Noble County uses the Southeast Ohio Building Department (340 Muskingum Drive, Marietta, 740-374-4185), run by Washington County, for commercial building permits; it has served the unincorporated county since October 5, 2007, and covers Caldwell, Batesville, Belle Valley, Dexter City and Summerfield, while Sarahsville is under the state. County resources describe that service as commercial. For a house, the permits that matter are local: a septic permit from the Noble County Health Department, a floodplain permit through the Emergency Management Agency in flood areas, a $25 driveway permit from the County Engineer, and zoning only in Wayne and Buffalo townships, a few other areas and the zoned villages.
What requires a permit in Noble County?
Commercial buildings, industrial work, buildings of four or more units, and accessory structures such as towers, storage tanks, pools and tents are on the Southeast Ohio Building Department’s list of permitted work, along with the structural, mechanical, electrical, re-roofing, fire alarm and fire suppression work inside them. The OSU Extension page that the county Planning Commission links for zoning information describes that department as serving Noble County for commercial permits. Everything else a builder needs comes from county and township offices.
Permits commonly needed
- Commercial plan approval (Southeast Ohio Building Department; the state in Sarahsville)
- Household sewage treatment system permit (health department)
- Private water system permit to drill, alter or seal a well (health department)
- Floodplain building permit in mapped flood areas (Emergency Management Agency)
- Driveway, right-of-way, road bore or tree trimming permit on county and township roads (County Engineer)
- Zoning permit in Wayne and Buffalo townships and in zoned villages
- Lot splits and subdivisions (Regional Planning Commission)
Where no permit office applies
- Zoning in the unincorporated townships other than Wayne and Buffalo, which the health department says are not zoned
- A regional building permit for one-, two- and three-family homes, since county guidance lists that department for commercial permits only
What Noble County decides and what the state holds
The building codes are Ohio’s, and only a department certified by the Board of Building Standards may enforce them; Noble County has been served by Washington County’s department since 2007 rather than running its own. The county decides its driveway and right-of-way fees, set by Commissioners’ Resolution 2023-2-5 and charged since April 1, 2023, its subdivision regulations (the 2024 edition took effect March 1, 2024, and proposed amendments were open for comment until October 28, 2026), and its health department’s septic and well program. Townships decide whether to zone.
Noble County building department: who handles permitting
The Southeast Ohio department’s jurisdiction list (revised June 2023) gives the start date for each place it serves, which helps when tracing older records.
Short on time to read all of this?
Get a free quote →| Place | Authority | Served since |
|---|---|---|
| Unincorporated townships | Southeast Ohio Building Department | October 5, 2007 |
| Village of Caldwell | Southeast Ohio Building Department | January 1, 1992 |
| Belle Valley; Summerfield; Batesville; Dexter City | Southeast Ohio Building Department | January 30, 2015; November 4, 2016; June 20, 2017; May 1, 2020 |
| Village of Sarahsville | State of Ohio, Division of Industrial Compliance (614-644-2223) | – |
| Office | Handles | Contact |
|---|---|---|
| Southeast Ohio Building Department | Commercial plan approval and inspections | 340 Muskingum Drive, Marietta; 740-374-4185; Monday to Thursday 7:00 a.m. to 4:15 p.m., Friday 7:00 a.m. to noon |
| Noble County Health Department | Septic systems, wells, point-of-sale inspections | 44069 Marietta Road, Caldwell; 740-732-4958; Monday 7 a.m. to 6 p.m., Tuesday to Friday 7 a.m. to 4 p.m. |
| Noble County Engineer | Driveway and right-of-way permits; addresses (tax map office) | 46003 Marietta Road, Caldwell; 740-732-4400; tax map 740-732-4941 |
| Noble County EMA | Floodplain building permits | 740-732-7387 |
| Noble County Planning Commission | Lot splits, subdivisions, variances | 740-732-2702; in office Monday, Wednesday and Friday 8 a.m. to 4 p.m. |
| Noble Soil & Water Conservation District | Conservation help | 46049 Marietta Road, Suite 5, Caldwell; 740-732-4318 |
The Board of Building Standards’ building-department look-up maps the authority for each address. The Southeast Ohio list still prints the department’s old 205 Putnam Street address; its current office is on Muskingum Drive.
Noble County permit types
Residential permits
County guidance lists the Southeast Ohio department for commercial permits only, and no county residential building department appears on the county’s pages. Ohio law says that where no department certified for residential buildings has jurisdiction, the owner does not have to submit plans for a house. A new home still needs a five-digit address from the Engineer’s tax map office (required even if no mail goes there), a zoning permit if the township or village is zoned, a floodplain permit if the lot is in a flood area, a septic permit where there is no sewer, a well permit where there is no public water, and a driveway permit. The County Auditor’s zoning sheet tells owners in zoned townships to get the zoning permit before the building permit is purchased.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Southeast Ohio wants one Application for Non-Residential Plan Approval per building or structure, with the parcel number, use group, construction type and cost, and a digital set of drawings (site plan, elevations, floor plans, wall sections and specifications) bearing an Ohio-registered architect’s or engineer’s seal. The form asks whether the site is in a FEMA flood hazard area and whether zoning approval has been granted. The whole process can be done electronically by email or Dropbox, and the department quotes 1 to 14 days for most permits and 30 days at most. It also approves signs on a separate application, and demolition and existing-building certificates of occupancy on their own forms.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. Wayne and Buffalo townships have zoning inspectors, and the auditor’s list adds the Wolf Run Acres area of Noble Township and the Village of Caldwell (Mayor’s office, 740-732-2635, $10 permit); the Noble County Airpark has its own 1967 zoning regulations.
- Floodplain. On a lot in a flood area, the health department’s septic approval depends on a copy of an approved floodplain building permit from the EMA.
- Septic. A soil scientist’s evaluation and a designer’s plan go by email to NobleSTS@odh.ohio.gov before a joint site visit by the county and the Ohio Department of Health.
- Lot splits. The Regional Planning Commission runs a property split application and ag-and-recreation exemption forms under the 2024 subdivision regulations.
Noble County permit costs and fees
Commercial plan fees are the Southeast Ohio Building Department’s, from its fee schedule revised November 1, 2025. Square and linear footage is rounded up to the next 100, the $50 certificate of occupancy or completion fee is added to every total, and the 3% Board of Building Standards surcharge is added on its own line. Application fees are not refundable, even if zoning or floodplain approval later fails.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| Structural | $275 processing + $10.00 per 100 sq ft |
| Mechanical / HVAC; electrical; fire suppression | $275 + $10.00 per 100 sq ft each |
| HVAC direct replacement | $200 electrical field inspection + $200 structural |
| Electrical service / temporary service | $275 / $200 |
| Re-roof, roof replacement or siding | $275 + $5.00 per 100 sq ft |
| Fence over 7 feet / retaining wall (48 inches from bottom of footing) | $275 + $30 / $20 per 100 linear ft |
| Fire alarm | $275 + $10.00 per device |
| Industrialized unit / tent | $275 + $5.00 per 100 sq ft / $100 + $100 inspections |
| Field inspection; partial or phased approval; resubmittal after 2nd revision | $200; $200 each; $100 |
| Certificate of occupancy or completion | $50 |
| Work started without approval | Double fee for a first offense, triple for a second |
Worked example from the schedule: a 3,180 square foot commercial building rounds up to 3,200, so structural review is $275 plus 32 × $10, or $595; adding the $50 certificate gives $645, and the 3% surcharge of $19.35 brings it to $664.35 before mechanical and electrical fees.
| Permit | Fee |
|---|---|
| Driveway (residential) or tree removal / trimming in the right-of-way | $25 |
| Utility installation (standard RUMA) | $50 |
| Commercial driveway (plans required) | $150 |
| Village of Caldwell or Buffalo Township zoning permit | $10 (per the auditor’s list) |
Driveway fees are non-refundable and paid with the application. Septic, well and floodplain fees are set by the health department and the EMA; ask each office for its current amounts.
Trade permits and who may pull them
On commercial projects Southeast Ohio lists the general, electrical, mechanical, plumbing, fire suppression and fire alarm contractors on the application and requires state-licensed contractors for electrical, mechanical and plumbing work; those are the OCILB licenses for commercial electrical, HVAC, hydronics, plumbing and refrigeration contractors. Ohio has no state license for general contractors, and the county’s pages show no county contractor registration.
Rather not deal with the Noble County building department?
Get a free quote →- Plumbing: Southeast Ohio posted residential and non-residential plumbing applications in 2026; its residential form, revised August 17, 2026, charges a $225 processing fee covering plan review and inspections, plus $20 per fixture and $50 for the certificate of completion. Its pages do not say which counties the plumbing program covers, so ask the department whether it applies to your Noble County address.
- Sewage systems: the health department registers installers, service providers and septage haulers, and a homeowner may install their own system after passing the contractor test.
- Wells: drilling, altering or sealing a well needs a registered private water systems contractor, or a homeowner who has registered with the Ohio Department of Health.
- Electrical and HVAC at houses: the county lists no residential permit for these trades.
How to apply for permits in Noble County
Request a five-digit address from the Engineer’s tax map office for a new building site.
Call the township zoning inspector or village if the land is zoned, and the EMA for a floodplain permit if it is mapped.
Hire a soil scientist and designer, email their work to the address the health department lists, then book the joint site evaluation.
Email, fax or mail the Engineer’s 2026 application; ODOT handles state highways.
Send the non-residential application and sealed drawings to Southeast Ohio by email or Dropbox with the fees.
Notify the Engineer (and the township trustee on a township road) before work in the right-of-way, and book building inspections a day ahead.
Review, corrections and what causes delay
On flood-prone lots the floodplain permit gates the septic permit, so a late flood determination stalls the whole house. Commercial applications are reviewed in 1 to 14 days in most cases; a third round of revisions costs $100, and phased approvals cost $200 each. Commercial driveways, utility work, bores and open cuts need plans approved before the Engineer issues the permit, and a pre-construction meeting may be required.
Inspections and certificates in Noble County
Southeast Ohio schedules inspections by phone at 740-374-4185, called in at least one day before you need one. Extra field inspections cost $200, the fee schedule marks which permits include their structural, electrical, plumbing and mechanical inspections, and a final certificate of occupancy is issued for occupied buildings once every inspection has passed.
The health department and the Ohio Department of Health make the final inspection of a new septic system before it is covered, and the health department inspects a new well, reviews the driller’s paperwork and takes a water sample before signing off. For a home sale, the health department offers point-of-sale inspections of septic systems and well certifications.
Want this handled start to finish?
Get a free quote →Ohio building code in Noble County
Commercial work in Noble County is reviewed under the Ohio Building Code by the Southeast Ohio Building Department. FEMA’s Community Status Book lists unincorporated Noble County (community 390428) as participating in the National Flood Insurance Program, with flood maps dated January 6, 2011.
Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Noble County permit search and official resources
For commercial plan approvals and certificates, ask the Southeast Ohio Building Department with the parcel number and address. The health department keeps every permit, inspection and service record for sewage systems in the county, and the Engineer keeps driveway and right-of-way permits. The county’s parcel viewer, auditor and recorder links are on the Engineer’s page.
- Southeast Ohio Building Department
- Southeast Ohio jurisdiction list (June 2023)
- Non-residential plan approval application and fee schedule
- Southeast Ohio application downloads
- Noble County zoning and permit process (OSU Extension)
- Auditor’s list of zoned areas
- Noble County Health Department sewage treatment systems
- Noble County Health Department private water systems
- Noble County Engineer
- Driveway access / right-of-way permit application (2026)
- Noble County Planning Commission
- Noble County subdivision regulations (effective March 1, 2024)
- Ohio Board of Building Standards building-department look-up
Inspections are where schedules slip.
Get a free quote →Noble County permit FAQs
Who issues commercial building permits in Noble County?
The Southeast Ohio Building Department in Marietta, for the townships and five villages; Sarahsville is under the state’s Division of Industrial Compliance.
Do I need a building permit for a house?
County guidance lists the regional department for commercial permits only; a house still needs septic, well, floodplain, driveway and any zoning permits.
Which parts of Noble County are zoned?
Wayne and Buffalo townships, the Wolf Run Acres area of Noble Township, the zoned villages such as Caldwell, and the county airpark; the other unincorporated areas are not zoned.
How much is a driveway permit?
$25 for a residential driveway, $150 for a commercial one, from the County Engineer under Resolution 2023-2-5.
Can I install my own septic system?
Yes, if you pass the contractor test; otherwise a registered installer does the work, and the county and state inspect it before it is covered.
Who handles floodplain permits?
The Noble County Emergency Management Agency, 740-732-7387; in flood areas the septic permit depends on it.
How long does commercial plan review take?
Southeast Ohio quotes 1 to 14 days for most permits and 30 days at most.
Simplify Noble County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Noble County sooner?
Let Alliance prepare, file, and track your Noble County permits while your crew stays on the job.
More Ohio permitting guides
Guernsey County
Read guide →Washington County
Read guide →Monroe County
Read guide →North Canton Building Permit Guide
Read guide →North Olmsted Building Permit Guide
Read guide →North Ridgeville Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Noble County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.