To get a building permit in Monroe County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Building permits for unincorporated Monroe County, Woodsfield and Clarington come from the Southeast Ohio Building Department in Marietta, a regional department that also serves Washington, Noble and Gallia counties; eight smaller villages are listed under state jurisdiction.

Authority: Southeast Ohio Building DepartmentCovers: Townships, Woodsfield, ClaringtonPhone: 740-374-4185
Building office
SEOBD, Marietta340 Muskingum Drive
House fee
$125 + $10 per 100 sq ftEach for building, mechanical, electrical
Review time
1–14 days30 days maximum
Septic permit
$274 new systemMonroe County Health Department

Monroe County, Ohio, does not run its own building department. Since February 5, 2010 the Southeast Ohio Building Department (SEOBD), based at 340 Muskingum Drive in Marietta (740-374-4185), has handled the county’s unincorporated townships, and its jurisdiction list adds the villages of Woodsfield (since 2010) and Clarington (since 2017). The same list places Antioch, Beallsville, Graysville, Jerusalem, Lewisville, Miltonsburg, Stafford and Wilson under the State of Ohio’s jurisdiction. Septic systems and wells are permitted by the Monroe County Health Department in Woodsfield, and county road access by the County Engineer.

What requires a building permit in Monroe County?

Under Ohio law, no one may go ahead with the construction, erection, alteration or equipment of a building until its plans are approved as the law requires. Where SEOBD has jurisdiction, its residential checklist (for one- and two-family homes and townhouses) says a permit is always required for the work below; apartments, condominiums and similar buildings are treated as commercial projects.

Permit required (homes)

  • Additions, garages, carports and finished basements
  • Porches or decks with a floor 16.5 inches or more above finished grade
  • Sheds over 200 square feet; fences over 6 feet, and any pool barrier
  • Retaining walls holding back more than 2 feet of fill, or carrying a load from above
  • Pools or spas holding more than 2 feet of water, over 150 square feet and over 5,000 gallons
  • Structural changes, prefabricated fireplaces, inserts and wood stoves
  • Replacing gas or oil furnaces, gas logs or gas appliances; new electrical circuits, fixtures or receptacles (low voltage excepted)
  • Re-roofing or new siding repairs of 400 square feet or more

No permit (homes)

  • Replacing 100 square feet or less of roof decking (unless it had to be fire-retardant)
  • Sheds of 200 square feet or less
  • Painting and wallpapering, gutters and downspouts, re-glazing
  • Kitchen cabinets; replacing plumbing fixtures without changing the piping; replacing light fixtures

Exempt work must still meet the code. For commercial, industrial and four-plus-family buildings, SEOBD requires permits for structural, mechanical, re-roofing, electrical, fire suppression, fire detection and alarm work and industrialized units, plus accessory structures such as towers, storage tanks, pools and tents.

What Monroe County decides and what the state holds

The building codes and the certification of departments are state matters. In Monroe County, SEOBD serves the unincorporated land, and Woodsfield and Clarington appear on its list with their own start dates. In the eight villages the jurisdiction list places under the state, Ohio law sends nonresidential plans to the state’s Superintendent of Industrial Compliance (SEOBD’s list gives 614-644-2223), and where no certified residential department has jurisdiction a homeowner need not submit house plans. Check the Board of Building Standards look-up map for any address.

Short on time to read all of this?

Get a free quote →

Monroe County building department: who handles permitting

SEOBD reviews plans, issues permits and inspects for the areas it serves in Monroe County, with residential and commercial applications and residential and non-residential plumbing applications on the same page. Its jurisdiction list (revised June 2023) groups the county’s communities as follows. The list does not say whether SEOBD covers residential work, commercial work or both in each place; in Washington County, for example, it is certified for commercial work everywhere but for houses only in Marietta and Belpre. Before planning a house, check the Board of Building Standards look-up or ask SEOBD whether a residential permit applies at the address.

Building code enforcement in Monroe County
AreaWho handles building permits
All unincorporated townshipsSoutheast Ohio Building Department (since February 5, 2010)
Woodsfield (village, county seat)Southeast Ohio Building Department (since June 11, 2010)
Clarington (village)Southeast Ohio Building Department (since July 14, 2017)
Antioch, Beallsville, Graysville, Jerusalem, Lewisville, Miltonsburg, Stafford and Wilson (villages; Wilson is partly in Belmont County)Listed as under the State of Ohio’s jurisdiction, 614-644-2223
Monroe County permit contacts
OfficeContact
Southeast Ohio Building Department340 Muskingum Drive, Marietta, OH 45750; 740-374-4185; Monday–Thursday 7:00 a.m.–4:15 p.m., Friday 7:00 a.m.–noon
Monroe County Health Department (septic, wells)118 Home Avenue, Woodsfield, OH 43793; 740-472-1677; Monday–Friday 8:30 a.m.–4:00 p.m.
Monroe County Engineer (county roads)47134 Moore Ridge Road, Woodsfield; 740-472-2537
Board of County Commissioners101 N. Main Street, Room 34, Woodsfield; 740-472-1341; office open Monday–Friday 8:00 a.m.–4:00 p.m., meetings Mondays at 9:00 a.m.

SEOBD’s department page and its residential plumbing application (revised August 17, 2026) give 340 Muskingum Drive, the address used here; the residential building plan approval application, whose fee pages were revised May 26, 2026, still prints the older address of 205 Putnam Street, Marietta.

Monroe County permit types

SEOBD posts separate applications for residential building plan approval, non-residential plan approval, existing-building certificates of occupancy, demolition, signs, and residential and non-residential plumbing. The residential form has a box to circle Monroe County, and one application is needed for each dwelling unit, building or structure.

Not sure this scope needs a permit?

Get a free quote →

Residential permits

  • Drawings: a site plan with lot dimensions, every structure, easements, setbacks and FEMA flood map data where it applies; a foundation plan; floor plans with room uses, egress windows and framing; exterior elevations; wall sections with insulation values; and an energy analysis. Truss drawings may follow after the permit but must be approved and on site for the framing inspection.
  • Electrical: designers or contractors submit a log-in data form and, where required, a fault current analysis before installing service equipment; review takes three to five days, so send it with the electric application.
  • Footing first: a footing and foundation permit is a partial approval, and building beyond it is at the permit holder’s risk.

Commercial permits

Commercial, industrial and multi-family projects of four or more units use the non-residential application with sealed drawings where required; electrical services over 400 amps need designer drawings. Partial or phased approvals cost $200 each. The application’s contractor list notes that state-licensed contractors are required for electrical, mechanical and plumbing work.

What comes before the building permit

  • Zoning. SEOBD tells owners in a city or village to ask that city or village about zoning, and owners outside one to contact their township trustees.
  • Septic and well. The Health Department reviews sites and designs and issues septic installation and alteration permits, handles new lot splits, inspects wells and offers oil and gas baseline water testing.
  • County roads. Work in a county road right-of-way needs the County Engineer’s access and right-of-way work application, and oversize loads a special haul permit.
  • Flood areas. SEOBD’s own floodplain program covers only Washington County; for unincorporated Monroe County, which participates in the flood insurance program, ask the Commissioners’ office (740-472-1341) who reviews floodplain development.

Monroe County permit costs and fees

SEOBD’s residential fee schedule was revised May 26, 2026 and its non-residential schedule November 1, 2025. Square footage is charged per 100 square feet, and commercial footage is rounded up to the next 100. The state assessment is added: 1% on residential and 3% on non-residential permits. Fees paid up front are not refunded, even if a permit cannot be approved or the job does not go ahead.

Rather talk it over?

Call 1-855-478-4290 →
SEOBD and Monroe County Health Department fees
ItemFee
Residential structural / mechanical / electrical (each)$125 processing plus $10 per 100 sq ft
Residential deck$50 processing plus $10 per 100 sq ft
Residential re-roofing or siding over 400 sq ft / fire suppression or alarms$50 / $100
Residential field inspection / one-time permit renewal$50 / $25
Residential plumbing plan approval (plan review and inspections)$225 plus $20 per fixture; certificate of completion $50
Commercial structural, mechanical or electrical (each)$275 processing plus $10 per 100 sq ft
Commercial re-roof or siding / fence over 7 ft$275 plus $5 per 100 sq ft / $275 plus $30 per 100 linear ft
Commercial fire suppression / fire alarm system$275 plus $10 per 100 sq ft / $275 plus $10 per device
Generator / kitchen hood suppression$100 processing plus $200 each for electrical and structural field inspections
New tower$300 processing plus $200 each for electrical and structural field inspections
Commercial certificate of occupancy / partial approval / third and later resubmittals$50 / $200 / $100 each
Work begun before approvalDouble fee (residential); double, then triple for repeat commercial offenses
Septic site review / design review / new system permit / alteration permit$125 / $125 / $274 / $160 (Health Department, 2024)
Review of subdivision lots / home loan sewage inspection$100 / $75

Worked example from the residential schedule: a 1,600-square-foot new house pays $125 plus 16 × $10, or $285, for each of the structural, mechanical and electrical permits, a total of $855, plus the 1% state assessment ($8.55), before plumbing. A new septic system for the same house adds the Health Department’s $125 site review and $274 installation permit. SEOBD takes checks, money orders and credit or debit cards made payable to the Southeast Ohio Building Department, and fees for situations the schedule does not cover are set by the Building Official.

Trade permits and who may pull them

For the areas SEOBD serves, electrical, mechanical and plumbing permits come from SEOBD on its own applications, and the department charges for each trade separately. The residential application lists electrical, HVAC, plumbing, fire protection, hydronics and refrigeration contractors with their registration numbers.

Rather not deal with the Monroe County building department?

Get a free quote →
  • Licenses: SEOBD’s commercial packet states that state-licensed contractors are required for electrical, mechanical and plumbing work, in line with the Ohio Construction Industry Licensing Board’s licensing of commercial trades. Ohio has no state license for general or residential contractors.
  • Plumbing: residential plumbing plan approval is $225 plus $20 per fixture, with a fixture count sheet covering everything from water heaters to floor drains; ask SEOBD whether it or the Health Department inspects plumbing at your address.
  • Septic installers: installers, service providers and septage haulers register with the Health Department for $150.
  • Electric utility: the application explains how the utility may limit available fault current at a home’s service and when a fault current analysis is needed.

How to apply for a building permit in Monroe County

1. Confirm the jurisdiction

Check SEOBD’s list: townships, Woodsfield and Clarington go to SEOBD; eight villages are listed under the state.

2. Clear zoning locally

Ask the village, or the township trustees outside a village, about zoning.

3. Settle septic and well

File site review and design applications with the Health Department on unsewered lots.

4. Complete the SEOBD application

Circle Monroe County, enter the parcel number and attach the drawings.

5. Submit electronically

Send drawings through SEOBD’s Dropbox submission process, with payment to the Southeast Ohio Building Department.

6. Receive the plan approval

SEOBD sends the approval to the owner by a Dropbox link; keep a set of the approved documents on site.

Review, corrections and what causes delay

SEOBD says most permits take 1 to 14 days, with 30 days as the maximum. Incomplete applications may delay processing. Commercial resubmittals after the second revision cost $100 each, and work begun before approval can double the fee. A residential permit can be renewed once for $25.

Inspections and certificates in Monroe County

Call SEOBD at 740-374-4185 at least one day before you need an inspection; the department posts an inspector’s calendar and separate residential and non-residential inspection lists. Approved documents must be on the job site for every scheduled inspection. When all inspections are complete, SEOBD issues a final certificate of occupancy for an occupied building; commercial certificates of occupancy or completion cost $50, and an existing building can get one through its own application.

The Monroe County Health Department inspects septic systems and wells. Its environmental services page sets out the steps for approval to install, replace or alter a home sewage system on an existing lot, and posts the design, site review, installation and alteration applications, a list of soil scientists and evaluators, the current installer list and the 2026 septage hauler list; new wells use the Ohio Department of Health’s well permit application. Its Board of Health meets on the third Wednesday of each month at 2:30 p.m. at the department. Home loan inspections of a sewage system cost $75, or $125 with the water supply.

Want this handled start to finish?

Get a free quote →

Ohio building code in Monroe County

SEOBD enforces the statewide Ohio codes for the parts of Monroe County it serves. FEMA’s Community Status Book lists unincorporated Monroe County (community 390404) as participating in the National Flood Insurance Program, with current flood maps effective August 19, 2010; villages participate separately.

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Monroe County permit search and official resources

For records of permits SEOBD issued, contact the department in Marietta; the Washington County website that hosts SEOBD’s pages links its public records request page. Health Department permits for septic systems and wells are kept in Woodsfield.

Inspections are where schedules slip.

Get a free quote →

Monroe County building permit FAQs

Who issues building permits in Monroe County, Ohio?

The Southeast Ohio Building Department in Marietta (740-374-4185) for the unincorporated townships, Woodsfield and Clarington.

What about the other villages?

SEOBD’s list places Antioch, Beallsville, Graysville, Jerusalem, Lewisville, Miltonsburg, Stafford and Wilson under the State of Ohio’s jurisdiction (614-644-2223).

Do I need a permit for a shed or deck?

Where SEOBD handles residential work, a shed over 200 square feet needs one, and a deck needs one when its floor is 16.5 inches or more above grade.

How much is a permit for a new house?

$125 plus $10 per 100 square feet for each of the structural, mechanical and electrical permits, plus 1%; about $855 for 1,600 square feet before plumbing.

How long does SEOBD take?

One to 14 days for most permits, 30 days at most.

Who issues septic permits?

The Monroe County Health Department, 118 Home Avenue, Woodsfield (740-472-1677); a new system permit is $274.

How do I book an inspection with SEOBD?

Call 740-374-4185 at least one day ahead, and keep the approved documents on the job site for the inspector.

Do I need a permit to re-roof?

On a home, yes for re-roofing or siding repairs of 400 square feet or more; replacing 100 square feet or less of decking needs none.

Simplify Monroe County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Monroe County sooner?

Let Alliance prepare, file, and track your Monroe County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Monroe County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.