and billboards; ground and wall signs are preferred.

Dover building department: who handles permitting

Two offices share the work. The city’s Building and Zoning Department, headed by Building and Zoning Codes Administrator John McFadden, issues Dover’s building and zoning permits and answers questions on any project in or around a home. Commercial and industrial buildings also need the East Central Ohio Building Authority, which the Board of Building Standards certified to enforce the Ohio Building Code in Dover from January 11, 2005. Its Chief Building Official and Plans Examiner is Nicholas L. Montan.

Short on time to read all of this?

Get a free quote →
Dover permit contacts
OfficeContact
Dover Building and Zoning Department321 North Wooster Avenue, Dover, OH 44622; 330-343-6740
City Hall hours and main lineMonday to Friday, 8:00 a.m. to 4:30 p.m.; 330-343-6726
Service Director’s Office (Planning Commission questions)330-343-6725
East Central Ohio Building Authority (commercial)339 Oxford Street, Dover, OH 44622; 330-364-3164 (city page: ext. 3, then ext. 1); fax 330-364-4690
Plumbing in Tuscarawas CountyOhio Department of Commerce, Division of Industrial Compliance, Plumbing Section: 800-523-3581, ext. 2 (inspections ext. 1), per ECOBA

Land around the city in Dover Township is not city territory: the township has its own zoning and building inspector (330-343-6413), according to the Tuscarawas County Planning Commission’s October 21, 2026 letter. For which certified department, if any, covers one-, two- and three-family work at a Dover address, check the Board of Building Standards look-up map or ask the department.

Dover permit types

Dover’s permits are handled by the Building and Zoning Department at its North Wooster Avenue office. Most residential permits need a footprint sketch showing where the work sits on the lot, its distances from the property lines and the dimensions used to figure lot coverage, so staff can tell whether the project needs a variance from the Board of Zoning Appeals. Siding and window replacements are the exception and need no sketch.

Residential permits

  • Swimming pools: at least 10 feet from the rear property line, 10 feet from the house and 7 feet from the nearest side lot line, never under overhead lines, enclosed by a fence at least 4 feet high with a lock and gate. A rigid-sided above-ground pool at least 4 feet tall may have the fence requirement waived. The pool counts toward lot coverage as an accessory use.
  • Fences: up to 6 feet in a rear yard and 3 feet in a front yard, with tighter limits on corner lots for visibility. A fence may enclose the whole property and may sit on the line, but the owner must find the property pins or have the lot surveyed; the city suggests leaving a mower’s width so both sides can be maintained.
  • Additions, decks, garages, sheds and storage barns: footprint sketch with setbacks and lot coverage.
  • Siding and replacement windows: permit required, no sketch.

Commercial permits

Commercial work takes two tracks: the city’s commercial building permit and sign permits for zoning, and ECOBA’s plan approval for code compliance. ECOBA wants construction documents prepared, sealed, signed and dated by a registered design professional, uploaded with its Application for Plan Approval and fee worksheet to an online Box folder it provides. Plumbing plans go separately to the state Division of Industrial Compliance with that office’s own application and fee.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning check. The department reviews area and use requirements on every application; a project that breaks a setback or lot coverage limit needs a Board of Zoning Appeals variance first.
  • Planning Commission. Rezonings, annexations, street and alley vacations, subdivisions and developments go to the seven-member Planning Commission, which also approves lot splits and site plans. It meets at 10:00 a.m. on the second Tuesday of the month in Council Chambers when there are agenda items; rezonings start with the city’s Application for Zoning Change and go on to City Council.
  • Floodplain. Dover takes part in the National Flood Insurance Program; ask the department whether a parcel lies in a mapped flood hazard area before designing.
  • Commercial plan approval. ECOBA approval is needed before construction of any commercial building or alteration within its scope.

Dover permit costs and fees

The city’s fees below are the ones its Building and Zoning FAQ publishes; the page carries no date and the adopting ordinance sits in the Codified Ordinances, so confirm the amount when you apply. ECOBA charges its own fees for commercial plan review and inspection under its posted schedule, which is dated effective November 1, 2017.

Dover city permit fees (Building & Zoning FAQ)
PermitFee
Residential permit, work valued up to $5,000$25
Residential permit, work valued over $5,000$50
Commercial building permit$125, plus $10 for every $10,000 of value over $10,000, capped at $500
Swimming pool$50
Fence$25; $15 if the fence costs under $500
Advertising sign$50, with a sketch

Rather talk it over?

Call 1-855-478-4290 →
ECOBA commercial fees (schedule effective 11/01/2017)
ItemProcessing + plan exam and inspection
Structural$275 + $10.50 per 100 sq ft
Mechanical / electrical / fire suppression$275 + $6.50 per 100 sq ft each
Fire alarm$275 + $6.50 per device
Roof replacement$275 + $1.75 per 100 sq ft
Re-inspection penalty / certificate of occupancy$150 / $75
Working without plan approval200% of the plan approval fee

Worked example (city permit). A commercial project valued at $60,000 is $50,000 over the first $10,000, so the city fee is $125 + 5 × $10 = $175. ECOBA’s plan approval fees for the same job are charged separately and are based on the floor area affected, which may extend beyond the limits of construction. ECOBA takes plan approval fees at application, inspection fees before the inspection, and payment by cash, check or major card; a 25% late fee applies after 45 days.

Trade permits and who may pull them

Dover requires every business working in the electrical, plumbing, HVAC and roofing trades to obtain a yearly registration to work in the city, and also to obtain zoning certificates for the work it performs. Ask the Building and Zoning Department for the registration form and fee before the first job of the year.

  • Commercial electrical and mechanical work is reviewed and inspected by ECOBA as part of the plan approval, with separate fees for structural, mechanical, electrical, fire suppression and fire alarm work.
  • Plumbing in every Tuscarawas County community stays with the state: ECOBA’s certification excludes the plumbing provisions, and plumbing plans and inspections go to the Ohio Department of Commerce’s Division of Industrial Compliance.
  • State licenses: commercial electrical, HVAC, hydronics, plumbing and refrigeration contractors need an Ohio Construction Industry Licensing Board license in addition to the city registration.

The registration rule is written for businesses in the trades. An owner planning to do his or her own electrical, plumbing or roofing work should ask the department before buying materials, keeping in mind the city’s reminder that every repair or replacement of house components must still meet the residential code.

Rather not deal with the building department?

Get a free quote →

How to apply for a Dover building permit

1. Confirm it is a Dover address

Make sure the parcel is inside city limits; Dover Township and other surrounding areas have their own offices.

2. Call the department

Describe the project to the Building and Zoning Department at 330-343-6740 to learn which permits and sketches it needs.

3. Draw the footprint sketch

Show the work on the lot with setbacks and lot coverage; siding and windows are the only jobs that skip it.

4. Handle zoning issues first

If the sketch shows a setback or coverage problem, apply to the Board of Zoning Appeals before the permit.

5. Commercial: get ECOBA plan approval

Book a plan exam with ECOBA, upload sealed plans to its Box folder and pay its fees; send plumbing plans to the state.

6. Pay the city fee

Pay the residential or commercial permit fee; on a commercial job, ECOBA’s certificate of plan approval must stay posted on site.

Review, corrections and what causes delay

For commercial plans, ECOBA asks applicants to schedule a plan exam appointment one to two business days ahead. Small projects, roughly eight sheets or up to $500,000, are usually reviewed the same day as the appointment; larger ones may take two business weeks. Plans that cannot be approved as submitted may get a conditional approval for minor or interpretive issues, and approved plans can be downloaded only after all fees are paid. On the city side, a footprint sketch that shows a setback or lot coverage conflict sends the project to the Board of Zoning Appeals, and anything needing a rezoning waits for the Planning Commission’s monthly meeting and City Council.

Inspections in Dover

ECOBA inspects commercial work in Dover. Inspections must be requested at least one day ahead through its online inspection request form or by contacting the inspector, and on inspection day the approved drawings must be posted, lot lines clearly marked and the site accessible. Missing a scheduled inspection, blocking access or calling for work that is not finished brings a $150 re-inspection penalty. When every inspection is signed off, send the completed inspection log to the building official to receive the certificate of occupancy ($75); owners of existing buildings can also ask ECOBA in writing for a certificate of occupancy for a use that has long been in place.

For residential permits, ask the Building and Zoning Department at 330-343-6740 which site checks apply to your project; pool fences, setbacks and fence heights are the details its FAQ stresses. Plumbing inspections are requested from the state’s Division of Industrial Compliance.

Ohio building code in Dover

ECOBA enforces the Ohio Building Code for commercial and industrial buildings in Dover, and the city reminds homeowners that the Residential Code of Ohio applies to their projects. FEMA’s Community Status Book lists the City of Dover (community 390543) as participating in the National Flood Insurance Program, with a current flood map dated July 22, 2010.

Want this handled start to finish?

Get a free quote →

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Dover permit search and official resources

Dover does not post an online permit search. Ask the Building and Zoning Department at 330-343-6740 about city permits on a property, and ECOBA at 330-364-3164 about commercial plan approvals and certificates of occupancy, including replacement copies of approved stamped plans ($100). The city posts its zoning map and City Council agendas and minutes, and links its Codified Ordinances from the Building and Zoning page.

Inspections are where schedules slip.

Get a free quote →

Dover building permit FAQs

How much is a residential building permit in Dover?

$25 for work valued up to $5,000 and $50 above that, according to the city’s Building and Zoning FAQ.

Do I need a permit for siding or new windows?

Yes. The city lists siding and replacement windows among the improvements that need a permit, though they need no footprint sketch.

Who reviews commercial projects in Dover?

The East Central Ohio Building Authority at 339 Oxford Street (330-364-3164), in addition to the city’s own commercial permit.

How far must a pool be from the property line?

At least 10 feet from the rear line, 10 feet from the house and 7 feet from the nearest side line, with a 4-foot fence and locking gate.

How tall can a fence be?

Up to 6 feet in a rear yard and 3 feet in a front yard; the permit is $25, or $15 for a fence costing under $500.

Do contractors register with the city?

Electrical, plumbing, HVAC and roofing businesses need a yearly city registration and zoning certificates for their work.

Who handles plumbing permits?

The state Division of Industrial Compliance keeps plumbing jurisdiction throughout Tuscarawas County, ECOBA says.

When does the Planning Commission meet?

At 10:00 a.m. on the second Tuesday of each month in Council Chambers, 321 North Wooster Avenue, when there are agenda items.

Simplify Dover permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Dover sooner?

Let Alliance prepare, file, and track your Dover permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Dover permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.