Morgan County, Ohio Building Permit Guide

To get a building permit in Morgan County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Commercial building work in Morgan County goes to the Mid-East Ohio Building Department in Zanesville, or to the Southeast Ohio Building Department for McConnelsville, while the County Engineer in McConnelsville runs floodplain permits.

Authority: Mid-East Ohio Building Department (commercial)Floodplain: Morgan County EngineerPhone: 740-455-7905
Commercial
Mid-East Ohio Building DeptMcConnelsville: Southeast Ohio
Houses
No county building departmentFloodplain, septic, driveway permits
Floodplain permit
$200 + $50 inspectionNew structures, from Feb 1, 2024
Zoning
Villages onlyPlus some subdivisions

Morgan County has no building department of its own. Commercial buildings in the townships and in Chesterhill, Malta and Stockport are approved and inspected by the Mid-East Ohio Building Department (22 North 5th Street, Zanesville, 740-455-7905), which states it has no authority over one-, two- or three-family homes; McConnelsville is listed under the Southeast Ohio Building Department in Marietta. For land development the County Engineer names three required permits: floodplain, sewage disposal and driveway. A new structure in a mapped flood zone costs $200 plus a refundable $50 inspection fee.

What requires a building permit in Morgan County?

The answer splits by building type. Commercial, industrial and public buildings, and homes of four or more units, follow the Ohio Building Code, and the Mid-East Ohio Building Department requires a plan approval for new construction, additions, alterations or a change of use on commercial property anywhere in its part of the county. For houses, the County Engineer’s development page says development “at this time” needs permits in three areas only: floodplain, sewage disposal and driveway.

Permits the county and its partners issue

  • Commercial plan approval and inspections (Mid-East Ohio, or Southeast Ohio in McConnelsville)
  • Floodplain development permit for new buildings, additions, fill, grading, paving, tanks, fences and electrical service in a mapped flood area
  • Sewage disposal permit for a home septic system (health department)
  • Driveway permit from the County Highway Department, or from ODOT on state routes
  • Lot split review by the Engineer and Planning Commission

No floodplain permit needed

  • Replacing a septic system or well (health department approval still needed)
  • Normal maintenance under $1,000, such as roof, siding, window, HVAC or plumbing repairs
  • Movable temporary structures used 6 to 8 months a year, such as tents, floating docks and campers
  • Landscaping, gardens, agriculture, land clearing and tree work

Separately, the Engineer’s March 2024 floodplain notice reminds owners that every new building over 100 square feet, even one on skids, needs a “building permit” so the County Auditor can assess it, and warns that the Auditor can reach back five years. The Auditor’s matching form is the Notice of Building Improvement or New Construction, which cites the state duty to report new buildings and improvements and a 50% penalty assessment for failing to do so.

What Morgan County decides and what the state holds

The building codes are statewide and are enforced only by departments the Ohio Board of Building Standards certifies; Morgan County uses two neighboring regional departments for commercial work rather than running one. The county itself decides its flood damage reduction regulations (most recently updated by Resolution 23-549), its floodplain and lot-split fees, its subdivision regulations, adopted by the Commissioners on December 6, 2004, and its driveway rules on county roads. It has no county zoning: the Engineer says zoning applies only inside the villages and in subdivisions that adopted their own rules.

Short on time to read all of this?

Get a free quote →

Morgan County building department: who handles permitting

Use the table to match your address and project to an office. The Mid-East Ohio Building Department is run by Muskingum County and serves six counties; the Southeast Ohio Building Department is run by Washington County. Both are certified for commercial work, and neither takes zoning questions.

Morgan County permit offices
Place or taskOfficeContact
Commercial work in the townships, Chesterhill, Malta and StockportMid-East Ohio Building Department (Chief Building Official Jason R. Baughman, PE)22 North 5th Street, Zanesville; 740-455-7905; Monday to Friday 8:00 a.m. to 4:30 p.m.
Commercial work in McConnelsvilleSoutheast Ohio Building Department (per the Mid-East Ohio list)340 Muskingum Drive, Marietta; 740-374-4185; Monday to Thursday 7:00 a.m. to 4:15 p.m., Friday to noon
Floodplain permits, lot splits, county roadsMorgan County Engineer (also Floodplain Administrator)155 East Main Street, Room 208, McConnelsville; 740-962-3171
Driveways on county roadsMorgan County Highway Department740-962-2041
Home septic systems; commercial plumbingMorgan County Health Department740-962-4572
ZoningEach village (and subdivisions with their own rules)McConnelsville 740-962-3163; Malta 740-962-4971; Chesterhill 740-554-6994; Stockport 740-559-2411

The two departments’ own lists differ slightly: the Mid-East Ohio list (revised October 24, 2024) assigns McConnelsville to the Southeast Ohio department, while Southeast Ohio’s posted 2023 jurisdiction list has no Morgan County column, although its 2025 application names Morgan among the counties it serves. For a McConnelsville commercial job, call both before you file. The Board of Building Standards’ building-department look-up shows the authority for each address on a map.

Morgan County permit types

Most permits here are site permits rather than building permits. Commercial plan approval is the exception, and it goes through a regional department in a neighboring county.

Residential permits

Neither regional department has authority over one-, two- or three-family homes, and the county’s pages describe no residential building department. Under Ohio law, where no department certified for residential buildings has jurisdiction, the owner is not required to submit plans for a house. A new home still needs a floodplain determination (and a permit if the lot is in a mapped flood area), a sewage disposal permit from the health department where there is no sewer, a driveway permit, an address, and the Auditor’s improvement notice; inside a village, the village’s zoning approval comes first.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

The Mid-East Ohio Building Department takes building and sign applications online, with a link at the end of each to pay and upload plans, or in person at its Zanesville office. It wants one application per structure, a site plan, and plans by an Ohio-licensed design professional except in limited cases; it reviews submissions the week after they arrive if filed by 4:00 p.m. on Friday and can approve a foundation alone. For McConnelsville, the Southeast Ohio department takes digital drawings through Dropbox or by email, one application per building, and its application fees are not refundable.

What comes before the building permit

  • Floodplain determination. Ask the Engineer’s Office, 2nd floor of the Riecker Building at 155 East Main Street, or use the county’s floodplain parcel viewer. A lot touching the light-blue flood hazard area needs a floodplain development permit for any construction, and nothing permanent may be built between the purple dashed line and the water’s edge.
  • Floodplain application package. A site plan by a licensed surveyor, engineer or architect showing the location, size and height of the work and the 100-year flood elevation, plus construction plans or sketches.
  • Sewage disposal. The health department issues residential septic permits, and a floodplain determination is required before you apply.
  • Driveway. The Morgan County Highway Department issues driveway permits; state routes go through ODOT’s Morgan County office (740-962-4665).
  • Lot splits and subdivisions. Reviewed under the 2004 subdivision regulations, at $100 per new lot.
  • Village zoning in McConnelsville, Malta, Stockport and Chesterhill.

Morgan County permit costs and fees

There is no county building permit fee because there is no county building department. The fees you meet are the County Engineer’s floodplain and lot-split charges, in force since February 1, 2024, and the commercial plan fees of whichever regional department serves the address. Certified departments add the Board of Building Standards assessment, 3% on nonresidential fees; Southeast Ohio prints it as its own line, and Mid-East Ohio’s schedule does not show it, so ask whether it is included.

Rather talk it over?

Call 1-855-478-4290 →
County Engineer fees (from February 1, 2024)
WorkFee
Floodplain permit, new structure (house, mobile home, garage, carport, barn, shed, pavilion, storage container, cabin)$200 plan review + $50 inspection fee, refunded after final inspection
Floodplain permit, other work (renovation over $1,000, additions, foundation repairs, earthwork, retaining walls, fill, paving, propane tanks, electrical service, fences)$100 plan review + $50 inspection fee, refunded after final inspection
Floodplain violation (owner and/or contractor)$300 per day
Lot split$100 per new lot
Starting construction before all required permits$300 penalty
Commercial plan fees
ItemMid-East Ohio (rev. Nov. 2025)Southeast Ohio (rev. Nov. 1, 2025)
Structural$250 + $10.50 per 100 sq ft$275 + $10.00 per 100 sq ft
Electrical$250 + $8.25 per 100 sq ft$275 + $10.00 per 100 sq ft
Mechanical / HVAC$250 + $8.25 per 100 sq ft$275 + $10.00 per 100 sq ft
Re-inspection or field inspection$125$200 per inspection
Work started without approval$500 fineDouble fee, then triple

Worked example from the Mid-East Ohio schedule, which rounds area up to the next 100 square feet: a 2,450 square foot commercial building counts as 2,500, so structural review is $250 plus 25 × $10.50, or $512.50, before the mechanical and electrical fees. Mid-East Ohio also charges $350 for an existing-building certificate of occupancy and $250 for replacing up to three HVAC units; its fees are due with the application and plans are not reviewed until they are paid.

Trade permits and who may pull them

On commercial projects the regional department reviews electrical, mechanical, fire alarm and fire suppression work as part of the plan approval, each with its own fee line, and Southeast Ohio’s contractor sheet notes that state-licensed contractors are required for electrical, mechanical and plumbing work. Those are the OCILB licenses that cover commercial electrical, HVAC, hydronics, plumbing and refrigeration contractors. Neither department’s Morgan County pages mention a local contractor registration.

Rather not deal with the Morgan County building department?

Get a free quote →
  • Plumbing: the Morgan County Health Department posts a commercial plumbing permit and requires a food-service plan review before it approves plumbing plans for a food business.
  • Houses: the county’s pages list no electrical or HVAC permit for one-, two- and three-family homes; in a flood area, new electrical service still needs a floodplain permit.
  • Fire review: Mid-East Ohio notes that its approval does not include fire department approval, which the owner must obtain separately where required.

How to apply for permits in Morgan County

1. Find the parcel on the county GIS

Turn on the flood hazard layers, or ask the Engineer’s Office whether the lot touches a mapped flood area.

2. Check zoning

Inside a village, call the village; in the townships there is no county zoning unless a subdivision has its own rules.

3. File the floodplain application if needed

Attach the surveyor’s or engineer’s site plan with the 100-year flood elevation and pay the plan review and inspection fees.

4. Get septic and driveway permits

Health department for sewage, Highway Department or ODOT for the driveway.

5. Submit commercial plans to the right department

Mid-East Ohio online for most of the county; Southeast Ohio for McConnelsville.

6. Report the finished building

File the Auditor’s Notice of Building Improvement or New Construction.

Review, corrections and what causes delay

A missing floodplain determination holds up the septic permit, and starting before every permit is in hand risks the county’s $300 penalty. On commercial jobs, Mid-East Ohio does not start review until fees are paid and offers no expedited review, so a late Friday filing waits a week; revisions go in through its plan update link. Southeast Ohio lists turnaround of 1 to 14 days for most permits and 30 days at most.

Inspections and certificates in Morgan County

Mid-East Ohio issues a list of required inspections with each approval and needs at least 24 hours’ notice, booked by phone at 740-455-7905 with the plan approval number. Fire alarm, sprinkler, kitchen hood, gas pressure and HVAC systems must be pre-tested before the inspector arrives. Every commercial building should hold a certificate of occupancy, issued once all inspections pass; an existing building without one can apply with a floor plan and the $350 fee. Southeast Ohio schedules inspections at 740-374-4185 at least a day ahead and issues its certificate for a $50 fee.

Floodplain permits carry their own inspections: the $50 inspection fee is returned once the Engineer’s final inspection passes.

Want this handled start to finish?

Get a free quote →

Ohio building code in Morgan County

The Ohio Building Code governs commercial work through the two regional departments. FEMA’s Community Status Book lists unincorporated Morgan County (community 390420) as participating in the National Flood Insurance Program, with flood maps dated September 19, 2012; that county listing covers unincorporated land only.

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Morgan County permit search and official resources

Commercial plan approvals and certificates of occupancy sit with the department that issued them: Mid-East Ohio keeps records from 1996 and answers records requests by business name and address. Floodplain permits and lot splits are kept by the County Engineer, and septic permits by the health department.

Inspections are where schedules slip.

Get a free quote →

Morgan County building permit FAQs

Do I need a building permit for a house in Morgan County?

Neither regional department has authority over one- to three-family homes, and the county lists floodplain, septic and driveway permits as the development permits it requires, plus the Auditor’s improvement notice.

Who approves commercial buildings?

The Mid-East Ohio Building Department in Zanesville for the townships, Chesterhill, Malta and Stockport; the Southeast Ohio Building Department in Marietta for McConnelsville.

How much is a floodplain permit?

$200 plan review plus a $50 inspection fee for a new structure, or $100 plus $50 for other work; the $50 comes back after the final inspection.

Does Morgan County have zoning?

Not at county level. Zoning applies inside the four villages and in subdivisions that adopted their own rules.

Who issues septic permits?

The Morgan County Health Department, at 740-962-4572, after a floodplain determination.

Where do I get a driveway permit?

The Morgan County Highway Department (740-962-2041), or ODOT’s Morgan County office for state route driveways.

Do I have to report a new shed?

The county asks owners to report new buildings over 100 square feet, even on skids, so the Auditor can assess them.

Simplify Morgan County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Morgan County sooner?

Let Alliance prepare, file, and track your Morgan County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Morgan County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.